Material Cost display on Order

I have created a value category Z1 - Material and assigned a cost element. Then In the maintenance order I have selected a material in component tab. The material has same cost element that is assigned to value category Z1. But cost of material is still not appearing. Moving avarage price is appearing in the purchasing data. Which setting is still remaining?
Regards,
VM

Objective is to have planned and actual cost display of material and exrternal services on the maintenance order :-
I am writing the setting which I have done so far:
1. Define value categories Z1 and Z2. Z1= Material and Z2=External Services.
2. Assignment of cost element on value category. Z1= say '1234' and Z2= say '5678' these cost elements I have received from CO.
3. Material and services which I am selecting on the PM order have the same cost elements as assigned in cost elements.
4. Now define new cost variant ZPMO for PM orders.
5. Define new valuation variant 016.
6. In this valuation variant setting will be like this:
    a. Material tab - Strategy sequence should be like this, 1. value price according to price control in mat.
                                                                                2. MAV
                                                                                3. Standard price.
    b. Activity type- Strategy sequence should be like this,  1. Plan price for the period
       CO version plan/activity - 0
    c. External processing - net quotation price
7. Costing parameters are assigned to PM orders.
After these settings I am creating PM order. External Service's planned cost is displaying on the order but material cost is not displaying.
I have checked the CONTROL tab cost variant ZPMO is assigned there in Costing variant for planned costs
as well as actual cost. RA key(000001) is also displaying.
Still some setting is remaining. I think it may be something very basic. Can any body tell me about it ?
Regards,
VM

Similar Messages

  • Material cost in production order plan cost

    Dear all,
    -we are in sales order cost object with non-valuated stock...
    -we have created two production orders from MRP run. First one is for semi finished material and second one is for finished material.
    Issue-1
    Both production orders not showing material cost in production order plan cost...
    Issue-2
    When i consumed raw material against semi-finished material production order (261-E), system not gnerated any document and material cost not updated either in production order or sales order...
    where should i do changes in configuration to get updated material cost in the production order...
    Best regards
    Kishore

    Hi
    Issue 1 : Check Whether Standard cost is present for header material of prod order, and under control tab of order costing variant for plan is present.
    Issue 2 : Use 261 instead 261E.
    Rajneesh

  • Freight not to be loaded on the Material Cost in Purchase Order

    Hi,
    For Purchase Order, we want to configure a scenario where in we want the freight not to be loaded on the Material Cost.
    Where need to change in the configuration do achieve the same.
    Please guide.
    Regards,
    PK

    HI PK,
    1. New condition type to be created by copying the standard condition type FRA1/FRB1/FRC1
          New condition type ZFR1 created by copying FRA1 - M/06.Accrual flagged in this condition type same as FRA1 and Condition category of the new condition type should be Blank and maintain X-Negative value in the plus/minus field. Accrual must be flagged.
    2.New account key ZR1 created
    OLME -- >conditions -- >Define pricing Determination process -- >Define Transaction/Event keys
    3.Assign this condition type to pricing procedure - M/08 .Also assign transaction key ZR1 .
    80     1     FRA1     Freight %     70             X                              FR1
    80     2     ZRA1     Freight  in spl GL     70             X                         FRE     ZR1
    4.GL account maintained in OBYC for this new account key -ZR1
    Maintain same conditions for FRA1 and ZFR1.
    5. Goods receipt debits freight amount to separate account
    Inventory Acct -  100 Dr
    GR/IR - 100 Cr
    Frght Clr Acct - 20 Cr
    Frieght payable - 20 Dr
    6. At the time of MIRO
    Vendor - 120 cr
    GR/IR - 100 Dr
    Frght Clr actt - 20 Dr
    Hope Help U !
    Regards,
    Pardeep Malik

  • Material document display with ordering address

    Hello all,
    When we create a purchase order and do not order from the "main" (VN) vendor but from an ordering address (OA), and post the goods receipt (101) against this PO, then the material document records only the VN number and not the ordered from number. 
    Is there a list/display that shows all material documents for an order from address versus the vendor address?
    Thanks,
    Annabelle R.

    Thank you very much.
    In addition, as per SAP Library:
    Purchasing > Master Records from the Purchasing View > Vendor Master Data > Partner Roles in Purchasing:
    "In the Logistics Information System (LIS) and in the Business Information Warehouse (SAP BW), you can only run analyses for vendors. You cannot run analyses for any of the other partner roles supplied in the standard system."

  • Distribute a material cost to 4 orders

    Hi,
          In my Scenario a material is used for more than one order( say 4 orders).say 1.8 kg is required to process all those 4 orders.How to distribute those cost into 4 orders.How to distribute this cost to 4 ordrs.

    Hello Velmurugan,
    If the Material is used in all the 4 Orders then with reference to GI, System will post the costs..
    Could you please elaborate the requirement..
    Regards,
    Siva

  • Not getting Material Costs in Production Order - MTO Scenario

    Hi,,
    When we are execting MTO Scenario, We are not getting Material costs in Cost analysis of Production Order (Transaction Code CO03).
    We have executed cost estiamte. but we are not gettig the material cost.we are getting only Activity price of Labour Hours.
    The problem is -
    1. we have created Sales order
    2. we have Run MRP & Planned order changed as production order
    3. But in this production order Costing Relevancy check box was not activated automatically. it is in gray mode and not able change this.
    4. Is the problem with SD configuration? Kindly help me in fix this issue.
    Note  - if we create production order directly - it is showing the Material cost. But only in MTO scenariod it is not giving the material cost.
    Kindly help me how to fix this issue.
    Thanks
    Kishore
    Edited by: Emergys Corp on Nov 5, 2009 7:02 AM

    In Requirement class (SD Configuration - OVZH)- we have to give valuation & Costing Sheet assignment.
    Thanks
    Kishore

  • Display process order material wise planned cost

    Hi
    When I display process order CO03 and select variant Cost Trend for cost analysis. System show total figure of raw material.
    My requirement is to check material number wise pland qty and value for a process order. Planned Activity Qty and Actual Qty with value
    thanks

    Thanks for reply
    Here is a ABAP report requirment on following format please help me.
    Product :: Description ::  Raw mat :: Planned Mat Qty :: Act Qty :: Planned Mat Cost :: Act Mat cost
    9000     :: Milk           :: 100000     ::  2000Kg             :: 1900      :: 50000      ::  60,000      
    thanks

  • Actual cost not correctly displayed for material consumed in an order

    Hi All,
    I have an issue which is as follows:
    In a service order, I have consumed 13 materials for which I am able to view the list of goods movement with its amount and plant and storage location.
    For each goods movement system has generated material document, accounting document, controlling document, etc.
    However system is not displaying the actual costs of all the 13 materials consumed within the order. Only one material cost is dispalyed in actual cost of overview tab of COSTS tab.
    Incidentally, when I clicked the "Rep. Plan/Act." button, system is displaying the actual costs of line item wise material consumption.
    Kindly let me know what could be the reason for this error.
    Many thanks in advance............ JK.

    Kannan,
    If the "Rep. Plan/Act." costs are correct, then you have problems with your value categories
    Have a look at the following correction programs:
    Run TCode OLI5 to correct value category errors (program RIPMCO00)
    Run TCode OLPM to re-build structures (program RIPMS001)
    PeteA

  • SAP report which display PO nos based  on cost center, Internal orders

    Hi.
    I am looking for a report in MM which will display the list of purchase orders for a cost center, Internal orders etc.
    The report output should have ALV grid format,The output of the report should have material no or short text, PO quantity, PO Price, PO value. GR qty, GR value,IR qty, IR value, G/L to which consumption has posted etc.
    Reports ME2K, MB5S, ME80FN do not show the G/L account to which GR value is posted.
    Basically I am looking for a existing report which is readily available.

    Hi
    I dont think there is standard report. we have developed custom report one of my previous project.
    YOu can try a abap query using tables EKKO, EKPO, EKBE and EKKN.
    regards
    Srinivas

  • Material Cost Not Shown in Production Order if planned with MD50

    Hi,
    We have run MRP MD50 for a sale order item ie FERT material which has BOM Items. All the stock of the BOM items is tranfered from Unrestricted Stock to Sales order stock. FERT ITEM planned order is converted to Production Order and all the BOM items sales order stock is issued against PO & Sales order no with Movement Type 261E.
    After confirmation and goods receipt stock of FERT is shown under sales order Stock of Fert Material.
    We can see the cost of operations but cost of materials consumed against the Production order is not displayed in Production order Cost analysis..How material cost can be displayed????
    If i create PO with out refering the sale order that is normal process i can see the cost of materials triggering in Production Order.
    Can we settle the varience when we are planning against sale order???
    Some one Pl help us.
    John

    Dear,
    Check your variant which showes the cost. See the following report
    KKAC - For Sales Order with Assigned Orders  or
    KKBC_KUN - For Sales Order or
    KOB1 - Actual Costs

  • Material costed, production order with no target cost

    I've a case of production order and I don't where to find information to solve it.
    I've a product A costed from March. Standard cost is correct.
    I'm creating a production order now. The cost estimate is calculated during the delivery.
    I've confirmed order by CO15. I've created a variance by deleting 2 items in bom of order. And confirm less than wanted on other component. But I don't think these variances are linked to my problem.
    In CO02 and cost analysis : target cost of my product equals 0.
    I've checked my prod cost variant and choices are : std price, L price from PIR, moving average price.
    Thanks for your helps
    Christophe

    How can I see that ? I've checked that material cost has taken the bom during the cost explosion. Components are also costed.
    I've noticed that target cost appears after variance calculation for product.

  • Material cost / Price on sales order ?

    Do we get the material Cost / Price (Vendor Material price ) on sales Order ?
    I means can we see the material Cost and Material Sales price in Sales order ?
    Hope my question clear .

    Hi -
          Please follow above answer and ignore my reply. 
    Thanks!
    Anesh B
    Edited by: Anesh B on Oct 7, 2009 4:28 PM

  • Error reading material cost estimate for sales order (KE292)

    Dear All,
    I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
    Message no. KE292
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
    However, no product cost estimate could be found for this sales order item.
    The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
    CO-PA Customizing settings.
    System Response
    The system cannot process the document any further.
    Procedure
    Check your Customizing settings."
    We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
    Regards,
    Nagaraju,

    Hi,
    When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
    If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
    Hence, try to run cost estimation and then do releasing.
    Thanks & Regards
    Ravi Kumar

  • To see the cost of production order  after settlement to header material

    hello guys,
       In make to stock,we settle the total cost of prodution order on header material,right(if we keep as the default rule( distribution rule in order type)?
         If i want to see that cost of production order which we settled against the header material,where should i check it?should i check in material account or somewhere else?
             Thanking you guys in advance.

    Dear,
    There is a little missunderstanding in your thought.
    If the material of price control S, When you do the GR, the STD cost of material is deducted from production order cost, then when you settle the production order, the variance is settled to variance account/PD account. hence the production order cost balance is zero.
    Example- Production order cost is 60000
    After GR the production order cost balance is 60000-50000 = 10000.
    After settlement production order cost balance is zero.
    Now your question is where can i see the production order cost?
    You can see the production order cost in the production order itself.
    In the production order...cost disply option just filter the origin with test settlement and GR.
    Then total up the cost, then you can see the cost as 60000.
    please come back if you need more help.

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

Maybe you are looking for

  • Report to Display Release Notes

    How do we extract data that is displayed as long text in the Release notes scetion under each module  or in other words where (table ) is it stored ??

  • Can't go back to mac OS

    Bonjour, Can somebody help me to go back to mac OS ? When i open my computer in anyway i have windows XP ; I can't boot to mac OS; Before this day i could pass to one système to another without problèmes. I use bootcamp and macOS (tiger) open first b

  • Types of Mapping XI Support

    Hi All, Could you pleasae tell me the defination of the followings terms  :- <b> 1. Structure Mapping 2. Node mapping 3. Value Mapping 4. Functional Mapping</b> Which one is/are not supported by XI ? I think 'Node Mapping' only ?? If you anyone have

  • Kernel broken. Pacman errors with PGP sig [solved]

    I had the unlucky situation to have a power failure in the middle of a Kernel upgrade using Pacman. System came back up and the kernel was not installed. So I have NO working OS on the machine. I can boot into a live USB environment and chroot into m

  • How do I backup all my files if my Macbook won't start up?

    So a few days ago, my dad and I got into a fight - he reacted by pouring coffee all over my macbook, then continuously slammed it on the floor. There wasn't really much I could do for my macbook then, except the basic procedure of powering it off, tu