Material batches from Production Supply Area St. Type

Hello Team,
1.  User do LP12 for WM Staging [MvT 319]
2.  He Goto LB11 and creates TO.
3.  But when User creates TO for 319 MvT, system picks up batch from Production Supply Area.
It should NOT pick up material batches from Production Supply Area.
Please suggest at earliest..
Thanks
Tushar

Hi,
Check customizing settings
check PK05, check if you have maintained the proper production supply area , WM storage loc. As I see it you are doing prod supply for release order parts. Also see cr02, basic data , see if you have assigned proper production supply area.
check storage type 100 is properly defined , movement type 319  are created and their assignment made in WM.
Also check if you have activated PP/WM interface.
If all the settinsg are done , there should be no problems.
Regards

Similar Messages

  • Production supply Area assigned to Mov Type 319

    Dear All,
    What is happening in background if we set production supply area to mov type 319(Replenish for production).
    Also please tell what is KANBAN Interface & why it is used.
    Thanks & Regards,
    Olet Malla

    Hi
    Yes you do not have WM-PP interface.
    With WM-PP Interface you can automate the entire process based on Production order status.
    For example when you confirm the Production order system will genearate TR automatically for all the components. This can be further automated to complete the warehouse operation by changing the status of Production order.
    [Advantage|http://help.sap.com/saphelp_46c/helpdata/en/c6/f840fb4afa11d182b90000e829fbfe/content.htm]
    Karthik

  • Replenishement directly from external supplier to production supply area

    Hi Experts
    I'm new in WM,
    We have a big tanks for oil which will be used by the production as a component during the production process, these tanks is in the PSA "Production supply Area" and the supplier provide the oil directly to PSA ( not throug the Warehouse) so these tanks are under the production control.
    we need to implement this process in SAP.
    we need the stept by step implementation of that request
    your support is highly recommanded for us
    Many thanks in advance
    Olfa

    There are many ways to do your requirement. One among them is, Implement KANBAN Process using External Replenishment.
    Evaluate options using PK01 .. External proc.
    Regards,
    Sathish

  • Picking in WM for production supply area

    Dear expert,
    In my scenario when production order is released it will automatically create TR. Then convert to TO to move from fixed bin (source) to production supply (storage type 100). Now, i want to do picking this material from production supply (storage type 100) to supply area in work centre for production.
    How to do this?

    Hi BPO,
    Please define your requirement better. What causes problem to you?
    Are you speaking about raw materials or SFG that you get when you book confirmation against your PrdOrd?
    You can create storage bins under storage type 100 as well (to store your goods there) and you can define storage typr search (SPRO) and storage strategies (WM view in material master).
    You can define control cycles for your supply areas...
    What's your problem exactly?
    Thanks,
    Csaba

  • Production supply area (PSA)

    Hello,
    I would like to know how to define the production supply area in the material master record. It would be of much help and precise if anyone could mention the view in material master in which the Production supply areas could be assigned for a material.
    Thanks,
    Maxx.

    If you set this up on material master, it will always stage material to this area. You can achieve the same by maintaining a control cycle. With control cycle and leaving this field blank on material master, you can map it to the level of storage bin for production staging.

  • Production supply area (PSA) and supply area

    Hi,
    Is there any difference between supply area and Production supply area. it woul be good if you could explain me the difference.
    Thanks,
    Maxx

    Both are same
    Production Supply Area is the link between Warehosue Management and Production function.
    Production supply areas (PSAs) are used for material replenishment and are situated directly on the shop floor in the production department. The supply area groups work centers near production storage bins based on the material staging methods. You need to enter the PSA in the work center master data.
    http://help.sap.com/saphelp_46c/helpdata/en/c6/f8412f4afa11d182b90000e829fbfe/frameset.htm
    Hope this helps.
    An area on the shop floor where material is provided that can be directly used for production.
    The supply area is used, for example, in KANBAN production control and for material staging using Warehouse Management (WM).
    Proposed Supply Area in Material Master Record                                                                               
    The supply area is used as an interim storage area on the shop floor    
         which is used to provide materials directly at the production line.                                                                               
    The proposed supply area is mainly used for KANBAN materials that are   
         only or usually provided at one supply area in a plant. Here, this supply
         area can be easily saved in the system.                                                                               
    The proposed supply area is used, for example, to determine the supply  
         area for the dependent requirements of a material.                      
         The supply area in the dependent requirements of a material is required:
         o  to enable the system to calculate the KANBAN control cycles          
            automatically                                                        
         o  to enable you to select requirements in the pull list with reference 
            to a supply area

  • Difference between Production Supply Area and a Storage Location

    Hello Experts,
    Basic question but wanted to get more clarity on the concept as i never worked on the PSA
    Can someone tell me the exact difference between PSA and a SL. I understand PSA is a Kanban, WM and SL is an IM concept. Can a work center have a storage location assigned or just a PSA? Can a GI be done from PSA or just from a storage location.

    Hello
    The production supply area is a master data used by WM, while the storage location is used by MM-IM.
    Check this link for details:
    Production Supply Area - Warehouse Management System (WMS) - SAP Library
    The goods issue is done with reference to the storage location
    It is possible to assigne a storage location to a production supply area and assign the production supply area to the work center.
    BR
    Caetano

  • Errror : production supply area not available fieldin  work center .

    HI
       hi friends
            i want  to maintain production supply area in work centre...
            production supply area means storage location??
          i have a confusion between storage location and production supply area
    pls suggest me where i missed the setting
    with regards
    dinesh

    Production supply area is not a storage location. It is linked to one, but you may have more than one supply area per storage location.
    Supply areas are used in KANBAN processes, and I think that also in WM-PP interface.

  • Material Batch in Production Order

    Good afternoon,
    We have the scenario where a Material batch is only allowed in ONE production order, for example:
    Material 123, Batch A: Qty50
    Material 123, Batch B: Qty50
    I have a production Order that requires 75 of Material 123.
    The production Order can only be a maximum of 50 and another for 25 has to be raised as only 1 material batch is allowed per Production Order.
    Is this possible?

    Guy,
    I think you are saying since your component material 123 has 2 batches of qty 50, you want to generate Finished product production order qty =50 automatically.
    This is a typical requirement in Chemical/Pharma industry where production batch size is determined by available raw material qty.
    This feature can be used in a concept called Material qty calculation used in the PP-PI model where you work reciepe & process orders. unfortunately this feature is not available in the PP module of SAP.
    Alternatively your client may have to go for an ehancement pack " Industry solution - Pharma"
    However if you are using PP-PI module the solution is as follows
    With material qty calculation based on raw material qty (eg 50) issued to production order, FG production order qty can be reduces to 50 (based on formulae maintained in Mat-Qty section in Recipe).
    Hope this helps resolve your question.
    thanks,
    Ram

  • Extend the Material Code from One Business Area to other Business Area.

    Dear All,
    I have create some material codes in a business area XYZ with Storage Location AA11 in Company code ABC. There is another business area PQR with Storage Location BB22 in Company code ABC. How can I extend the Material Codes of the Business Area XYZ with Storage Location AA11 to Business Area PQR with Storage Location BB22 through LSMW.
    I am waiting your reply.
    Regards,
    Hemang

    To extend material masters you can use anyone of the  SAP given import methods in LSMW.
    But I am a bit confused with the terms you are using, what do you mean by business area? and a material master is not created per company, the company is not among the organisation levels.
    Are you talking about plant and sales area?

  • Production supply area w/Min Max

    Hello,
    I have a WM scenario that i want to prototype, and i would like to know the steps involved in this WM scenario.
    The scenario is :
    Production Area Supply w/ Min Max
    Illustrate the material replenishment to the PSA based on min/max levels for raw materials and intermediates; Min level based on requirements for 2 production runs, Max level based on requirements for 3 production runs.
    the material for the replenishment is taken from the storage types.
    pl. do mention the steps or how to carry out the scenario with the t codes involved in it.
    Thanks,
    Maxx

    I suggest you checking system by two ways:
    1) Set PSA to work center, now it works? If so please check BOM settings carefully.
    2) Don't use dynamic production bin, just try a physical bin. If it works please check control cycle settings.
    Note: You create the dynamic storage bin "production order" in the control cycle for pick parts. The system then stages all the materials for a specific production order in a dynamic storage bin with this production order number.
    When you system emit errors again please use LS24 to check if having a dynamic bin with a production order number.

  • Production supply area question

    Hi
    I need to stage materials from WM storage location (0001) to production line.
    Generally in WM, material staging happens by staging the materials to the PSA. So I create PSA and assign it to the workcenter.
    Next step is to assign this PSA to the storage location. My question, is this storage location a different storage location or is it the same 0001 location?
    Thx

    hi ,
    This should be a new storage type  and need not have to be a storage location.  You can use the same 0001 itself.
    cheers
    Rav

  • Material Return from 542 movement type without purchase order

    HI Expert
    I have a problem regaring material return from vendor through 542 mov type against purchase order.
    when i transfer material to vendor with mov type 541. and after grv if we return material from vendor against purchase order.
    system doesnot allow to return material against purchase order. it allows mov type 542 for returning material from venodr without pruchase order.
    Suppose we have 10 quality for a component to transfer vendor we take grv and issue 5 qty through 543 move type automatically. if we want to take return 5 remaining qty from vendor against purchase order .
    system doesnot allow to return component from vendor against purchase order.
    but allow  to return component from vendor without purchase order.
    vendor stocks becomes less but purchase order still open for open quantity.
    how we could control vendor's returing material with the reference of purchase order after grv.
    with regards
    sanjay agrawal

    HI,
    Are you creating return Po for subcontracting vendor with item category L.?
    we used movement type 541 to send material to vendor ,now you want movement type 542 in system means take back from vendor?
    I don't think so it will make work and make any sense
    why you are not adjust your component with subcontracting adjustment in sap mm
    check following link
    [http://help.sap.com/saphelp_470/helpdata/en/4d/2b908943ad11d189410000e829fbbd/content.htm]
    Regards
    Kailas Ugale

  • Material Return/Scrap Material from production generate inspection lot

    Hi experts,
    I would like to confirg the following:
    When material return or scrapped material return from production(mvnt type 262), system is required to generate inspection lot.
    How can I config this scenario?
    Thanks!
    Regards,
    Daniel

    The inspection lot origin '05' is assigned to movement type '262'.
    (You can check this in update control at transaction OMJJ.)
    So you have to activate the inspection type '05' or new one.
    But you should be 'careful' because an inspection lot will be create even if other movement like '501'.
    Regards
    Luke

  • Material Staging for Production

    Hi,
    When WM is implemented, is it really necessary to use Production supply area and Control Cycle? or only Interim storage area 100 is sufficient? We are not using any KANBAN features,,
    Regards
    Shrinivas

    When WM is implemented, is it really necessary to use Production supply area and Control Cycle? or only Interim storage area 100 is sufficient? We are not using any KANBAN features,,
    1.
    If you use WM/PP interface, you use interim storage type 100 for material staging. In this case production supply area is a must.
    In this scenario you move the pick parts to the interim storage type (100) by processing the TR that is created at the time of PrdOrd release (e.g.).
    Please notice that no IM movement is posted at that time. When you get the parts in interim storage type you post IM-mvt 261 and consume the components (so, first WM movements and after that comes IM movmement). Storage type 100 behaves like an interim storage type.
    2.
    If you don't use WM/PP interface you use interim storage type 914. First you post IM-mvt 261 and after that processing the TR (that is created as a consequence of IM booking) you will get the TO and move the parts from normal storage type to 914.
    So, in this case WM movements come after IM movement.
    Regards,
    Csaba

Maybe you are looking for

  • .pages file cannot be opened in pages

    I've been working yesterday and today on a report for a customer in pages with many graphs. Tonight, I planned to finish the report, but Pages can't open the document anymore. I've tried many things: - Open it in Pages via 'open documents' - Open it

  • Short dump in DB13 backup

    Hi, we got a short dump during the backup of the local HANA DB in Tx DB13. SAP Netweaver 7.30 SP08 SAP HANA 1.00.70.00 Category           ABAP Programming Error Runtime Errors     EXSQL_ILLEGAL_DISCONNECTION ABAP Program       CL_HDB_UTILITIES_DB13==

  • Want to manually change Call Duration on my Nokia ...

    Is it possible to manually change the call duration to what I want it to be set as. I used my dada phone while he was away and holiday, and just found out that he wrote down the total call duration before he went away.  I have been using his phone an

  • ComponentWorks and Visual C++ 6.0

    How do I load the ComponentWorks 2.0.1 Controls in Visual C++ 6.0 ? Caroline Catel | mailto:[email protected] SINFOR Rhone-Alpes | Phone: (+33|0) 4 72 13 56 00 10 Place Charles Beraudier | Fax: (+33|0) 4 72 13 56 01 F-69428 LYON Cedex 03 | Web: http:

  • MSconfig boot is blank, but still boots. Need to remove a boot menu entry.

    Hello, I have three boot menu entries that appear when I restart my pc.  The last one I would like to remove, as it isn't valid anymore.  When I go into msconfig, boot (tab), there isn't any entries in it.  I tried recreating another administrator pr