Material Component to Network - BAPI_NETWORK_COMP_ADD

hi,
has anyone come across this SAP problem?
I use BAPI_NETWORK_COMP_ADD to add a material to a Network.
It adds fine, and shows up in CJ20N.
However, if you go to the Plan/Actual Cost (CN41), there is no cost associated.
Okay. I used BAPI_NETWORK_COMP_CHANGE and it finally added the Cost to the Material Component.
HOWEVER, it doesn't have the Cost on Network/WBS element level.
Therefore, the plan/actual Cost for Project Definition is wrong.
Can anyone help?
If you add a material component manually in CJ20N and then change quantity, it works fine.
The thing is, CJ20N uses so many memory objects, it's hard to copy what it does. 
Thank you
Bill

Hi,
after the transfer,
go to CJ20N and check the network control parameter, where the cost calculation parametrs are maintained.
1- cost to be calculated
2- cost to be calculated aftr release
3-donn plan cost
select the correct one
again check the costing variant and check the material valuation
rgds
ashis

Similar Messages

  • How to create a Purchase Requisition for a material component in WBS or NW?

    Hello All,
    I have created a project with the following structure:
    Project Defination (Construction of Sub station)
          Main WBS
                   Level 1 WBS
                             Level 2 WBS
                                       Network for level 2 WBS
                                                      Activity  (Procuring Material)
                                                                 Material Component - MATXXX (Stock Item)
    Now in the above structure i have a activity where in i am procuring all the materails required to construct a Substation.
    So under this activity i have assigned all the materials which are needed to build Substaion.
    After i change the status of the project to release, there  a reservation created for the quantity of the material which i have mentioned in the material component under the activity.
    Now my querey is, how should i create a Purchase requisition for the reserved materail quantity in order to bring in the stock against the WBS / network / Project ?
    Awaiting your reply.
    Thanks and Regards,
    Sudarshan.

    Hi Sudarshan,
    In your case you can run Me5J to check the list of PR created against your project.
    Then Create PO and similarly you can check list of PO in Me2J.
    Then followed by GR and check if any GR release exist in MIGO. Then once after doing GR you can check the Material in Stock which will move material from Unrestricted stock to Project Stock which you can check it in MMBE.
    Then you can do the Good Issue in MIGO itself and run MIRO to complete the cycle.
    Regards'
    syed

  • G/L is not automatically assigned to material component

    Hi All,
    We use transaction CJ20N in creating a meterial component, non stock item category(N), G/L is not automatically populated. Could you please tell me how does the system in SAP automatically assign G/L account in the material component. I have checked the valuation class for the material group and a G/L is assigned there but it is not assigning in the material component.
    Thanks in advance

    hi,
    yes i have checked the network profile and the g/l account is mandatory, therefore prompting the system for the g/l account to be assigned first
    also, the g/l account is assigned to the valuation class
    Edited by: UserID on Aug 8, 2011 8:09 AM

  • Material component

    HI All,
    I selected a material component with item category "L" and procurement type "Third party requisition for WBS element" and then created PR from project builder. then created  a PO and rreceived the material into stock.
    now i can see the material in stock with the corresponding WBS Element.
    when  i tried to create a delivery through CNS0 then the material (line item) in the delivery becpomes not relavent for GI and could not issue out the material to customer. I checked the delivery and found that the movementnt type 281 was not copied into the delivery, so i could not issue the material.
    my question here is, whether the combination item cat "L" and procurement type "Third party requisition for WBS element" is correct?..if not then in CJ20N system should not have allowed me to select this combination.
    i assume the "N" with "Third party requisition for Network" is correct. But i would like to know reason for my earlier issue.
    is there any solution for this? please help.
    Thanks
    Diva

    Hello
    Do you get unrestricted project stock in MMBE once you make GR?
    In CNS0 you make a delivery from project for goods to the customer and unrestricted project stock is mandatory.
    For this you need to create reservations in the project for the materials which you want to deliver.
    I'd suggest to try for item category L and "PR+Reservation" scenario.
    Hope this will help you
    Regards
    Ashish

  • Cost of Material Component

    Hi experts,
    I am not able to view the cost of material component in Structure overview report...but i am able to see the cost of the activity , WBS element...I wanted to see the cost of material component also..pls tell me what is to be done?

    Hi ,
    Go to the network header select Control tab , In selection tab Costing put following parameters,
    Costing sheet PP-PC1,Costing varian plan PS02 costing variant act. PS03,Plan cost calc 2.determine plan cost.
    save the project and reopen and check for planned cost.System will get material cost from material master.
    Rgds

  • GI Actual Cost-Material Component

    Hello Experts,
    I have maintained movement type 101 for GR, 281 for GI for valuated project stock and Item Category L for creating material component. Actually, my report reflects the planned figures on WBS, then breaks on activity then reflects further breakdown at the material breakdown level under the activity.
    When comes to actual cost i.e. first GR the value goes on WBS, which is correct. However, when I do GI it goes on the activity and my material actual cost breakdown figures don’t appear, neither does the commitment column. They remain zero instead and the Actuals GI figure reflects on activity.
    Can you please tell me where am i doing anything wrong.?
    Thanks,
    Kumar Srinivasan

    Hi,
    Just check your procurement parameters.
    If the parameters are set to reserve/ purchase the material for a network and not WBS then it will always look for the network number as the controlling object. From there only you handle your stock, Good Receipts, Good Issues and its valuation means how it is valuated.
    Eg:-
    If you have set up your project by contradicting that the project definition has group requirements for a project and then you don’t have Q on your special stock indicator on the procurement page, then you will have your costs going in different directions.
    I hope this will clear your doubts.
    Regards,
    Amit Rajoria

  • CN01 assign Material Component to internal activity

    Hello gurus;
    In transaction CN01 / CN02 can I assign only one Material Component to internal activity without Bill of Material (BOM)?
    It is possible? How can i do?
    Best regards,
    Mariano

    Virendra;
    Thanks for your response.
    I saw the SAP Help portal in [http://help.sap.com/saphelp_46c/helpdata/es/4c/227a7746e611d189470000e829fbbd/frameset.htm]
    and I must use a Bill of Material to assign material component. There is no other choice
    This is the point where I disagree with SAP, cause the client says that they use Operational Networks, cause it's more simple to assign components to activities.
    Best regards.
    Mariano

  • How to change material component for a Purchase Order?

    How to change material component for a Purchase Order?
    I need FM .
    PLEASE help

    Dear ,
    Create PO with item category L....There in Item detail you will get tab for material.
    There click in component Button, it will take you to the component screen there you can assign and deassign components.
    Hope this helps.
    Regards
    Utsav

  • "No valid material component found" when Routing upload using LSMW RCPTRA02

    I want to upload routings through LSMW RCPTRA02 incluing routing headers, sequences, operations and component allocations. But systems appears error CM 101 "No valid material component found" . Does anybody occurs the same error before?
    The materials truly exists in BOM component.
    Sincerely thanks,
    Alina

    Hi,
    What is the status of the BOM? There should not be any problem if the material BOM exists.
    Regards,
    Krishnendu.

  • CJ20N-Reservation no. to be passed to PR during material component creation

    Hi,
    In CJ20N when the user creates a material component, PR is created automatically. In this PR, the Reservation no. should also be passed.
    I tried using enhancement COZF0002 and passed the reservation no. as under:
    EBAN_IMP-rsnum = RESBD_IMP-rsnum.
    But while saving the project, the Reservation no. is not getting stored in the PR.
    Can anybody tell me how can I pass the reservation no. to PR?
    Thanks in advance.

    -

  • How to activate price tab in material component

    Dear All,
    Actually i need to assign price for my issuing material, but i am not able get the price tab in material component its only showing general data here i able to assign the quantity. I need help for how to activate the price tab.
    Regards,
    S.Suresh.

    Hi,
    if you take non stock material component ( item category as "N") then system allows you to change the price.
    for this click on material component then, click on Purch.data tab...here you can chnage the price.
    But this is not happening with stock material ( item category as "L").According to me this will not happen with stock material.
    sandeep

  • Restriction for Material Component deletion after PO creation in PS

    I want to restrict the material component deletion from the Projects once the PO is created for it. I have done the required configuration settings in OPSG (Change Profile Order Change management) where the system must give an error for material component deletion once the PO is created for it. But still it is not working.
    1) Why the configuration in OPSG is not working?
    2) Is it required to use user exit CNEX0009 or CNEX0039?
    3) Where can I locate uset exit CNEX0039 if required?
    Can anyone help on this issue!!!!

    Hi,
    Please check again the settings in OPSG.It is std functionality in SAP so i think it should work.
    Muzamil

  • Process order - material component deleted

    Hi,
    I would like to know where can I check if a material component has been deleted in a created process order. Would there be any history for this?

    Dear,
    in easy easy menu...
    Logistics -> Production -> Shop floor control -> Control -> Order change management ®-> Change process......
    Regards,

  • Bapi assign PO to material component

    Hello
    I am migrating some material components to a new project structure.
    I have created the new material components and the new PO (based on the old ones) but i do not know now how to link the material component to the PO.Is there any BAPI that does this?
    Do i have to first create a purchase requisition for this material component or how can i link the mat component to the PO.
    I have used  bapi's for creating material components and PO,so i would need also some bapi that could do something like that.
    Is there any bapi for changing material component ?
    thank you

    Hi
    before creating material components,we have to set the purchase requisition flag to "immediately" so that a purchase requisition is created immediately after material component creation.
    Afterwards i have read the newly created PR's and gave them as parameter to the bapi for PO creation

  • Material component in created status

    Hi,
    The n/w is released also activity is released but the material component assigned are still in created status. PR,PO and GR for the material done but GI not allowed because of this status movement allowed is untick.
    Please suggest.

    Hi,
    Thanks for your reply ..
    the material component status in cj20n is created not released where as the activty is released. Procurement for the material is allowed but since the material is in system status created movement allowed is untick and hence GI not allowed.
    Regards

Maybe you are looking for