Materials-Not relevant to planning

GM!
I have read that it is possible to flag materials in order component for Detailed operation planning as "Not relevant to planning" so that the reservation/purchase requisiton is not generated for such materials..
I dont know where exactly this setting in Order components page lie or how to achieve this...
Can anyone please let me know how to achieve above said function...
Thanks
Murad Shaikh.

Hi,
In the Maintenance Order, in component tab, while assigning the component, we can decide which component to be planned & which are not to be included in planning.
Options available are From release, immediately & never. Check these options.
[SAP Note|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1148139]
Regards,
Maheswaran.

Similar Messages

  • Materials not relevant for Picking

    Hi Guys,
    I have an outbound delivery wherein some of its materials don't have any value for the picked quantity and the materials' picking status says that they are not relevant for picking. Do you guys have an idea on how can I fix this issue??
    Thanks!

    HI,
    As per your above thread, I understand that your delivery has multiple line items with different materials.
    Check whether any of the material is relevant for picking. If yes, then compare the sales views of the materials which are relevant for picking with the ones which are not.
    Hope you can find some differences.
    Also check the transaction 0184 & OVLP.
    Thanks & Regards,

  • Delivery 0080000276 is not relevant for transportation planning.

    At the time of (delivery related) invoice creation, system throws a message "check the error log".
    Log says:
    " Error Log             0080000276 000010 Delivery 0080000276 is not relevant for transportation planning
                LongText
                    Detail
                     Diagnosis
                         Copying control for billing requires that shipment costs
                         are copied from the shipment belonging to this delivery.
                         No shipment costs could be determined, because this
                         delivery is not relevant for transportation planning.
                     System Response
                         The system assumes that no shipment costs are to be billed
                         in this case.
                Technical data
                    Tech. data details
                     Client                                 251
                     Group Number
                     Sales Document Number                  0080000276
                     Item Number of the SD Document         000010
                     Schedule Line Number                   0306
                     Counter in Control Tables              00
                     Message Identification                 VY
                     System Message Number                  306
                     Output Type                            I
                     Message Variable 01                    0080000276
                     Message Variable 02
                     Message Variable 03
                     Message Variable 04
                     Group Type                             F "
    Please advice if anyone have any idea for this error log.

    Error Log 0080000276 000010 Delivery 0080000276 is
    not relevant for transportation planning
    It is not necessary to assign the Transportation Planning to Delivery type.  Only recently, I completed a similar configuration and running successfully for a client.  The issue is  because of your copy control VTFL.  For more information, check note 713171.
    thanks
    G. Lakshmipathi

  • VF01 00700009 00010 Date 000001 is not relevant for billing (billing plan)  VF143

    Hello, all:
    When I test the scenario 'Integration of resource-related billing and milestone billing', I meet an error: 00700009 00010 Date 000001 is not relevant for billing (billing plan), the message number is VF143.
    How to solve this problem?
    Thanks in advance.

    Hi,
    For this,there are two ways.
    1.Goto the T.Code "VF01".
    Enter your Sales order number and enter the billing date.
    Enter.
    All the items are displayed as a list.Double click on the item you need.
    Save.
    2.Goto the T.Code "VF01".
    Enter your sales order number and don't press "Enter".Click on Selection list and select your desired item and click on "Copy".
    Save.
    Regards,
    Krishna.

  • Unit of measure conversion for CIN is not relevant for pricing

    During creation of Ad item type order, when we enter the planned ad size e.g. A CO (Columns) x B IN (Inches), the system is showing a message "Unit of measure conversion for CIN is not relevant for pricing" and pricing is not determined in the Billing Data Set. However if the planned ad size is maintained as A CO (Columns) x B MM (Millimeters), there is no impact to pricing conditions.
    Any light how to fix this issue?
    Thanks,
    Suseela. V

    Dear Suseela,
    You need to maintain Unit of conversion using transaction code JH51. You have to follow the path Logistics-Advertising Management-Master Data-Conditions-Order/Billing Document-UM for Pricing.
    Here you can maintain combination using Booking Unit, Content Component, Design type and assign Unit of Measure to get relevant pricing into billing set conditions.
    Hope it will help. Thanks!
    Regards
    Indra

  • Item Not relevant for Billing - due to Batch Management

    Dear All ,
    We have activated the Batch  management and the materials are picked from the batch  . When we create billing document ZF2 and ZIV  using VF01 with ref to delivery , we get an message - check log - when we go to the log we see that item 900001 is not relevant for billimg n which is an warning message . This message need to be supressed .The message type - VF044.
    Can you please give me your inputs on this.
    Thanks and regarsd
    Veera

    Hello Friends,
    We are also facing the similar issue as -
    Delivery item 900001 is not relevant for billing , message
    Client: 002                     
    Group Number                                                   
    Sales Document Number  :                0080106599              
    Item Number of the SD Document:         900002                  
    Schedule Line Number                 :  0044                    
    Counter in Control Tables             : 00                      
    Message Identification                 :VF                      
    System Message Number            :      044                     
    Output Type                           : I                       
    Message Variable 01                                            
    Message Variable 02                                            
    Message Variable 03                                            
    Message Variable 04                                            
    Group Type                             : F                       
    As per the note 77414, we made all the settings however system is showing the same message during billing execution. In this regard could you please support to get the solution.
    Best Regards,
    Goutham

  • Enhanced Rebate settlement - item not relevant for billing

    I'm trying to settle an enhanced rebate agreement & i continue to get the error
    "Item is not relevant for billing".  I'm using the materials for which the rebate was accrued as the settlement materials via the configuration for a variable key. 
    I've checked item categories and copy control and do not see what can be causing this.  When bill a standard rebate agreement, i do not get these errors. 
    Any assistance would be appreciated.

    Hi Thomas
    As you are able to create rebate with standard rebate agreement, and as you are getting  "Item is not relevant for billing"  , then check your item category configuration and  condition type assignment  done in the pricing procedure.
    Also just cross check copy control settings  between the standard rebate copy control settings and your enhanced rebate agreement settings
    Also check the configuration done with the enhanced rebate agreements
    Thanks and Regards
    Srinath

  • Why the basic finish date is not adjusted in planned orders

    Hi, all.
    Can anybody help me to understand:
    "Why the basic finish date is not adjusted in planned orders during
    forward scheduling, but in production order basic finish date is adjusted?
    It is look like non-coordination between groups of developers.
    And lead to situation, when planner don't see in MD04 when he can really wait material receipt. He must go to planed order and check production data there, it's unusable."
    Am I right, or SAP have it's own logic.

    Hi,
    Production orders are different story. Since production order is a constant element, they are not created in the course of MRP, basic dates can be adjusted. In production order basic finish date is adjusted, but you won't see for the upper level materials', basic dates of the planned orders adjusted according to the prodcution order you create. Production order is consistent within itself in terms of date and is not dependent to other elements of MRP, but planned orders are not like that.
    MRP creates planned orders whose basic finish dates are calculated by subtracting goods receipt time from production start date of the source of requirement. MRP works backwards without changing directions. Meanwhile if any production finish date is calculated different than the basic finish date due to forward scheduling, in order not to violate the alignment between the basic finish date and source of requirement's start date, basic finish date is not adjusted. If it was, dates of all the planned orders calculated so far at the upper levels of the BOMs had to be recalculated, otherwise all the consistency of all the dates is violated. This cannot be done because changes in any level affects all lower levels.

  • HBR sequence on data form does not execute when Planning data form is saved

    Has anyone experienced this issue before in Planning? Below I have included the scenario and what has been attempted to correct the situation.
    We are using Hyperion Planning/Essbase 9.3.1, sequence contains 3 business rules - 2 executed on the Workforce Cube and 1 transfers totals from Workforce Cube to Main cube. 2 of the BR's contain run-time prompts - 1st BR in the sequence (calculation in Workforce) and 3rd BR in the sequence (transfer of Workforce totals to Main). We are using Projects to assign access priviledges to the BR's and sequences. All 3 business rules, as well as the sequence itself, validate successfully in the admin services console.
    In Planning the data form contains BR Properties to "Save on Exit", "Use members on data form" and "Hide prompt". Have tried removing BR from data form, then put BR back on data form. Also tried building a new sequence in EAS console and attaching that BR to the existing data form. Neither of these attempts were successful. Tried building an entirely new data form with the newly created sequence, still unsuccessful. Was able to execute the sequence successfully when processed from the Tools -> Business Rules menu. Sequence was once again successful when I tried modifying the data form to remove property "Hide prompt". Problem with leaving the form in that state is, our users would not know which Planning server they were on as they access the Planning application through Workspace and we currently have 2 application servers in this environment - so essentially they have a 50/50 chance of selecting the correct server.
    We have this same setup in another environment where the execution of the sequence on the data form works successfully. We have compared everything that I can think of and it all appears the same in both environments - in fact this used to be successful in this environment, but all of a sudden stopped working earlier this year - we have not applied any patches or upgrades to either environment. Do not know if this is relevant or not, but we do currently utilize Netscaler in both of these environments.
    Any experiences with this type of situation or suggestions at this point would be greatly appreciated.

    I don't have a solution for you but more steps to solve the problem
    You are ultimately on the right track in some ways but break it down into it's components.
    The problem could like in the business rule, the form connection, the variables, even the order of operations could all be in play.
    So I would strip this baby down to its bare bones then build it back up.
    1) Run the business rule. Each one separately and only after the previous ones is complete without variables and without touching the form
    Is it successful: go to 2
    If it isn't successful: trouble shoot the calc and or try running in EAS natively to see if that gives you ideas
    2) Run the calc outside the form but with variables included. Did it prompt you correctly.
    Is it successful: go to 3
    If it isn't. What is wrong with the variable
    3) Now attach it to the form but don't hide the prompts
    Still good go to 4
    4) hide the prompts and run on save
    And if it fails on step four then it's not picking up the right variables in the prompt. And you need to look at why it wouldn't grab the right item.
    This will isolate your problem for you and give you steps to fix it. Ultimately 99% of the time something did change in the structure for example that is impacting the calc. And when you isolate the problem this will reveal itself quite quickly.

  • 0080004528 000000 The document is not relevant for billing

    Hi All,
    How to rectify this..
    0080004528 000000 The document is not relevant for billing
    Please do give me the reply ASAP
    you will be given full points..
    Jay

    First, check the detailed error log in VF01 screen.
    For goto Edit in menu bar and select log or press Shift + F1 from keyboard.
    We may get more information on error. 
    It can be b'coz of either case mention below.
    1.Ensure that the correct copy control settings are done in VTFA (Order to Billing, order related billing) or VTFL (Delv to Billing, delv realted billing) based on your business process requirement. If either of them is not maintained, kindly maintain.
    2. Check whether your reference doc is in BLOCK status. Remove the block and proceed.
    3. Use Tcode VOV8 and select your order type.
    Maintain the order related billing as F2 and remove the value in delivery related billing if there is any thing.
    Then use tcode VOV7 and select your item category.
    Maintain the billing relevance as either B or C or F as per business process requirment. If you are using billing plan then maintain it as "I".
    Thanks & Regards
    JP

  • Error: The document is not relevant for billing

    Hi All,
    I am creating a service order have already done pricing procedure, copy control setting all and condition record but when I tried to do billing with reference to the sales order it prompts me the message saying that the document is not relevant for billing. I really have no idea where went wrong as I used the default billing type F2 only. I have maintained F2 as order related billing.
    Appreciate all of your inputs in this.

    Hi,
    First goto VOV8 T.Code and select your order type.Details.
    Maintain the order related billing as F2 and remove the value in delivery related billing if there is any thing.
    Next goto VOV7 T.Code.
    Select your item category.Details.
    Maintain the billing relevance as "B/C/F".If you are using billing plan then maintain it as "I".
    Save.
    And ensure that the correct copy control settings are done in VTFA for your order combination.
    Regards,
    Krishna.

  • The Item Is not relevent for billing

    Hi gurus
    while I am trying to create a billing document with VF01 respect to particular billing document, it is showing in the log  "The Item Is not relevent for billing" afert processing.
    I want to know what  what are the cases in which you will find this error and what should i do to overcome this error??
    regards
    Saifur Rahaman

    select ur Item category using path
    IMG -> Sales --> Sales documents --> sales document item --> define item categories
    and check in basic data whether u have marked this ITEM Category as Billing Relevance or not
    A     Delivery-related billing document
    B     Relevant for order-related billing - status acc.to order qty
    C     Relevant for ord.-related billing - status acc.to target qty
    D     Relevant for pro forma
    F     Order-related billing doc. - status according to invoice qty
    G     Order-related billing of the delivery quantity
    H     Delivery-related billing - no zero quantities
    I     Order-relevant billing - billing plan
    J     Relevant for deliveries across EU countries
    K     Delivery-related invoices for partial quantity
    L     Pro forma - no zero quantities
    M     Delivery-related invoices-no zero qtys (incl main batch itm)
    N     Pro forma - no zero quantities (including main batch items)
    P     Delivery-related invoices for CSFG - No batch split items
    Q     Delivery-related invoices for CRM
    R     Delivery-related invoices for CRM - No zero quantities
    S     IBS-DI: Order-Related Bill. Doc. with DP w/o Billing Plan
    T     Delivery-related invoices for CRM with IV in CRM
    U     Delivery-rel. invoices for CRM with IV in CRM - No zero qtys
    V     Delivery-related IV of stock transport orders in CRM

  • No reqmts/caps exists or not relevant to finite scheduling

    Hello everyone,
    I had a question relevant to capacity planning. When i have created my process order and when i am running capacity availablity check the message "No reqmts/caps exists or not relevant to finite Scheduling" is displayed. I have checked my material master and the "relevant to finite scheduling" tick is activated in the resource. Still the capacity is not checked. Not able to see why.
    I have created 4 new capacity categories and assigned the same to the resource. Any concerns there?
    Any suggestions as to why the capacity is not being calculated? Any help would be appreciated.
    Sincerely,
    Aji Kurian Mani

    Dear,
    Please check the following
    In the availability check OPJK is the setting is correct? Overall profile is the std one or you have created a new one?
    In CM01 are you getting any entry?
    pl confirm.

  • Assignning materials to a Inspection Plan by BAPI? QM

    Dear sappers,
    I a help with QP02. I need 2 Functions modules or BAPI's: 1st for assigning material-plant to an Inpection Plan and 2nd for cancelling the assignment of material-plant to the Inpection Plan automatically.
    I have checked all BAPI's in SE37, but more effort is needed.
    I know this is a real thread, so thanks for your help.
    Does anybody have any brilliant idea?
    Thanks a lot.

    Hi Gerard,
    I am looking for an automated way of assigning materials/plants to inspection plans and also for cancelling such assigments. I assume it is not far from the requirement you describe.
    Have you found a way to solve it ?
    Best regards,
    Thomas

  • No charact. values combinations relevant for planning exist!

    Dear all
    I have maintained all the class 300 and the relevant characteristics, together with the relevant maintenance such as Configuraiton Profile (CU41) and etc.
    Previously, I am able to use the LSMW I created for Tcode: MDPH (Create Planning Profile for Manufacturing Material) to perform the mass upload for the Planning Profile.
    However, until today during my upload, I face the following error:
    "No charact. values combinations relevant for planning exist
    Message no. 6P569"
    Please advise.
    Thanks

    Hi Diamos,
    I'm having scenario of characteristic values planning. I maintained 300 variant in Material master. I created planning table in MDP1 and i maintained values in MDP4. While doing the transaction MDPH it is showing warning as
    No Characteristic values combination relavant for planning exist. Message No.6P569
    with executing tick mark i maintained planning profile.
    While in PIR i need to select the characteristic values as per the requirement. Its not happening in the PIR. How to select the Characteristic values.
    Kindly provide information on this.
    Naren