Mass processing

HI,
Is it possible to st the Deletion flag to the process order through mass processing.
Regards,
Amit

Hi ,
Thanks for the reply.
Actuallay in my senario we have a user status NDLF - No deletion Flag.
So in mass processing i want to deactivate the NDLF status and want to activate the DLFL status. we are scheduling background job monthly once to do this activity.
So  i was just trying through COID / COHV / COHVPI. Whether it can possible or not.
But in COID mass processing we can update user status NDLF but we can not update  DLFL deletion flag.
So i need to run 2 different  variant
1 for Removing NDLF stataus through COID and
2 for Updating DLFL status through program .
Do you have any better solution than this.
Regards,
Amit

Similar Messages

  • Mass Processing pop up in BI 7.0

    Dear Experts,
                         I am getting popup window "mass processing" while doing status not ok(RED) for some delta loads in monitor screen(Before going for Repeat delta)
    Here it is asking for :
    " 2 Infoproviders still have to be checked ?
    Interactive or Automatic (without asking for confirmation)?
    Which option i need to select ? What is Interactive & Automatic ? I haven't seen this popup earlier. What could be the reason for this popup screen ? Please suggest how to proceed in this case .
    Thanks & Regards,
    Pcrao.

    Hi,
    One option I thought of, but never applied in practice. Create an excel with all the field related information in the structure of table,
    RSDIOBJ Directory of all InfoObjects
    RSDCHABAS Basic Characteristics (for Characteristics,Time Characteristics, and Units)
    *RSKYF Key Figures
    RSDTIM Time Characteristics
    RSDUNI Units*
    And upload this table with the flat using function module etc.
    But then you would need to update below tables to with relevant details.
    RSDIOBJT Texts of InfoObjects
    RSDIOBJ Directory of all InfoObjects
    RSDIOBJT Texts of InfoObjects
    RSDATRNAV Navigation Attributes
    RSDATRNAVT Navigation Attributes
    RSDBCHATR Master Data Attributes
    RSDCHABAS Basic Characteristics (for Characteristics,Time Characteristics, and Units)
    RSDCHA Characteristics Catalog
    RSDDPA Data Package Characteristic
    RSDIOBJCMP Dependencies of InfoObjects
    RSKYF Key Figures
    RSDTIM Time Characteristics
    RSDUNI Units
    Edited by: Parth Kulkarni on Jun 22, 2011 4:56 PM

  • Mass processing of Workorders-Reg

    Hi,
    We are having standard Tcode COHV for mass Processing of Production Order.
    Like that do we have any tcode for mass processing of Workorder.
    The reason behind is instead of having CO99 for closing the order with only one plant(my requirement is multiple plants and multiple order types) ,Is it possible to use IW38 in Background to change the order from TECO to CLSD.
    Because the option is given in IW38(Menu- Program-Execute in Background).If so how to do that?
    Pl throw some light on this.
    Regards
    KRISHNAN

    Krishnan,
    In my 4.7 A&D IS system, we don't even have a menu path starting with Program in IW72 or
    IW38 (Menu- Program-Execute in Background).
    Only Order > Completion > Complete business, but these programs are designed to release, TECO etc all from within the transaction.
    Additionally, you are not restricted to one plant and one order type in CO99. You can leave these open, you are then only restricted by one Controlling Area.
    Problem with that is that you are not restricted to PM orders, all order types are processed.
    If you are using PM task lists in all your orders, that may work for you as a selection criteria, but that's an unlikely case.
    If not, you should be able to reach an agreement with all internal order type users that all orders should be (financially) closed after n days in state of TECO.
    Most companies are keen not to leave any 'finished' orders open and available to financial postings.
    The usual late postings are differences in invoices and purchase orders. If there are a lot of these it is practical to wait a number of days and then close.
    The errors that occur afterwards can always be processed by reversing the closure.

  • Problem in COHV with mass processing function Release.

    Hello,Guru's
    I have problem in COHV with mass processing function Release.
    even after execution of COHV the status of Orders remains unchanged.i.e. remain Created instead of Release
      My user require all Orders should release in mass process
    with material availability Check .
    and OPJK setting is
    material availability
    Check availability during order release=X
    Release material = 1(User decides on release if parts are missing)

    > with material availability Check .
    > and OPJK setting is
    > material availability
    >  Check availability during order release=X
    > Release material = 1(User decides on release if parts are missing)
    Hi,
    With these two settings in OPJK, there will not be any impact on COHV.
    Any dates, date ranges you are inputing in the COHV.
    Try with Manually inputing some of the Orders in COHV and in the Foreground you try.
    Afterwards, try with Some selected Orders in the Background..
    You may get the clue for the problem..
    Regards,
    Siva

  • Mass processing by T.code COOIS

    Hi,
    How can I execute some mass processing in the T.CODE COOIS and  not only reporting.
    I canu2019t use u201Csettingsu201D and u201Cmass processingu201D in my system. They are deactived. Do I need some customizing.
    Thanks
    Dede

    Hi Glenn,
    Please use COHV - Mass processing by which you can execute the required changes.
    COOIS is purely used to collectively get the desired reports for the discrete production process( production orders, etc)
    Hope this clears your question.
    Thanks & Regards,
    Abhijeet Guha

  • QAC2 in mass processing

    Dear Experts,
    I know the transaction QAC2 for transfering inspection lot qty from plant to plat or storage location to storage location.
    When it is executed for an inspection lot and SL is changed or plant is changed a material document of mvt-323 is generated for each individual posting.
    But is there any transaction for mass processing of this activity and to create only one material document for bulk inspection lots.
    If any one knows about this, please update ASAP
    Regards
    Vivek

    There is no std SAP  T- code available which could process this in Mass .

  • SOP mass processing problem

    Hi All,
    I am working on flexible planning in SOP.. I am trying to transfer the SOP plan to demand management through mass processing function..
    I have done the following...
    I created transfer profile through MC8S
    i created activity through MC8T  and assigned the transfer profile created earlier..
    then created a mass processing job through MC8D and then finally scheduled it... SOP plan is not getting transferred to demand management.
    I am getting the below error...
    When I transfer the plan manually through MC90 for each material transfer is successful...
    why  the plan is not getting transferred through mass processing.. can somebody help me out...
    Thanks
    Kumar

    Hi,
    Thanks for reply.. our planning periodicity is weekly buckets....
    I am sending the screen shots of the same....
    Screen shot of planning type...
    Screen shot of MC8D...
    I have entered plan in weekly buckets
    Now this is not getting transferred to demand management...
    Can you help me out...
    Thanks
    Kumar

  • Mass Processing of Planned orders

    Hi all,
    We can do mass availability check for the planned orders and we can firm the planned orders for which the materials are available through COHV but can we have a output log after the mass processing so that we can see the list of planned orders got firmed and for any other messages.
    Regards
    Kumar

    Dear,
    In COHV or COMAC.
    in mass processing gtab page
    select function = material availability check, execute it.
    In selection tab page
    Plant
    Order type
    System status - MSPT.
    Or
    Start the report PPCOXPR1 with the T.code SE38
    Then try with Tcode CO24..
    Regards,
    R.Brahmankar

  • Mass processing for SOP

    Hi,
    I am able create sale plan through MC87 transaction by selecting the create sale plan through forecasting, when total consumption values are maintained in the material. But I want this to be done by MASS processing function. In other words I want to up date key figure sales in S076 table.
    There is one tcode MPBT which is to create total forecast in background. But this is happening only when unplanned consumption values are maintained in material. Is this behaviour is correct?
    Can u detail the configuration settings required for mass processing of SOP.
    Through help I came to now that mass processing can be done for forecasting. Is this forecasting and creating sales plan are same. Kindly brief.
    Thanks & Regards,
    N. Laxman

    you can refer the below link:
    [http://help.sap.com/printdocu/core/Print46c/en/data/pdf/LOLISPLN/LOLISPLN.pdf]
    configuration steps for SOP:
    1)Set parameter for Info structure and Key figure
    2)Maintain Transfer Profile
    3)Define Activity
    4)Define Key figure assignment
    5)Define copy profile.
    procedure of Standard SOP:
    1. Create Plan in inactive version
    2. Disaggregate product group plan & Check capacity
    3. Version Management
    4. Transfer Product group to planning
    procedure of Flexible Planning:
    1.Create Plan in inactive version
    2.Convert Plan in to Active Version
    3.Transfer to Demand management
    Master Data in SOP:
    1.Information Structure
    2.Planning Type
    3.Planning Hierarchy
    4.Product Group
    5.Resource
    6.Rough cut planning profile
    It's very helpful link & std procedures for SOP.
    SOP steps have 3 classifications
    1) STD SOP for Material
    2) STD SOP for Product Group
    3) Flexible Planning
    A) Now Let we take STD SOP for Material
    This will takes place in Material and Plant level
    so the charateristics will be Material and Plant
    The key figures are Sales,Production Qty,Targer stock level,.......etc
    Steps
    1) Create Planning for material MC87
    2) Copy to Active Version MC78
    3) Transfer to Demand Mangement MC74
    B) STD sop for Product Group
    Here also the Characteristics are same material->product group
    You have to maintain master data Product group
    steps:
    1) Create Product Group MC84
    2) Create Plan for Product Group MC81
    3) Disaggregate Product Group Plan MC76
    4) Copy to active version MC78
    5) Transfer to Demand Management mc75 for Pg or mc74 for material
    C) FLEIXIBLE PLANNING
    Here you can able to Define your own characteristics and Key figures
    Char like Sales org,Dis chann, Div,......
    Key figures like stock,invoice qty,....
    steps
    1) Create Info structute MC21
    2) Maintain Planning Parametes MC7F
    3) Create Planning Type MC8A
    4) Create Flexible Planning MC93
    5) Copy to active version MC8V
    6) Transfer to Demand managemet
    5) Create Std SOP Planning -MC
    6) Transfer to DM from change mode of Flex Plann with active version MC94
    if you want use the flexible planning info like SIS in std sop after the 4th step of above it will be like
    5) MC87 std sop there Sales data from SIS it will ask for info str and version then you can get it automatically then the std steps like
    6) Copy to Active Version MC78
    7) Transfer to Demand Mangement MC74
    Pls let me know any clarifications.

  • Mass Processing errors

    Hi Experts,
           I am doing mass processing of process orders through CORM transaction, its showing errors for some orders,
    The errors are,
    1.  Balance of ORD 1000010 is not zero
    2. Unprocessed future change recs for order 1000012 prevent del. flag/completion
    3. System status CRTD is active (ORD 1000220)
    Please explain me in details the solutions for all the above errors.
    Thanks & Regards,
    Karad D D

    Hi Devidas,
    1. Balance of ORD 1000010 is not zero.
    For this please get in touch with Costing persons. Orders are not yet settled. hence this problem is there.
    2. Unprocessed future change recs for order 1000012 prevent del. flag/completion.
    Few transactions are open for this material please close it.
    3. System status CRTD is active (ORD 1000220)
    Please put status TECO for this orders this will solve your problem.
    Please confirm,
    Regards,
    Amit Kulkarni.

  • Mass processing Tcode for disaggregation of Prod group plan to Lower levels

    is there a TCode to mass disaggregate the sales plan to FG forecast. I am looking for 'Mass Processing' function of what MC76 can do 'Product Group by Product Group.
    Such processing should blow thro' intermediate level of Product group & then to next level which would be FERT materials.

    is there a TCode to mass disaggregate the sales plan to FG forecast. I am looking for 'Mass Processing' function of what MC76 can do 'Product Group by Product Group.
    Such processing should blow thro' intermediate level of Product group & then to next level which would be FERT materials.

  • Transaction for Mass processing of PM(Plant maintenance) orders

    Hi all,
    Pls let me know if there is any standard tcode for  for Mass processing of PM(Plant maintenance) orders
    I checked for COHV ,but it's appplicable only for produciton orders it seems
    Costing has to be recalculated for all the orders of order type PM02 for financial year 2008-09
    Awaiting eagerly for your reply
    Thanks,
    SVP

    Hello,
    Please try using IW38,IW39
    execute the screen and then you get the option for releaseing , teco etc
    Regards
    gajesh

  • Mass processing of FBRA (Reverse clearing docs). Is this possible?.

    At present it does not seem to be possible to mass process the reverse clearing documents, although it feels like it should be possible. Has anyone come across or know of an enhancement that may allow this to happen?
    Jas

    Thanks for that.
    Of course you did not mean CATT as  that's a testing tool and not a loading tool. CATT has restrictions on the number of records that can be loaded, from what I recall.
    However, there are a number consultants here that believe that there is something available and your answer has just sent them all scurrying to OSS to check.
    Regards
    Jas

  • Mass processing of orders

    Dear all,
    We have a condition wherein we require to mass process of revoking of technically completed production orders.
    Is there any transaction through which this can be achieved.
    Regards,
    M.M

    Hi Magesh,
    As far as my knowledge is concerned there is no transaction through which this can be achieved. You will have to take the help of the technical team for this.
    Hope this helps you.
    Do award points if you found them useful.
    Regards,
    Rakesh
    P.S. you can send me a mail at my mail id [email protected] for any specific details

  • Mass processing of indexes cancelled

    Hi,
    After a system refresh there were a number of missing secondary indexes (tcode DB02).
    I have selected them all for mass processing, and then stared to process them with tcode SE14 > DB Requests > Mass processing.
    During this mass processing the system has been restarted and the job TBATG-20100723 failed
    joblog:
    Job started                                                                
    Step 001 started (program RADBAT01, variant &0000000000000, user ID myuser)
    DB log: TBATG-20100723                                                     
    Job cancelled due to system shutdown
    Now in SE14 > DB Requests > Mass processing the job status of the remaining indexes is "cancelled".
    Is there anyway to restart this process?
    Kind regards,
    Nicolas

    Hello,
    The job has status cancelled.
    I've done a check status but this didn't change anything in DB02
    Kind regards,
    Nicolas

Maybe you are looking for

  • Cryptography - symmetric

    I have problems decrypting the data i have encrypted using the same cipher instance and key. i get an error "javax.crypto.BadPaddingException: Given final block not properly padded" when decrypting long strings. I was able to successfully decrypt str

  • ASA enable authentication for AD user by ACS TACACS fails

    In order to authorize command on ASA8.x for different users, I have to put 'aaa authentication enable console TACACS' into ASA configuration, and in ACS - user setup - TACACS+ enable password - Use separate password, I set an enable password. It work

  • VAMT Queries

    -          Can we activate office 2013 pro plus volume license edition using VAMT 2.0

  • HeuristicMixedException on VMS with 6.1sp2

    Has anyone using VMS encountered the random unexplained javax.transaction.HeuristicMixedException with 6.1sp2 that was suppose to have been fixed in 6.1sp3. http://e-docs.bea.com/wls/docs61/notes/bugfixes2.html#1147388 "064232,The javax.transaction.H

  • Reload Detail screen everytime user searches

    Hello I have created a custom app using the master - detail template. I want to change the standard functionality to reload the detail screen every time a user does a search, even if the search returns the current loaded entity in the detail screen a