Material Description from Purchase Order Intercompany to Outbound Delivery

Dear.
For a purchase order intercompany I change the material description of an item.
I create the delivery from po using VL10D , I check the delivery but the item position is taken
from material master and not from the purchase order changed material description.
How can I solve this problem ?
Thanks

Hi
Check tcode VTLA for NL/DL for item category NLN for instance. You must have in data transfer the subroutine '302' )Item w/o Sales Order). You have this coding:
  if not xkomdlgn-arktx is initial.
    lips-arktx = xkomdlgn-arktx.
  endif.
Try to do this, you have a coding:
  lips-vbelv       = xkomdlgn-vbelv.
  lips-posnv      = xkomdlgn-posnv.
where you must have the PO number and item. Search in EKPO the description and replace it in LIPS-ARKTX. For this, create your own VOFM and replace it in the settings of VTLA.
I hope this helps you
Regards
Eduardo

Similar Messages

  • How 2 Copy Header & Line Item Text from Purchase Order 2 Out Bound Delivery

    Hi SD Gurus,
    I want to copy header and line item text from Purchase Order to Out Bound Delivery (This is required in Stock Transfer Process).
    I have been able to do successful config. for copying header and line item text from Sales Order to Outbound Delivery but config. doesn't seems to be same for copying text from PO to OBD.
    Is there any way to achieve the same? Can some expert show the way to achieve this.
    Thanks in advance.
    Warm regards,
    Rahul Mishra

    Hi Ravikumar thanks for u quick reply.
    This is wht is currently coded.
    concatenate values to get item text for read text function
       invar3+0(10) = invar1. "PO number
       invar3+10(5) = invar2. "PO line number
       SELECT SINGLE * FROM stxh WHERE tdobject = 'EKPO'
                                   AND tdname   = invar3
                                   AND tdid     = 'F01'
                                   AND tdspras  = sy-langu.
       IF sy-subrc = 0.
         invar4 = invar3.
    reading the text for the document items.
         CALL FUNCTION 'READ_TEXT'
           EXPORTING
             id       = 'F01'
             language = sy-langu
             name     = invar4
             object   = 'EKPO'
           TABLES
             lines    = it_itab.
    I have seen some PO's which have info rec texts in that, which gets pulled by the above code...first thing is its id is F02 which exist in STXH table also there is other text with F01 id, and hence the table it_itab gets both these text hence no pbm.
    but i came across a PO which has only one text which is info rec text with id F05 and is not store in stxh and hence doesnot get pulled by read_text fm. How do i change my cod to get this text which should not hamper other PO's as well.
    As mentioned in above msgs, this F05 could be retrieved by providing object name as EINE.
    anyhelp will be appreciated and rewarded.
    thanks

  • Material description VS Purchase order Text when creating a PO

    Hi Gurus,
    When creating a PO for a specific material, I have to print a purchase order text different from the material description.
    To do this, a specific text has be added to the material master data in the tab "Purchase order Text" with the italian language maintained.
    But, when i start to create a new PO for this material, the short text that is shown is retrieved form the Material description and not from the Purchase order text that has been added before.
    How can I do to have the purchase order text shown in the PO instead of the common material description?
    Thanks in advance for your support.
    Regards,
    Valentino
    Edited by: Valentino Rosso on Sep 9, 2009 10:58 AM

    Hi Rajaram,
    thansk a lot for your answer, it has been very helpful.
    Could you please clarify me the below points?
    1) Could you please confirm me that this is the functionality of the standard SAP System? That means that in case we want to put the purchase order text in to "short text" we would need to create an ad hoc development, right?
    2) In case we print the PO with the purchase order text added for the material, is there any point where we can find this information for the material, or we will see just the material description from the Material Master Data?
    Thanks a lot for your support.
    Regards,
    Roberto

  • Purchase Order assigned in Outbound Delivery - GI GR simultaneously

    Hi all,
    I kindly ask you how to customize the assignment of Purchase order in outbound delivery.
    Trough this link system allows you to carry out at the same time a goods issue (referred to the delivery) and a goods receipt (referred to the PO).
    In delivery exists a folder called "Purchase Assignment" in which the link is carried out.
    My suspect is that does not need customizing, is something SAP native.
    Thanks a lot

    Hi Ivan,
    I dont know about Substitution but you can use the User Exits available in SD for Billing documents Release to Accounting. In the user exist, you can write your coding to determine the Cost Center from the Profit Center. The relationship between Cost Center and Profit Center is maintained in table CSKS.
    You can use the following user exits available in SD module for release to Accounting
    EXIT_SAPLV60B_004
    EXIT_SAPLV60B_008
    Please read the documentation of the exits before using.
    Hope this helps.
    Regards
    Mahendra
    Assign points if it helps

  • Purchase order Number and Outbound Delivery

    Hello All,
    I want write a select query which will show all outbound deliveries of a Purchase order. How shoudl I relate them? I mean what database tables can I use?
    Regards
    Puru

    Hi,
    You can use following database tables.
    VBAK- Sales header for PO number
    LIKP-  Delivery header for outbound delivery number.
    VBFA-To link sales  and  delivery in document flow.
    Reward if useful.
    Thanks,
    Pramod

  • Text copy from Purchase Order to Inbound Delivery

    Dear All,
    We would like to copy header texts from purchase order to the inbound delivery document.
    I could not found the customizing point copy-rules for theses documents.
    Is this possible and where have we to configure it?
    Thank you.
    Best regards,
    Thomas

    Hi,
    my situation is:
    - a WM managed warehouse, society A;
    - a HU managed warehouse (without WM), society B;
    - a purchasing process of HU from society A towards society B.
    Society B have a scheduling agreement; when a delivery schedule appears, in society A born a sales order and a delivery. After the registration of the delivery good issue, an idoc transfer information for inbound delivery creation.
    This process is ok without WM, but with a WM managed warehouse the idoc has the following problem:
    "V51VP - item was not found - process cancelled".
    Can you help me to transfer these HU?

  • Can SAP get material number in Purchase order in external processing?

    I have a question that:
    As I know, Exeternal processing is a service, so that Material number can not be shown in purchase order converted from PR for external processing. Here, PR can be automately generated from transaction CO01 to create an external processing production order. Meanwhile, for external processing, purchase info record is created without material number only with material group.
    So, I want to know that if there any solutions to show material number in purchase order generated for external processing?
    thanks,
    best regards,

    If therer are no production order, How can I get finished products from internal activity and external processing?
    Now, external processing in our company like this:
    1.create an purchase info record. (type:subcontracting, with material group, but not material ID)
    2.Maintan external processing data in external operation where external processing happens.(control key: pp02, external processing data: info record, purchase org. net price, cost element etc.)
    3.create a production order for the material.(one of the operations is an external processing operation described like step 2)
    4.Purchase requstion is changed into Purchase order. (Purchase requestion is automately created with the production order)
    5.MIGO to receive goods from the purchase order.
    6.finished the production order and delivery goods.then the production order is DLV.
    In step 4, purchase order can only get the production order ID, but there are no material ID shown in it. Only method to show material is that maintaining a description text in the external operation, then, purchase order item could show material in material text(but, here, there is no material ID derectly from info record or production order).
    this is the big problem now for our company. No material ID can be automately carried into the purchase order.
    Hope you help..
    thanks...

  • Delete item from Purchase Order

    Dear All,
    I want to cancel line item from Purchase Order.
    But  i am unable to do it as i have already made advance payment against PO/Item.
    Actually advance payment was against another Item of PO but by mistake selected wrong item while f-47.
    Now i want to delete item for which made avance payment and transfer advance payment with another PO item.
    How to do it.
    Regards
    Swati

    Hi,
    Your Issue
    Lets say, you have created two items in a PO, and made adv payment against item 10 instead of 20.
    Now you want to delete the item 10---
    Solution
    I hope you have not done any GRN to both items (10 & 20) of your PO.
    Then make your item 10 as same as your item 20. (Do change the material code, order qty, price etc)
    Then delete the item 20.
    So with this, you have made your errorised PO item as actual item, and deleting yout actual PO item as errorised item.
    This is as good as swaping the items from one item to another item in the same PO.
    This will resolve your issue.
    Thanks,
    Srinu

  • Revision level not appearing in material tab of purchase order

    hi
    I have matained revision level in material master but it is not appearing in material tab of purchase order and print preview of purchase order
    regards
    Badari

    Hi, If u have created proper change no in CC01 with assigned object material with proper validity period u can give revision level to material.
    In order to reflect the current revision level on PO printout, the coding in PO print program should be designed accordingly to pick the latest revision level. PO output needs to be re-issued so that the new output can pick the latest information like PO revision level from the master.
    Refer below link also for more information,
    [Revision level in purchase order|Revision level in purchase order]

  • Creating asset from purchase orders

    Dear Gurus.
    Please let me know how to create asset from purchase orders.
    Thanks
    Rgds,
    Saurabh

    hi,
    First, determine the information that is necessary for creating the purchase order:
    Check in the Purchasing component whether a purchase requisition exists for the asset (Logistics - Materials management - Purchasing).
    Determine the vendor from whom you are ordering the asset. If needed, enter the purchasing data for the vendor.
    Determine the asset number of the asset that is being ordered. If necessary, create a new asset.
    Create the purchase order. If there is a purchase requisition, use it as a reference (in Purchasing: Purchase order - Create).
    In the initial screen, when you specify the account assignment type A (for asset), this determines
    The account assignment to an asset
    How the goods receipt or the invoice receipt is to be handled (are asset values to be posted at the time of the goods receipt or at the time of the invoice receipt).
    Once you have entered the general purchasing data in the first screen (order date, material group, etc.), a dialog box appears. Enter the asset to which account assignment is to be made in this dialog box.
    If the asset master record for your purchase has not yet been created, you can create it directly from within the purchase order transaction.
    Display the order item and its current delivery status (in Purchasing: Purchase order - List display - By account assignment).
    Later, post the goods receipt or the invoice receipt. (The Customizing definition of the account assignment type determines when the asset values are posted - either at goods receipt or at invoice receipt.) See the corresponding documentation for the Materials Management (MM) component.
    regards,
    Siddharth.

  • Is there is a way to have a link from purchase order to cost center report.

    Is there is a way to have a link from purchase order to cost center report.
    I am meaning kind of:
    Standard way to customized this link?
    or
    User exit to have this link in place
    or
    Any other solution
    Thanks

    For me it does not make any sense from going from PO to cost center report.
    However, if you want to see the purchase order cost incurred with a cost center, execute KSB1 report. Within the layout, bring "Purchasing Document" field, where you can see the purchase order number in cost center line item report.

  • A report to view the cash flow coming from Purchase Orders.

    Hi All,
    Could anyone suggest me a report to view the financial obligations which comes from Purchase Orders?
    Thanks
    Gandalf

    Hi,
    You will have to activate basic cash management (part of FSCM) and use TCode FF7B (liquidity forecast). What the report would do is, based on the delivery date of the purchase order and the payment terms of the vendor (plus some grace days for clearing the payment as per configuration) determine the date of expected payments and project the cash (and bank) balance by days/week or months.
    Alternatively you can write your own ABAP code which will do the same thing.
    a. Take a list of all open POs and determine the delivery date (EKKO and EKPO)
    b. Add the payment terms as per purchase order to the delivery date
    c. Compute the cost of the purchase order item
    d. Display the report which projects expected payments by date
    Rgds
    Shivram.

  • A report to view the cash flow from Purchase Orders.

    Hi All,
    Could anyone suggest me a report to view the cash flow (financial obligations) which comes from Purchase Orders?
    Thanks
    Gandalf

    Hi,
    You will have to activate basic cash management (part of FSCM) and use TCode FF7B (liquidity forecast). What the report would do is, based on the delivery date of the purchase order and the payment terms of the vendor (plus some grace days for clearing the payment as per configuration) determine the date of expected payments and project the cash (and bank) balance by days/week or months.
    Alternatively you can write your own ABAP code which will do the same thing.
    a. Take a list of all open POs and determine the delivery date (EKKO and EKPO)
    b. Add the payment terms as per purchase order to the delivery date
    c. Compute the cost of the purchase order item
    d. Display the report which projects expected payments by date
    Rgds
    Shivram.

  • Error while creating work order from purchase order

    Dear All,
    We are having a subcontracting scenario where we are creating a Work order from PO but getting the below error.
    Error - "No master data assigned to partners-locations-product combination."
    Done all the setting mentioned in the below thread but the error still persist.
    Error in Generating Work order from Purchase Order
    Any suggestions on which master data we need to check?
    Thanks,
    mahesh.

    Hi Mahesh
    In the below transaction
    /SCA/MFGCFG - Work Order Configuration
    Can you maintain Master data Assigment properly
    Valid From
    Valid To
    Active---Checked
    Can you please list what you maintained
    Regards
    Vinod

  • No update of sales order from purchase order

    Hi,
    When I am trying to change the delivery date of a purchase order line item, I get the error
    "No update of sales order xxxxx from purchase order (error V1 348)" How can I resolve this?
    Sincerely,
    Ketan

    Hi,
    Check whether this PO is created w.r.t. PR and PR is created automatically during Sales order creation.
    If it is so then need no to change the delivery date in PO, it will always get updated as per the Schedule Line date of sales order.
    You can go for GR w.r.t. PO directly.

Maybe you are looking for

  • How to use List of values with bind variables on item?

    Hi I made a dynamic list of values with a bind variable as a provider. I tried to run the list, and it worked fine - i filled inn the bind variable when asked for, and i got a list of values to choose from. I would very much like to use this list of

  • What has been lost in Numbers 3.0 upgrade?

    Has anyone got a list of features that has been lost in the new version of Numbers? I am aware (and disappointed) that the useful Categories feature has gone (I have requested this feature back on relevant Apple page). I think I also saw that Print v

  • 20-pinn to VGA cable

    I can't seem to get my ipad to display on the projector when plugged into a projector via the apple vga connector cable. With my mac, I would use auto detect display, and when i plug the cable into my iphone it says that the accessory does not work w

  • Search is working fine on one server but not giving results from other servers. moss 2007?

    hi, we have multi server or wfe architecture. configured search service on one server 01, central admin is 02, and query as 03, now crawled content with hostname:port of 01. everything is fine. but now when we trying to search results its giving resu

  • Troubles with Visual Studio Ultimate 2013

    Help, please, to resolve issue with Visual Studio Ultimate 2013: VS 2013 Ultimate update 2 System.Exception Пакет не прошел проверку обновлений, зависимостей или конфликтов. Windows не удается установить пакет App.a5e822f7e.a1268.a4a33.aa189.adc28119