Dear experts,
We want's to Map one scenerio in SAP...
The company has an agreement with vendor who will supply the  Casting materials on fixed rate on KG basis for one year.
The vendor will supply the materials which contenet the casting e.g. fg220.( Gear;Bush etc)
Now we want's to give the vendor the open PO for casting type fg220,
While doing the GRN we want's to take the different materials code ( Gear, Bush) belongs to fg220 for stock updation.
Is it possible to map it in standard SAP?
Thanks in advance,
K. Subhash

Hi Subhash,
if u dont want to use different matl codes for stocks.
Then you can use MPN material for it.
If want any help pls reply.
Hope this will solve your problem.
Thanks and regards
Gitesh

Similar Messages

  • Material Master - Purchase order Text view as plant specific

    Is there any provision in standard SAP to make Material Master u2013 Purchase order Text view as plant specific.
    Example: Material Master u2013 Sales text view is sales org & Distribution channel specific and the sales text is unique of each of the sales org and distribution channel combination.
    i.e, if we change sales text for a sales org and distribution channel combination, it will not affect the sales text of another sales org and distribution channel combination.
    Similarly, can we make the Purchase order Text view as plant specific? How to achieve this?
    As of now, if we change the text for one plant, it will be affected to all other plants also.

    Hi Pankaj, thanks for the reply.
    The solution you have given is applicable if the info record PO text is used only in Purchase order?
    Moreover, we are not using plant specific info records.
    We want to use material master PO text for some other custom transactions.
    Please give your inputs.
    Thank you.

  • Create single TO for each position of material in purchase order

    Hi, I am facing a problem while recieving stock from GR mvt 101
    I'm following this steps
    1.- I'm creating a purchase order with several materials (The number of material
    is diferent for each material)
    2.- Good Receipt with MIGO,I'm using movement type 101, this was configurated for
    create automatic TR and TO
    3.- while I'm traying to create a Tranfer Order(LT04), SAP system send this errror
    "you need to create single TO for each position of material"
    Note: Only one Transfer Requirement was created with several postions.
    4.- if I use LB11, the transfer order is created manual for each material, however
    I need to do this one by one.
    Are there any configuration that enable create one single TO for each position in
    purchase order??.
    Im trying to create  TO with LT10 using a new movement type and this enable me move
    material to bin location. However the TR still exist.
    Thanks in advance.
    Regards

    The problem was resolved.
    Thanks in advance

  • Material in purchase order doesnot appear in ME2O

    Dear MM Experts,
    I am PM Consultant but the problem is really weird, after releasing a subcontracting maintenance order and then creating a purchase order for the material in the order, the material doesnot appear in ME2O , by the way this only happen with some materials but not all materials in the system,
    Any help will be appreciated reallly,
    Thanks in advance

    ME2O is not a purchase order monitor, it is meant to monitor components of a subcontract order and create deliveries to your subcontractor.
    If ME2O does not show your order, then you either did a wrong selection, or your PO does not have any components.

  • Regarding material wise purchase order creation with reference to pr

    Dear sir
    I have a scenario depending on the  material wise pos creation
    I have two type of material
    1) raw material
    2) consumables
    When user will create purchase order for raw material, system should ask purchase requisition. ( i.e with out purchase requisition for raw material , system should not allow to create the purchase order)
    Where as for all consumables materials system should allow to create the purchase order
    Without purchase requisition also, for user.
    Regards
    Jrp.

    You have to create two different document type for purchase order.
    1) Raw Material Purchase
    2) Consumables Purchase
    You can create two different document type for purchase order with below mention path: -
    SPRO >> Materials Management >> Purchasing >> Purchase Order >> Define Document Types.
    After define two different document type, You can change field status for two different document type with below mention path.
    SPRO >> Materials Management >> Purchasing >> Purchase Order >> Define Screen Layout at Document Level.
    Select document type and change field status of purchase requisition.
    Regards,
    Mahesh Wagh

  • Material Management - Purchase Order

    Hi,
    My Requirement :
    I have 4 material. MAT1, MAT2, MAT3, MAT4.
    MAT1 -  has an Open Purchase Order.
    MAT2 - No Purchase Order Placed.
    MAT3 - No Purchase Order Placed.
    MAT4 - has a Closed Purchase Order.
    Could any one help me from which tables and fields I can get these information, that for a material number there has not been a purchase order placed and which has an open or a closed one.
    Will Reward on helpful answers.
    Thank you.

    Hi Subin,
    To cater this requirement, you have to go step by step.
    First fetch all PO against material no from EKBE table.
    After check against one by one PO, if it has entry MSEG table then it is delivered means it is closed.
    After that display in your report.
    Hope it will solve your problem.
    Regards
    Krishnendu

  • Updating Material master purchase order text -LSMW

    Dear Experts
    How can update Purchase order Text  through LSMW, while am doing recording system is not recording this field from material master
    Regards
    Ajeesh.s

    Dear Expert
    Please throw some light on this issue
    Regards
    Ajeesh.s

  • Explode Bill of Material on Purchase Order

    When we create a standard NB purchase order, we would like to explode a bill of material for the 1 finished goods material and create MRP requirements for the warranty materials on the BOM.  Basically, we want a requirement there so we can create a PO for these warranty materials.  We have looked at subcontracting, but we are not wanting to supply these materials to a subcontractor we just want to purchase them from a vendor and bring them into our inventory.
    We realize that we can explode the BOM if we start with a planned order.  However on alot of occasions we skip over the planned orders and purchase requisitions and manually create the PO.
    Does anyone know of a process to explode the BOM from the PO? or maybe a user exit on the PO that would allow us to do this.  
    We are currently on version SAP 4.6C.
    Thanks,
    Mark

    Hi James,
    As you rightly mentioned, the purpose of a BOM is to contain a list of materials. To create   
    a sales BOM. use T.code CS01.
    Here you give the usage as 5 - indicates sales and distribution as there can be production boms also with a different usage.
    After you enter inside give the components that make up your main material, say music system containing
    Itemcat          material               Qty  
    l               2 mt wires                2
    l               speaker                   2
    so on, then save it.
    For each of these you should have a material master created. For the main item ie., music system select the item category group as " ERLA " for header level pricing and
    " LUMF " for item level pricing.
    Maintain item category determinations in VOV4 as
    <b>For item category group ERLA</b>
    OR + ERLA                         -
    >  TAQ ( Header level pricing )
    OR + Norm +     + TAQ (higher level item cat ) -
    > TAE
    <b>For item category group LUMF</b>
    OR + LUMF                         -
    >  TAP ( Item level pricing )
    OR + Norm +     + TAP (higher level item cat ) -
    > TAN
    This will setup the scenario you wanted. Now when enter music system in sales order with "  1 " quantity it will explode as
    2 wires
    2 speaker
    as was the component quantity mentioned in CS01.
    Hope it helps. Please reward if useful.
    Thanks & Regards
    Sadhu Kishore

  • Receipt material without purchase order

    Dear ALL,
    We want to create material receipt not without purchase order and try it by movement type 501 and its created. but problem is if material moving average is 0 then system post material without any account entry.  now i want system restrict to user if value is 0 for posting.
    Regards,
    Mukesh

    Hi.
    Use the following logic in the system.
    At the time of the creation of the material document pass the material number in the MBEW table with the entries as :
    Material
    Valuation area = equal to the plant number
    check the material price = moving average or standard price.
    in case both the material prices are  0 then display the error message in the MIGO screen. It will stop posting the 501 movement type.
    I hope this helps

  • Sales Order specific Purchase Order

    Dear Experts,
    our client has scenario which is sales order centric, which mean that when PO is created it has to be with reference to sales order, however this is not a third party scenario. How do we link sales order details on PO ? How can we do sales order specific receiving ? suggestions on standard configuration are welcome.
    Thks,

    AHD,
    ???? What you are describing sounds like standard Make to Order.  Nothing special required.  Probably a third of all SAP Finished Goods planning implementations are set up this way.  If you wish, it is possible to carry the sales order reference all the way down to the raw materials.
    In Make to order, all the supply elements (including stock) are planned in a separate segment, one segment for each sales order/item.  The planned orders, production orders, purchase requisitions, and purchase orders are all specific to a single planning  segment.  These non-stock supply elements may not be received to any other segment.  Stock may not be issued to any other segment.
    Here is one of the most common MTO scenarios, 'Make to Order without Variant', SAP Best Practices
    http://help.sap.com/bp_bl604/BBLibrary/HTML/148_EN_IN.htm
    As always, for Best Practices, don't forget the Prerequisite matrix.
    http://help.sap.com/bp_bl604/BL_IN/Documentation/Prerequisites_Matrix_BL_EN_IN.xls
    Best Regards,
    DB49

  • Searching Material in Purchase Order-- Urgent

    Hi,
    Is it Possible to search a material while raising Purchase Order by Material PO text. Actually the requirement is that while raising  PO, the users want to search the material by Material PO text since they put the technical description in this field. As material description is 40 characters , the actual description is becoming difficult to understand.
    Is it Possible to search material by Material PO text?
    Regards
    John

    Hi john,
    In the standard drop down list it is not available.I hope that you can check with your basis team to add such drop down.Otherwise get the information thro' tables.
    regards
    venkadesh

  • Blocking material for Purchase order only

    hi all,
    i have a material and i want to block it for purchase order only bcos we dont want to allow to purchase it but it can perform all other operations. can anyone please help me?
    regards saurabh.

    Dear,
    Go to MM02, in Basic1 tab
    X-plant material status -   01     Blocked for procment/whse
    but it is relevant not only for that plant but also for client level becoz while go to MM02, please not select any plant and go to Basic Data 1 tab.
    this may help u
    Reagrds,
    pardeep Malik
    Edited by: Pardeep  Malik on Mar 14, 2009 5:59 AM
    Edited by: Pardeep  Malik on Mar 14, 2009 6:06 AM

  • Material Master Purchase Order Text.

    Hi Guys,
    What is table and Field name where "Purchase order Text"  stored.
    Reg,
    Gopi

    Use Function Module READ_TEXT by passing parameters TDOBJECT = OIJRCODE_H and TDID = AASI and TDNAME= Key and Fetch the PO Header infoInstructions.
    Based on ur requirement use the parameters
    Also, you may try table STXH or STXL
    or use READ TEXT and pass the values

  • Field material in purchase order Release ECC.6

    Hi, I see that in my system ECC.6 the field material in PO is hidden. How can I do to see material field?
    Thanks

    Hai Barbara...
    Can you be more specific on your question...
    Please provide exact requirement so that you get quick answers..
    Please mention the Field name or tech details of that field and where your are trying to see it.
    Thanks
    Arshad

  • Material Mater Purchase Order Text in Display Mode in T.Code MM02

    Dear Experts,
    In some code when I want to change the PO text in Material master it reflect in Display mode but maximum code display in change mode plz explain where is the setting.
    RCR

    HI,
    To change the settings of any field in transaction to display, change, required, or hide, u have to pick the field selection group from OMSR and then go to OMS9, select your transaction and then change the settings.
    Hopw this helps,
    Swapnil

Maybe you are looking for

  • Four feet not laying flat?

    I notice that my new MBP's four little round foot pads are not perfectly level. The front right corner is a bit raised. In other words, touching the other three corners doesn't cause the MBP to rock at all, but touching the front right corner makes t

  • ECCS report painter/writer library empty?

    Hello, the standard delivered library 0CS (zero CS), which supposedly contains standard EC-CS reports (and is referred to in various SAP documents) is empty in our system, also in source client 000 (we're on ERP, 6.0). Has SAP stopped delivering the

  • How to Cater Credit Floor Policy in Credit Management

    Dear Guru's, Here is the issue, My client has policy of credit ceiling and credit floor ,which  are: Credit Ceiling: During the month O/s balance should be raised up to the Maximum Credit Ceiling, if any sales order  proceeds beyond Maximum Limit the

  • What is causing error 50202

    After many hours (24-48 typically) of running, my application displays the error message shown above (error 50202).  The application sequentially fires outputs with NI 9485 modules and checks input voltage on a 9201 module, and then appends data to a

  • Help! Creative suite installation on macbook air

    I need to install Creative suite on my new mac air, i only have the installation on dvd, how do i do this?