Material Cost Estimate Error

Dear all,
Can you please help me resolve error "No price could be determined for internal activity A0110 7250."?  In KP26, i have input the variable price.
Please help.
Thanks and regards,
Ching

Dear,
T.code KP27 - Dispaly Activity type/Price Planning.
Enter Version,
activity type
From to period
Fiscal year
cost center
Check Activity type rate are maintain or not for perticular month for which you are doing entry..
If activity type rate is not maintained then maintain it in T.code
KP26 - Change Activity type/Price Planning.
As you maintained it your issue will be resolved.
Hope above will helpful.
GOPAN

Similar Messages

  • Valuation with material cost estimate: error with product

    Hi Experts,
    Message no. KE350, Valuation with material cost estimate: error with product "2286940000". Please suggest me to resolve this issue.
    Points will be provided for good solution.
    Regards,
    Jay

    Hi Jaya
    This means that your customization is wrong then...
    In KE4J or KEPC you have assigned costing keys to your material types or some other combination... You should have done this config in a way that costing key is not called  for in the case of non valuated materials...
    In Ke40 you have defined costing key where in you have specified "Issue error msg if no cost estimate found".. This costing key is assigned in KE4J or KEPC in a way that it is getting called even in case of non valuated materials...
    Do you have a separate mat type for non valuated material? If yes, remove this mat type from KE4J/KEPC..
    If you dont have separate mat type i.e. in the same mat type if you have both valuated and non valuated, then you have a problem.. You would get stuck in that case
    Regards
    Ajay M

  • Valuation with material cost estimate: error with product "117122"

    Hi people,
    We have the error:
    =====================
    Valuation with material cost estimate: error with product "117122"
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate a line item using the current standard cost estimate.
    In order to determine the current plan period, the system needs to read the valuation segment of the material master.
    The system has found that the current plan period is not filled forproduct "117122" in plant "UBE1".
    We have the follow configuration in trans.: KE40:
    . Determine material cost estimate
       . Transf. Standard Cost Estimate
    . Costing Variant
    . Control Data for Standard Cost Estimate
       . Period Indicator = "Current Standard Cost Estimate acc. to entry in mat master
    . Addiitonal data CO-PC
        . Transfer cost estimate in controlling area currency  "activated"
    We think the reason about our error is because the field above is activated and some configuration more is necessary for this case. For examplo: Trans.: OKYW and this one was not configurated yet.
    Do you know what happend?
    If we need to configure some transation, or sonly process the cost estimate?
    Thanks,
    Rosana.

    Hello Guido
    Thank you very much for your return.
    It is happenning in a Client that some people are doing the configuration.
    Before we didin't have in KE40, the fiel "Transfer cost estimate in controlling area currency" activated.
    And now, the people activate that in this new Client and I don't know the impact about that.
    I think we have to make the configuration in OKYW.
    The other transation you told me, we don't have any information.
    Could you tell me some other idea what happend?
    Message error is just "Message no. KE350"
    Abou claculate the cost:
    It was calculated by trans.: CK11N for future planning and the real wasn't not possible to release because this material already have moviments.
    Could you tell us is there is some thing more to do?
    Thanks,
    Rosana.

  • Valuation with material cost estimate: error with product " 200038 "

    Hi,
    I am getting an error:
    Valuation with material cost estimate: error with product " 200038 "  (Message KE350).
    Kindly assist on the same?

    If this material is mto material go to t.code KE40 and maintain define access to standard cost estimate define cost key with
    "Transfer sales orde cost estimatex".
    If it is mts material define costing key with Transfer std cost estimate  and in costing data
    costing variant : ppc1
    costing verstion: 1
    period  indicator:  Release std cost estimate matching with goods issue or material costing matching posting date.
    This will resolve ur problem.

  • Material Cost estimate error in CK11N

    Hallo friend,
      While I cost estimate in particular material through CK11N then this error occur as No price could be determined for material/batch 1002769-750/ plant XYZ. Even the material is maintained in BOM and Routing also.  What would be the procedure for costing calculation ?
    With Regards,
      Samrat
    Edited by: Samrat Roy on Feb 25, 2008 3:07 PM

    Hi,,
    kindly tell me urgent solution which is still pending.
      With Regards,
       Samrat

  • Valuation with Material cost estimate

    Hi,
       I am getting an error: "Valuation with material cost estimate:error with product 003443434(material number)
    Does anyone know which transaction is used to correct this error?
    Thanks

    Hi,
    Go to MM02. Select the views of the materials i.e. accounting 1 & 2 , costing 1 & 2 . Look at the valuation class u have maintained for the same material in the view Accounting 1.
    Hope u will get ur problem solved..Assign points, if helpful.
    Satya

  • Cost Estimate Error

    Hi Experts,
    The user executed standard cost estimate for the month of 6 - 2010 and after that they did enter the price manually in MR21, Now they are getting the error Valuation with material cost estimate: error with product "1200004626"  and Message no. KE350... Kindly help me how to fix this issue...
    Thanks
    Yadayya

    Hi,
    I think first you have done standard cost estimate thru CK40N and for next month you might have updated the price through MR21. So system is looking for standard cost estimate and not considering this MR21 price..
    So please run standard cost estimate for current month.. this error will be fixed.
    Thanks
    Fit 4 Nothing

  • Error reading material cost estimate for sales order (KE292)

    Dear All,
    I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
    Message no. KE292
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
    However, no product cost estimate could be found for this sales order item.
    The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
    CO-PA Customizing settings.
    System Response
    The system cannot process the document any further.
    Procedure
    Check your Customizing settings."
    We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
    Regards,
    Nagaraju,

    Hi,
    When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
    If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
    Hence, try to run cost estimation and then do releasing.
    Thanks & Regards
    Ravi Kumar

  • Error while creating material cost estimate

    Hello All
    I am creating material cost estimate of FG whose components are SF & ROH-2. While creating cost estimate system gives an error message which states: :
    *No cost element segment exists for 40103110 on 01.09.2009
    Message no. CK048
    Diagnosis
    The consumption account found by automatic account determination for material STD-PRICE-SF does not exist for the date 01.09.2009 specified.
    Procedure
    Check the cost element segment's validity period
    Check cost element
    Or, if you have authorization, create a cost element which did not exist previously.
    Create primary cost element*
    Please provide your valuable inputs regarding this error message. Looking forward to your inputs & feedback.
    Regards,
    J K Tharwani

    Dear Jitendra,
    Its Seem primary cost element you mentioned is not defined for 09 period.For this go to KA06,gIve that cost element number and the Valid from  date as 01.09.2009 and valid to date as 30.09.2009, press enter it will take u inside the T.C,feed the relevant data and save.
    Now again take the costing run.This time system should not throw the error.
    Check and Revert back.
    Thanks and Regards,
    Jitendra DIlip Chauhan.

  • Error during Material Cost Estimate (CK11N)

    hi friends,
    I am getting am error during the material cost estimate run.(ck11n)
    "No control record for the activity type"
    please let me know what is the problem.
    regards
    Ramesh

    Ramesh,
    System is not able to determine activity type price.
    You need to input activity price in transaction KP26 for Version 0/Period/Cost Center/Activity Type combination.
    Regards,
    Prasobh

  • Error  - Material cost estimate with quantity structure

    Hello Gurus!
    Can anyone please help with the following problem:
    I’m trying to do the material cost estimate with quantity structure, but the system is throwing back the message  " There is no exchange rate for exchange rate type P on 1.01.2008: CHF -> EUR". 
    This happens because I have a subcontratation in my routing in CHF, and in transaction OB08, and I don’t had defined that rate (type P CHF –EUR).
    I need to know if there is any solution to the system assumes other Type of Exchange Rate (the last real exchange rate that I have introduced in my system, not the planned!)
    Points will be assigned to the suitable answer.
    Thanks in advance.
    Mary Jane

    Hi Sridhar
    Thanks for your reply.
    In OKEQ for the version 0, I have the rate type M.
    I don't understand why the system throwing back the message  " There is no exchange rate for exchange rate type P on 1.01.2008: CHF -> EUR".!
    Do you know why?
    Thanks and regards
    Mary Jane

  • Cost Estimate error is coming at the time of billing document release

    Dear All,
    Hi, I am facing one problem that is whenever i am releasing the billing document system gives the error message.
    Error : No standard cost estimate found for this material 164001001.
    Here problem is some finished products we have a cost run and other finished materials we don't have a cost run. Other finished materials billing document release time we are facing the above error. There is no costing run for other finished materials. Here we have a CO-PA.
    I have mainatined the costing key settings(ke40) in co-pa. In Ke40 t.code i have maintained the below settings.
    1. I have selected transfer standard cost estimate radio button under determine material cost estimate.
    2. Costing variant is 1010( This is our varaint)
    3.Costing version is 01
    4. Period indicator : Current standard cost estimate account to entry in material master.
    I have maintained the above settings in ke40 t.code. Please suggest if any thing is wrong on above settings.
    And also i have maintained costing key to material type assignments in ke4j t.code.
    Here i maintained the three point of valuation (PV), One is real valuation, second is manual planning, third is automatic planning.
    here i have assigned material type (fert) to costing key in costing key1 filed.
    Please suggest if any thing wrong in the above settings. Still i am facing the same error at the time of billing document releasing time. Anybody please help to me. It is a very urgent to me.
    Thanks & Regards,
    Reddy

    Hi,
    This is a common error when COPA is activated and when the Costing Key is assigned according to the Material type in KE4J.
    When you need Cost estimation for few FGs and dont require for other FG, then you list out the materials for which you require SCE and then assign these list of materials to the costing key in KE4H(Costing key for Products) leaving out those which dont require.
    But detail the requirement further to facilitate the solution.
    Thanks & Regards,
    Ravi Kumar

  • Release of Cost estimate error

    Hi,
    I am creating a material cost estimate by CK11n.
    Then doing Marking of the cost estimate in CK24.
    But, while releasing it gives errors like present period is too early.
    I have checked the current period in MM03.
    Ususally this problem starts during last week of the month.After 17th or 18th of the month the costs do not get released, accounting documents of billing docs of SD doesn't get generated. It asks for waiting till opening of next period.
    Why this kind of error happens? An elaborate explanation will be greatly appreciated.
    Thanks,
    Prithwiraj.

    While executing CK11n, please ensure that, start date as today's date. You will not find any error in CK24 if the CK11n start date is current date.
    Please make sure that, you are in current period.
    Please award if my answer works fine.
    Vijayanand Sankaran

  • Valuation using material cost estimate

    Ciao a tutti,
    We have create a material cost
    estimate without standard structure(unit costing) not FOR ALL MATERIALS, but only for ONE
    VARIANT of generic material (retail solution) (because the other variant have the same price, and because we have to reproduced 5000 BOM in unit cost for just
    one variant with transaction KKPA LSMW)
    So, now we have to valuated the material cost estimate when the customer create the billing document and put the split of the cost estimate in co-pa
    Our prolem is : we have calculate standard cost estimate for 5000
    variant not for all variant (because our customer crete the BOM in unit
    costing with transaction KKPA and LSMW, and they refuced the idea to
    calculate 30000 cost estimate with lsmw) so when we crete a billing
    document with a variant that haven't cost estimate created the system doesn't
    valuated the cost estimate (the system works well), but how I can change the variant in the valuation and put the variant that have the cost
    estimate calculate?
    Wiht the transaction "Assign Costing Keys to Any Characteristics" I think
    is not possible.
    I must to use enhance COPA0002?
    Thank you very much
    Paolo Artini
    tel: +393299223804

    Hi All,
    I am also facing the problem for Sales Order Cost Estimate. and the Costing Status is VO(Marked without errors).
    I have done the following
    created the Costing Key (sales order cost estimate)
    assigned costing key to the material type.
    assigned to the respective value fields
    sales order cost estimate,
    Run the RA
    Settlement done.
    But in COPA, cost estimates are not being split up based on the cost component (like Material, Labour and Over head) and it is getting posted to COGS only.
    Do we need to change the costing status to FR, if yes, but how to do ?
    Regards
    Ramesh KR
    +91 9884020411

  • Material cost estimate with quantity structure (tcode: CK11N)

    Hey dear friends.
    I donu2019t know in which forum I should put my question above.
    In fact, Iu2019m new to SAP PM module.
    Iu2019m trying to create material cost estimate with quantity structure (tcode: CK11N) for a material u201CXu201D.
    This material is manufactured.
    While running the transaction CK11N, I got an error message.
    After analyzing this error message, Iu2019ve realised that somebody had assigned wrong activity types to cost centers which are linked to this material in tcode: CR03, tab: costing.
    So Iu2019ve changed and assigned the right activity types.
    Then, Iu2019ve tried to run the tcode CK11N again. But the system still brings the wrong activity types and seems to ignore the ones that Iu2019ve assignedu2026
    It seems like the old activity types still linked to the cost centers somewhere else than in tcode CR03u2026
    Any idea about what am I mising ?
    Thank's in advance.
    Bahia.

    Dear Bahia,
    If its rate routing means,i guess you must be working in REM scenario.
    So goto CA22,delete the existing operation and then assign the same work center in a new
    operation,check what activity types is it proposing in the rate routing,if its reflecting correctly means
    save the datas.
    Also goto KKF6N--->click the change mode icon and then calculator button to create a preliminary cost
    estimate and then save the datas.
    One of our forum friend has asked you to check the production order read PP master data once
    again,but understand there is no production order concept in REM scenario,only planned orders.
    Then come back with your queries.
    Regards
    Mangalraj.S
    Edited by: Mangalraj.S on Jun 17, 2009 12:05 PM

Maybe you are looking for

  • Iphone 4 -- 4.2 upgrade....Text now making a noise when sent

    Good Morning, I upgraded over the night and now when i send a text it makes a noise every time it goes through. The text tones are off. IS there a way to fix this to not make a noise.

  • Can't open new message window or reply window in mail

    I just started having issues where I cannot open a new message window or a reply window. I also cannot open a new Note or To Do. I restarted, zapped the pram (8 times), and was going to trash the plist but couldn't find it. Does anyone know if there

  • Satellite Pro C50-A - Microsoft Office 2013 apps crash when opened

    I recently purchased a Satellite Pro C50-A PSCG7A-01X01V. I installed Windows 8.1 and then installed Office 2013. Unfortunately when I start one of the Office 2013 apps it immediately crashes with an error message eg: "Microsoft Word has stopped work

  • DVD drive in mac book pro

    Regarding the mac book pro   SKU: 3827134 Can you (bestbuy) tell me is it has a dvd drive?  It soes not show one in the specs that I can see.

  • How to hide the Attribute dimension from Planning webform

    I am in Planning 9.3.1 We are using members in row section of webform w.r.t Attribut dimension so when we are viewing the webform- it is displaying member name followed by Attribute dimension name . any way to hide that Attribute dimension member fro