Material Standard Price update.

I've been trying to update a material standard price via BAPI_MATERIAL_SAVEDATA or MY_MATERIAL_PRICE_UPDATE, with no success.
I've followed the example code give in the thread /message/9187089#9187089 [original link is broken].
Has anyone gotten this to work?

Sure.
Costing Type (OKKI) : 01 Standard Cost estimate (material), in this Price update: Standard price & Valuation View: Legal valuation.
Valuation variant components:
001: Planned valuation Materials: priority 1. Price frm purchasing info records, 2. Valuation price according to price control in material master 3.Valuation price with user Exit.
007: Production Order Actual: priority 1. Valuation price according to price control in material master.
Edited by: KMadhumati on Aug 12, 2009 9:44 AM

Similar Messages

  • Report on difference between PO price and Material standard price

    Hi,
    We need a report on Purchase price difference, which is report showing Open PO price & Material standard price, if there is a price difference
    This need to be run every day to avoid buyer changing price at PO level unless there is a valid reason
    Similarly difference if any between Schedule agreement price & Material master standard price
    Please help

    Hi,
    There is no standard report available for this.
    You need to develop one.
    Considering your requirement, it can be achieved with a query as well provided you do not need complex functionality out of the report.
    Hope this helps.

  • A Function or BAPI to get Material Standard Price?

    Hi All,
    I need a Function or BAPI to get the Material Standard Price when the following Criteria is given;
    1. Material Code
    2. Plant
    3. Period
    4. Year
    5. Company Currency (Optional)
    I need only the Standard Price and Price Unit. Please give me a example with sample values.
    Thanks,
    Kishan

    Sri:
    I need only the Standard Price and Price Unit
    there is no specific FM for that.
    you need to write small select query in FM than use this custom FM into your program.
    Amit.

  • Abap function module for material standard price.

    Dear Team,
    Can anyone tell me the abap function module for getting material  standard price respective of date and material code as input.
    I have observe table MBEW, where we will get standard price of a material for last change date. Not getting any table where price is coming out wrt of Date for a same material.
    Thx in advance
    Rgds
    sp
    kolkata

    HI.
    FM MSR1_MD_MATPRICE_GETLIST  should help.u.
    Regd,
    AS

  • How to get Material standard price: MBEW-STPRS?

    Hi BW experts,
    I am wondering what is the best way to extract data for <u>material standard price</u> in Material master data - Accounting view (<b>MBEW-STPRS</b>)?
    I checked existing extractors for material master, but I didin't find one which could be used.
    Any help and feedback will be awarded.
    Thanks and regards.
    Sally

    Hi Sally,
    Check if 0CO_PC_ACT_05 helps here.
    http://help.sap.com/saphelp_nw04/helpdata/en/22/1b383fdb800804e10000000a114084/content.htm

  • Standard Price Update fo WBS Element

    Hi SAP Community,
    For a free stock material I can update the standard price by transaction code CK11N and mark/release by CK24;
    For a sales order stock material I can update the standard price by transaction code VA02;
    But how can I update a standard price for a WBS element stock material??
    Thanks & Regards,
    Daniel.

    Hi,
    If your order in Based on the Sales Oder they you can carryout easy cost planning for sales order
    why do u want to standard price to be updated to WBS element
    Need some more clarity on your question
    let me know your process. what is the strategy you are using.
    Regards,
    Raj

  • Report displaying Material Standard Price and PO Price

    Hello Experts
    We have materials which are purchased. Price control is maintained as standard price and standard price is maintained using T Code MR21 periodically.
    Due to this when PO price is different from standard price maintained in material master (usually PO price is higher than standard price) all price difference are posted to price difference GL at the time of GR.
    Now users want to check variations between standard price and PO price for the material receipts.
    Can anyone suggest me any report which provides details of standard price and PO price for the material receipts?
    Thanks in advance for your help.
    Satya Alapati

    Nothing std I'm aware of either.  You could consider using the messages 06 205/6/7 to get a warning at the time POs are created that price varies significantly from std.
    Config help text below:
    Set Tolerance Limits for Price Variance
    In this step, you define the tolerance limits for price variances.
    When processing a purchase order, the system checks whether the effective price of a PO item shows variances compared with the valuation price stored in the material master record. In addition, it checks whether the specified cash discount value is admissible.
    Variances are allowed within the framework of tolerance limits. If a variance exceeds a tolerance limit, the system issues a warning or error message.
    In the SAP System, the types of variance are represented by the tolerance keys. For each tolerance key, you can define percentage and value-dependent upper and lower limits per company code.
    Standard settings
    The standard SAP System supplied contains the following tolerance keys:
    PE Price variance, Purchasing
    Tolerance limit for system message no. 207. This message appears if the specified effective price exceeds the predefined tolerances when compared with the material price.
    SE Maximum cash discount deduction, Purchasing
    Tolerance limit for system message no. 231. This is a warning message, which appears when the specified cash discount percentage exceeds the predefined tolerances.
    Note
    You can specify whether the system message appears as a warning or error message using the menu options Environment -> Define Attributes of System Messages.
    Activities
    Maintain the tolerance limits for each tolerance key per company code.
    Regards,
    Nick

  • Manual Standard Price updation

    Hi All,
    One of my client having 8 plants and have more than 1000 FG materials. We are not doing costing run. I have to update manually the standard price for all the FG materials for all the plants. How I can do the above updation in one screen.
    thanks
    Vinu

    HI,
    don't know why the s-price is not changed in your system but maybe the reason is the validity date of the future price.
    example: the validity date of the future price is 10.04.09. So you cannot release the price on 09.04.09 but only on 10.04.09 or a day after 10.04.09.
    BR Christian

  • How to set material standard price to zero

    Hi,
    I am facing a problem relating to standard price of material. The material price control indicator is S. The standard price of that material is 300/-. I need to change 300/- to zero. How can i do that?
    Pl. advise. I will assign the points for the answer.
    Bye

    Is this a purchased part?
    does the material have a cost estimate?
    The price control is "S" ??

  • Material standard price change!

    I am trying to do a standard price change for a material using the message type 'materialvaluation_pricechang'
    I configured the distribution model view and partner profiles for R/3 and XI.
    When I tried to create an IDOC with test tool we19, it got created with status 51 (application doc not posted)
    I got the following error. But in config I didn't see the step 'setup sending material prices'. I am working on SAP ECC 5.0.
    The error description is as follows.
    <b>No Customizing data for valuation area 0013 found
    Message no. CKMLSENDPRICE701
    Diagnosis
    The Customizing data for sending material prices to valuation area 0013 was not found.
    System response
    No price changes were made
    Procedure
    Edit the Customizing data for valuation area 0013 under Materials Management -> Valuation and Account Assignment -> Set Up Sending Material Prices</b>
    Please suggest.
    Thanks,

    Please find the code below in <b>bold</b>. I am trying to change the standard price of the material. Hence ls_ckmlcr-vprsv = 'S'. This is why the following lines in the below code never executes
    <b>ls_matpr_cr-newpvprs = l_price.</b>
    <b>ls_matpr_cr-newpvprs = ls_ckmlcr-pvprs.</b>
    And hence the below condition fails.
    IF ls_matpr_cr-newpeinh = ls_matpr_cr-peinh AND
           ls_matpr_cr-newstprs = ls_matpr_cr-stprs AND
           <b>ls_matpr_cr-newpvprs = ls_matpr_cr-pvprs.</b>
          l_nochange = 'X'.
        ENDIF.
    <b>ls_matpr_cr-newpvprs = ls_matpr_cr-pvprs.</b>
    ls_matpr_cr-newpvprs and ls_matpr_cr-pvprs are same in this case and the if condition fails. So no price change document is posted.
    Is this a bug? Is there any OSS note available to correct this problem.
    IF l_nochange IS INITIAL.
          ls_matpr_cr-newpeinh = ls_price-price_unit.
          <b>IF ls_ckmlcr-vprsv = 'S'.</b>
            ls_matpr_cr-newstprs = l_price.
          ELSE.
            <b>ls_matpr_cr-newpvprs = l_price.</b>
          ENDIF.
        ELSE.
          ls_matpr_cr-newpeinh = ls_ckmlcr-peinh.
          <b>IF ls_ckmlcr-vprsv = 'S'.</b>
            ls_matpr_cr-newstprs = ls_ckmlcr-stprs.
          ELSE.
            <b>ls_matpr_cr-newpvprs = ls_ckmlcr-pvprs.</b>
          ENDIF.
        ENDIF.
        IF ls_matpr_cr-newpeinh = ls_matpr_cr-peinh AND
           ls_matpr_cr-newstprs = ls_matpr_cr-stprs AND
           <b>ls_matpr_cr-newpvprs = ls_matpr_cr-pvprs.</b>
          l_nochange = 'X'.
        ENDIF.
    Thanks,

  • Mat standard price update in Mafg and DC plant at single runof CK11N

    HI,
    we have two plants US01 as Manfg and US02 as DC and we have same mat A in both the plants.
    If i do cost estimate in us01 and again in US02 and release CK24 then mat in both the plants are getting updated with following config.
    Will it be possible to update the stand price in both the plants at single  CK11N run without running in two plants seperatly.
    Special proc can be defined by PP guys or you can also define as below
    1. Go to OMD9
    2. Click on New entries: Enter your Plant = Plant 2 (receiver plant) "SP Pr Type" = Z1 and Proc Type = F;
    3. Under Special Procurement Secrion
    Enter U as special procurement and Plant 1 in the Plant Field (Transferring plant)
    4. Save this entry, and in Mat Master of Plant 2, specify F as Proc Type and Z1 as Special proc key
    5. Run CK11N in Plant 2... and release from CK24
    Thanks,
    sudha

    Dear Sudha,
    Special procurement is configured when there is a stock transfer from one plan to another plant. By this way there will be no new cost estimate in the receiving plant.
    Below document explains in details on the topic:
    http://www.sap-topjobs.com/SpecialPP/overviewdoc.pdf
    We also have transfer control configuration to avoid unnecessary costing estimates for already costed materials to get it transferred to the new material cost estimate when we have same components.
    Kind Regards
    Umapathi G

  • Mass Change Standard Price in Accounting view of material master

    Hi anybody,
    I am maintaining more than 5000 records material master . Each time  change material prices using MR21, but I don't want go MR21. need to develope one abap program for change material standard prices using BAPI or normal ABAP Program. how do I develope?
    please give me sample program for that.
    Thanks
    S.Muthu

    Hello Mani
    I have already checked all the open items.....
    No sale order. No entry in table MSEG.
    Only one PO without GR.....So that should not make any difference.
    Br
    Avinash

  • BAPI to change the standard price of the material

    Hello Friends ,
    I am struggling to find a BAPI to change material standard price. I found 2 BAPIs mentioned below. But was not able to make use of them.
    1) BAPI_MATVAL_PRICE_CHANGE
    2) BAPI_MATERIAL_SAVEDATA
    Can any of you help me in finding right BAPI?

    BAPI_MATVAL_PRICE_CHANGE
    PRICES_CHANGE & PRICES_POST
    BAPI_M_REVAL_CREATEPRICECHANGE
    BAPI_MATERIAL_SAVEDATA
    These are the fm's to save or change material price.

  • Material standard value in Pricing calculation

    Hi,
    I have requirement to have material standard price should be included in sales price determination in pricing procedure.
    E.p
    Material standard price in material master 50 rs
    then in Pricing it should come as
    Material cost  50
    Margin            20
    Sales Price     70
    How I can do this in system i.e. how I can get materail standard price in sales pricing procedure for calculation basis.

    Hi,
    I'm not sure about how determine the margin, but you want to use the condition VPRS to pricing. I suggest you to check these notes before:
    SAP Note 547570 - FAQ: VPRS in pricing
    SAP Note 1365939 - VPRS logic and Customizing settings in SD
    SAP Note Number 107693 Usage of MAP in sales pricing
    SAP Note Number 455988 VPRS for intercompany billing without delivery
    and related notes
    I hope this helps you
    Regards
    Eduardo

  • Change standard price

    Hi experts,
                 can u explain me how to valuate the material for which split valuation is active?  When i am going to t code MR22  i entered material it asked for valuation type i entered the batch which are existing next what to do. plz explain me how to valuate the material
    Thank you
    Sap MM

    Hi
    If you want to change the material standard price (complete valuation) then use MR21.
    MR22 can be useful if you want to change the material price (standard/ MAP) with resepect to quantity. ex: you received certain quantity of material at lower cost and you wanted to increase the price for that quantity only then use MR22. both these Tcodes generate same entried - price change documents.
    So use MR22 and enter material, valuation type, new price, quantity. If you dont want to change the price for certain quantity then use MR21.
    Thanks

Maybe you are looking for

  • User exit for Dlvy Block at header for sales order for Companycode & materl

    Hi all, I have a requirement. I need to apply a Delivery Block for all sales orders which fall In a particualr company code "999" and if they have any configurable material in the item level. When a Sales Order is generated, during the process of gen

  • FRM-41214

    Hi all, When calling a report from a form through the RUN_REPORT_OBJECT built in, the report does not run and the error 'FRM-41214 - Unable to run report' is being shown. Also, the return value for the RUN_REPORT_OBJECT command is <reportservername)_

  • FIle to file scenario with a delayed receiver

    Hi PI experts, I got a requirement to pull files from the sender folder once every day, but the receiver should get the file only once a week. I thought of appending it in the receiver channel, with temporary file. But in that case, the receiver side

  • Can I see what number an iMessage is coming to?

    I have iMessages for both my phone number and my daughter's phone number coming to my phone.  Is there a way to tell when an iMessage comes in which number it was addressed to? Thanks!

  • Pass Date from Internal table to Date field of Deadline(in expression tab)

    Hello, I need to set deadline in workflow according to dates in Internal table. So please guide how to achieve this.