Hi,
I have a DMS with MaxDB version 7.6.00.18.
I opened OSS message regarding an issue. I got a solution, however I was told that '7.6.00.18 is very outdated and no longer supported for productive systems'.
I can install the latest patch but how do I know when MaxDB version is no longer supported for productive system.
Can someone refer me to a note/article?
Thanks,
Omri

here is the details i found
Especially make sure to check in the Product Availability Matrix (PAM) http://service.sap.com/pam that the MaxDB / SAP DB version you plan to use is released for your specific SAP product!
Note 1178367 - SAP MaxDB: End of Support Dates
Cheers,
-Sunil

Similar Messages

  • Support message and change requests only for production system

    Hi guys,
    I would like to connect the solman helpesk with CHARM ( CHARM is still running ).
    In CHARM I have to create a CR only for production system. ( don't know why - but works as designed).
    In SAP helpdesk I can create support messages for every kind of system type but if I want to connect both (HD and CR) , the source system (ibase component) of the issue will copied to the CR and runs in error because of the rule (only p-system) of CHARM.
    Of course I can change the ibase to production system manually in SDCR but it seems a very error-prone method.
    Now my question: is it possible to change the ibase component due to the creation of CR by copy rule or something like this?
    Kind regards
    Rayko

    Hi Rayko,
    We do not have this option.
    Once in ChaRM, we assume that the changes will always correct an issue in the PROD system.
    I would recommend to open the tickets directly with the PROD system IBase, once the issue is also happening there.
    Best Regards,
    Fernando

  • Restrict print out of Purchase order only for Production system

    Hi,
    I want to restrict print out of Purchase order only for Production system, don't want to take it in devep or quality.
    is there any identifier to find the system is production or development.
    can anyone tell me how to restrict it,
    is there any function module, not based on client system.
    Thanx in advance
    Kesav

    Hi Kesavarathinam Vaidyalingam ,
    yes, I also use thomas' suggestion using
    t000-cccategory = 'P'.
    to determine productive client.
    Just one small hint: I found this condition as true in a test system: The admin had done a system copy to create a fresh test client - but forgot (or did not see a good reason) to change t000-cccategory = 'P. to  t000-cccategory = 'T'.
    Regards,
    Clemens

  • Content Server config for production system - oac0

    Hi all
    We are setting up content server for our ERP 2005 system, and I am wondering what best practice is for our scenario.
    We have one content server (CST) for development and test systems on host A, and one content server (CSP) for production system on host B. The Archive link configuration in dev and test points to CST. When this is transported to production, it will point to the wrong content server and I will have to reconfigure the archivelink in production to point to the correct content server (CSP).
    What is the best way to set up the production system to point to the content server CSP on host B? Should I define a new content repository in t-code oac0 in dev, and transport this to production? Should I define the new repository directly in production system??
    Please advise.
    Best Regards,
    Thomas

    Hello,
    I had the same problem a few years ago with R/3 4.7.
    I don't think there is a perfect solution but here is what I did :
    In the DEV system, in OAC0, I created 2 content repositories, one for the test sytem and one for the production. I transported these 2 content repositories in the production system.
    In the DEV system, in OAC3, I created temporary links from my business objects to my production content repository. I released the request order.
    Then I deleted these links which are wrong in the DEV system. I transported the order in the R/3 production system where these links are right.
    In the DEV system, in OAC3, I then created  the links from my business objects to  my TEST content repository. I released the second request order.
    So my config is now OK in my test and my production system.
    When we refresh the DEV system by a database copy from the production system. We just have to reimport the test request order to switch the links to be OK on the DEV system. We don't have to recreate the test content repository as it was defined als oi nthe production system.
    I am not sure that this is clear but this works for us with no problems since 2002.
    I hope this helps.
    Olivier

  • Project Management Question - timelines for Production system deployment

    Hi
    I need an expert advice on setting up timelines for establishing an Oracle Apps Production environment. We are implementing Oracle HR & Payroll at an organization.
    Our system architecture is a 2-node application tier and 2-node DB tier (RAC). RAC is configured by another party and we only have to prepare the application tier (2 nodes)
    We would be installing Oracle Apps R11i (11.5.10) with jserv load balancing on the 2-nodes
    Can anyone suggest how much time this should take to install/configure & patching of the application tier (on 2 nodes)?
    Regards
    Saira

    Duplicate post (check your other thread):
    Project Management Question - timelines for Production system deployment
    Re: Project Management Question - timelines for Production system deployment

  • Steps to configure BPM report from Solman 7.00 for productive system ECC6.0

    Hi all,
    Please given me the steps to configure Buisness process Monitoring reports from Solman 7.0 for productive system( ECC6.0, windows & database oracle 10.2),
    I wanted to create the Reports of  monitoring the buisness.
    Regards,
    Akash Basis consultant.

    Thanks for replying Volker von Gloeden,
    This thread is my first one in SDN & I am very glad that someone has given the answer ,
    I will take a look for solution you have provided & will inform you.
    Thanks again.

  • Minimum Trusted RFC's for productive system

    Hi!
    We have very strict requirements dealing with set up of Trusted RFC for productive system for ChaRM approach in SOLMAN.
    Can some one tell me which Trusted RFC's and users for the productive system do I need?
    a) Trusted RFC is not mandatory for the productive system
    b) Trusted RFC only in productive system, client: 000, users: 1 communication user and 1Dialog user
    c) Trusted RFC in productive system for  each client with users...
    Thank you very much!
    H. Thomasson

    Create the function modules in SE37 and set the remote-enabled flag in the attributes section. Then import them into XI.
    Create a custom Z table through SE11 on each system to store any data, and the code in each function module would reference it. (Either that or just hard-code everything)
    In short yes it can be done through SE37, no you don't need SE38.
    I think you're talking about function groups which is a container for the function module. You can do everything through SE37 if you use the Goto->Function Groups-> Create Group option and give it the same name as your Function Module.

  • Is HAGEO supported for SAP Systems?

    Could anyone enlighten me as to whether HAGEO (or HACMP/XD) is supported for SAP systems? I have a client who wishes to use this and believes it is fully supported. However, I have been unable to find any references to SAP systems running on HAGEO software.
    The IBM competence centre has not so far deigned to respond to my call.
    Does anyone know if it is supported/recommended or actually in use for SAP installations anywhere?
    This provides essentially HACMP over a much further distance than normal HACMP.
    We have proposed a simple HACMP cluster with mirrored disk to a second datacentre to provide DR, however our client thinks it will be cheaper to just have two systems, one in each datacentre, and linked by HAGEO.
    I have my doubts but have no evidence to the contrary currently.
    Thanks
    Andy

    For completeness, the ISCC (i.e. IBM) said (basically) don't do it. Use standby databases.
    What they actually said was that it was a very complex issue and perhaps we should get lots of IBM consulting in to answer this very difficult question.
    But i took the first answer as the likely outcome - don't do HAGEO or HACMP/XD with SAP systems.
    Andy.

  • Is vmware supported for production environment ?

    Hi All,
    Is vmware supported for production environment ?
    Thanks
    Sunny

    All,
    I'm glad someone has outlined the clear support statement that has existed for sometime between VMware - SAP.  For those of you still running on Oracle, here is some good news:
    Wording towards SAP Customers requesting support:
    "Oracle, VMware and SAP are working collaboratively to ensure support for SAP customers that use VMware virtualization for SAP solutions running Oracle DB. Functional tests are currently being performed to verify supportability of the SAP&Oracle stack.  Details will be made available in SAP note 1173954 u201CSupport of Oracle for VMwareu201D after tests have been completed. It is expected that in Q1 2010, ESX 3.5 and later releases including vSphere 4 will be supported by Oracle and SAP according to Oracleu2019s metalink note 249212."
    There is no reason why x86 platform today cannot run the most demanding workloads on VMware vSphere in a production environment.  But has noted earlier, don't get hung up on "production" - you have heaps of TestDev, SolMan TestDev, sandboxes, gateways, application servers etc that should immediately by put into a VM - once you are comfortable with your solution in-house, I'm sure you will move production instances into a VM as well.
    Below are some great resources for you to use in your quest to virtualize SAP on VMware:
    Additional Resources
    SAP Notes (for Windows platform)
    674851: Virtualization on Windows
    1104578: Virtualization on Windows: Enhanced Monitoring
    1056052: Windows: VMware ESX Server 3.x or vSphere configuration guidelines
    1260719: Detailed virtualization data using saposcol
    SAP Notes (for Linux platform)
    1122388 u2013 Linux: VMware ESX Server 3.x or vSphere configuration guidelines
    1122387 u2013 Linux: Supported Virtualization technologies with SAP
    171356 u2013 Virtualization on Linux: Essential information
    SAP, VMware (and other) benchmarks
    http://www.sap.com/solutions/benchmark/sd2tier.epx
    Introductory document u201CVirtualizing SAP applications on Windowsu201D by SAP
    https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/70f63258-bff1-2a10-9db6-
    cda6ef202bfc
    VMware and SAP
    White Papers, Success Stories, Webinars, Links, etc.
    http://www.vmware.com/sap
    SAP VMware Blog
    http://communities.vmware.com/blogs/SAPsolutions
    Regards,
    Andre Kemp
    VMware Sr. Product Marketing Manager - Asia Pacific
    Certified mySAP 2K and Migration Consultant
    Edited by: Andre Kemp on Dec 10, 2009 9:00 AM

  • Support for operating system to load blackberry 8900

    support for operating system to load blackberry 8900 javelin completely blank blank with no operating system and tries to desktop manager and nothing it can not reach by connecting with jvm and stops saying conmpletar could not load due to a connection of several steps someone could help me
    Solved!
    Go to Solution.

    claudia_0080 wrote:
    does not work
    But it does.
    Your three word response lacks any clue to any error or issue you encounted, let along a civil thank you.
    We're willing to help, but you need to cooperate.
    1. If any post helps you please click the below the post(s) that helped you.
    2. Please resolve your thread by marking the post "Solution?" which solved it for you!
    3. Install free BlackBerry Protect today for backups of contacts and data.
    4. Guide to Unlocking your BlackBerry & Unlock Codes
    Join our BBM Channels (Beta)
    BlackBerry Support Forums Channel
    PIN: C0001B7B4   Display/Scan Bar Code
    Knowledge Base Updates
    PIN: C0005A9AA   Display/Scan Bar Code

  • Log frequence for productive system

    Hello!
    We use SAP DB (version 7.7)  and use auto log function.
    We configured the redo log frequence so, that every 10 minutes a new redolog will be written to hardware drive.
    Question:
    How does this setting (log frequence of 10 minutes) affect the performance of the SAP system?
    And which setting (every 10, 20, 30 minutes) should be set for productive system?
    kind regards

    > My question is about the log settings. Untill today the redo logs were written to the drive, when the max. size of redo log (appr. 1 GB) has been reached.
    > Now I changed this settng, so I have every 10 minutes a new redolog file on the hardware drive.
    So again my question: Why did you change that? What was the reason to do so?
    > The questions:
    > Does this frequence (10 minutes) affect the performance of the server (network, SAP system, DB)?
    The default max time between database savepoints is 600 seconds - so 10 minutes.
    > What is the recommended setting to redolog setting for productive systems?
    There is no recommended setting for that, it all depends on what you are trying do. If you want e. g. a shadow database running "after" the production database for 10 minutes, then you use that 10 minutes setup. If you want an hour you configure an hour etc.
    It's all based on your setup and what you want to do.
    Markus

  • Is the JMS adapter on the J2se supported for productive use?

    Hello ,
    I am in a big confusion whether to go with simple J2SE AE for my JMS scenario or to install the J2EE AE.
    Is there any consequences or problems or difference in using the JMS scenario in J2SE AE and J2EE AE?
    It is purely for Production purpose. Whether it is supported to use J2SE AE for configuring JMS scenario in
    production systems?
    Regards,
    Soorya.

    Hi Michal Krawczyk,
    I knew that they are using J2SE AE. But i am having more specific question like, Is it feasible to configure a JMS scenario in J2SE AE environment for business scenario in production system.
    Can you please comment on this?
    Regards,
    Soorya.

  • MaxDB support for SAP XI 3.0 SP 18 (NW04)

    Hi,
    I need an advice.
    We are using SAP XI 3.0 SP 18 (NW04) on MaxDB 7.5.0.046. Because of some issues with the database we are considering upgrading to 7.6. However, it is not clear if MaxDB 7.6 is supported for NW04.
    service.sap.com/pam -> SAP NetWeaver -> SAP NetWeaver 04 suggests:
    1. tab Database platforms
    SAP KERNEL 6.40 64-BIT UNICODE  Maintained until 31.03.2013; MaxDB
    supported database version: MaxDB 7.5 64-BIT
    2. tab Process integration (PI/XI)
    supported database version: MaxDB 7.6 64-BIT
    QUESTION IS: which tab (1,2) should I trust regarding supported database version for XI?
    Best Regards,
    Piotr

    Hi,
    2. tab Process integration (PI/XI)
    supported database version: MaxDB 7.6 64-BIT  <b>is correct</b> as ..
    1. tab Database platforms
    SAP KERNEL 6.40 64-BIT UNICODE Maintained until 31.03.2013; MaxDB
    <b> is for application server ABAP</b>
    Award points if helpful
    Regards
    Umesh

  • Logical System Change for Production System

    Hi experts
    We have new CRM and BI project.  Logical System name of our ERP production system is not in naming standart. So we want to change logical system name and run BDLS in production system.
    Is there any risk about this prosedure?
    Best Regards...

    Hi,
    It is not advisable to change the logical system in production client once its assigned.
    Regards,
    Nisit

  • Add support for products that say No development planned in Vi

    I see now all cards...Even Q4-release ones, all have a non-beta driver? available...seems like your all done now?, and ahead of the game?.... I have a 8mth old Webcam Li've! Pro that has no development planned, that you could work on a driver for Vista 64bit...

    Well what im saying is they seem to be 'ahead of the game' (even tho my x-fi has the rare crackle)...Just saying it be nice if they would support products that are not that old...products that they are still selling. I bought many Creative devices..(speaker system, soundcards, webcams) as did everyone else. Would be nice to get more use out of my webcam li've pro yet.?Guess my biggest item was sound..and for the most part it is pretty decent...im sure the driver will be improved in short time.?