Maximium lot  size is 200 in MRP1 view.I have purchase order which 400 qty

Maximium lot  size is 200 in MRP1 view.I have purchase order which 400 qty , but my system is allowing to  pick 400 qty, can you please say wat may be the reason
regards
sakthi

Hello,
As others others experts are saying your maximum lot size will only work for MRP run not for manual created PR.
The system takes this value into account during the automatic lot size calculation for planned orders and production orders. The lot size of the individual orders cannot exceed this value
Regards.
Alok Tiwari

Similar Messages

  • MD04-  View Backdate information (purchaser order)

    HI Experts,
    any method to view backdated information in MD04 , example previous purchase order :-
    PO 4500039347 date 13.05.2014

    Hello
    What exactly do you mean by backdate??? From the above screenshot I can suppose that it is the document date, right?
    This information is not available on the standard MD04, however, you can include additional columns using a BAdI. Take a look on the document below for the BAdIs available on MRP:
    BAdIs for MRP
    BR
    Caetano

  • View and Email purchase order

    Hi Gurus,
    I have created Purchase order output usind Smartform. As there is no standard printing program, I have created z_program for printing, which is working well.
    But when I want to see preview using print preview button, there is nothing displayed. Also I need to be able to send output via email.
    Could you please help me?
    Thanks&regards,
    Jirka

    Hi,
    there is no output. I'm calling smartforms using this FM:
    CALL FUNCTION 'SSF_FUNCTION_MODULE_NAME'
      EXPORTING
        formname                 = 'Z_MM_PO_PRINT'
    IMPORTING
       fm_name                  =  fm_name.
    Nastaveni vystupu
      clear ls_out_opts.
      clear ls_control_pars.
    break hp_faltin.
      ls_out_opts-tddest = l_nast-ldest.
      ls_out_opts-TDIMMED = l_nast-dimme.
      ls_out_opts-TDDELETE = l_nast-delet.
      ls_out_opts-TDCOPIES = l_nast-ANZAL.
      ls_control_pars-no_dialog = 'X'.
      ls_control_pars-LANGU = l_nast-spras.
        CALL FUNCTION fm_name
        EXPORTING
          OUTPUT_OPTIONS = ls_out_opts
          USER_SETTINGS = ' '
          CONTROL_PARAMETERS = ls_control_pars
          gs_ekko    = l_doc-xekko
          gs_pekko   = l_doc-xpekko
        TABLES
          gt_ekpo    = l_doc-xekpo.
    Is there some special parameters maintenance, if I want to see print preview?
    Thanks&regards,
    Jirka

  • Material set to lot size TB not summing up orders when covering

    Hello all. I'd appreciate any input on this problem we're seeing.
    We have a material that has lot size set to "TB" (Daily lot size). This leads us to expect that demands on this material will be covered by purchase orders summing up all  the demands for this day.
    For instance we currently have 10 orders for 11. sep in different quantities from 1 to 3. Since the material is set to lot size TB we would expect to see a purchase order for 19 pieces which is the total.
    But instead we get a bunch of small purchase orders, the system doesn't appear to sum up as expected.
    Has anyone any ideas about why this may be so?
    Regards
    Simon Pedersen

    Thanks for the answers so far, It's not letting us make much progress though.
    The material is a trading good (HAWA). It has no BOM. The Collective indicator on MRP4 is not maintained (as far as i know it should not be since there are no dependent requirements involved). The demand is triggered by Sales Orders.
    The purchase requisitions get generated by the MRP run based on these sales orders. That is what we don't understand, since the material is set to TB the MRP should make a single bigger order instead of many small ones.

  • How to make lot size dependent in Material master?

    Hello Experts,
                   I created a Material master for a Finished product in Pharma industry and in work scheduling screen, under the section "In house production time in days", I see that "lot size independent". What change(s) in my settings in the Material Master can change it to "lot size dependent"?
    Does any changes in the  "Lot size data" section in the view "MRP1" have any effect on this field?
    Also one more question:
    Where is the Usage for BOM first specified? Is it in material Master or when creating a BOM?
    Thank you.
    Message was edited by: Visu Venkat

    Hi Visu
    No,Lot size data in MRP1 view will not have any effect in inhouse production time in work scheduling view.
    You need to maintain the base qty in work scheduling in order to get the scheduling time for lot size dependant.
    BOM useage is first specified only during BOM creation.
    Suppose if u maintain the BOM useage in material master before creation of BOM, then still u can create a BOM with different useage. During these case, there will be always inconsistencies.
    Hence Useage is always specified first during BOM creation.
    Hope u r clear now.
    Regards
    Vijay

  • Lot size dependent / independent

    Hi, please advise when the system uses this lot size times data in mrp4 view? Where we need to specify that whether lot size dependent or independent need to select? When the system uses this data and when the system uses the planned delivery days and in-house production days which is in mrp2? Pls advise.

    Dear,
    Planned Delivery Time use for  external procurement Like raw materials.
    In-house production time use for in house manufacture materials like HELB and FERT.
    In-house production time is independent of the order quantity.
    Lot size depnendent timing calculate from the routing.  It is calculated byadding the lead times of all operations, the float before production, and the float after production.
    You schedule the routing for a base qty The in the scheduling results screen click the button" scheduling results"
    You will get the results screen in days.
    In that screen at the botton there is abutton update material master.
    After this go to CA96 There update the material master.
    Please refer this link,
    Re: set up time dependant and independant of order qty
    Regards,
    R.Brahmankar

  • Lot Size Check at Good Receipt in MIGO

    How can I check lot sizes at the point of GR within MIGO? (as oppose to qty tolerances).
    Example, if my lot size is 100 and I raise a PO for 100 at the GR is for qty 80 (i.e not a complete lot size, which could mean a split pack) how can I get the system to produce an error message?
    Thanks in advance.

    Hi,
    U can use Shipping Instruction which is there in Purchasing Value Key(Purchasig View). Using this while GR u can give some points for Complete supply or Partial Supply.
    This is for tracking of partial supply and u can aslo this info. for vendor evaluation..
    Regards,
    Rajeev

  • Schedule with dependent lot size problem

    Hi,
        I maintain the setup/process/tear down time(base qty is 10) in Work Schedule view in MM02(dependent with lot size)..But the begin date/end date in these POs are the same when I create Production Orders with different qty.
        It seems my setting doesn't take effect..Do you have any suggestion?
    PO 1:   100 qty      Start date 11/10  End DAte 11/11
    PO 2:    1 Qty      Start date 11/10  End DAte 11/11
    PO 3:1000000 Qty Start date 11/10  End DAte 11/11
    Why the start/end date doesn't change based on my PO qty?thanks..

    Hi,
    Monst Yang wrote:
    >     I maintain the setup/process/tear down time(base qty is 10) in Work Schedule view in MM02(dependent with lot size)..But the begin date/end date in these POs are the same when I create Production Orders with different qty.
    In-house production time (lot size dependent or independent) is used for calculating the basic dates of planned orders when MRP is run with basic dates parameter (instead of lead time scheduling). However when production orders are created basic dates are always determined according to the production dates and production dates are determined by lead time scheduling. In other words, the lot size dependent production time data that you have maintained could only determine basic dates of planned orders, only if MRP is run with that parameter. In the case of your production orders, standart values of the operations and formulas of the work centers are used by lead time scheduling. Dates might be equal because scheduling formulas of work centers does not consider order quantities or labour hours, which would be multiplied by order quantities, are not maintained in routings. Investgate the production dates and scheduling of the operations in production orders. Also have MRP create planned orders to see the effects of lot size dependent times in master data. Be sure to emty the lot size independent production time in material master to avoid it overwriting lot size dependent time.
    Regards.
    Edited by: Özgen Canan on Nov 10, 2011 3:58 PM

  • Lot Size for Split Cost

    Hello,
    My company has just had SAP installed and I am trying to confirm whether there is a  general calculation in SAP or whether it is due to the configuration that has been choosen from our implementor.
    I have costed some materials we have setup as a split cost (choice of either purchased or manufactured) and setup the mixing ratio. I then cost it but SAP generates the Lot size automatically and this can not be changed.
    i.e. 90%:10% split gives a lot size of 280 (252 and 28) and 50%:50% split gives a lot size of 200 (100 and 100).
    Please can you confirm that this is normal and also if it can be overriden?
    Thank you for your assistance

    Hi,
    This is a normal behaviour of the system.
    regards,
    Sayujya

  • Material Cost Estimate with different lot size.

    What happens if the material cost estimate is run twice using different lot sizes each time  (all other parameters unchanged) for the same period?
    Will the cost estimate run later overwrites the results from cost estimate run earlier (though the lot size is different)? What is the role of lot size in a material cost estimate?

    The costing lot size impacts your cost estimate if you have lot size independent costs (i.e. setup cost).  Those fixed costs are spread over the costing lot sizee to give you a cost per unit..  Larger costing lot sizes can also help you minimize rounding issues.
    You can only have one marked cost estimate in a given period.  However, you can create and save a cost estimate as many times as you want as long as you have not marked it for release.  When you save the estimate it will overwrite an existing estimate.  You also have the option of creating multiple estimates under different versions or with different costing variants.

  • Finding Lot size in PPM

    Hi,
    where can i see the Lot Size of the PPM in PPDS PPM.
    i mean under which section, the operation part, or Activity Relationship or under PPM ?
    Thanks in Advance,
    PP.

    Goto transaction /SAPAPO/SCC03 or /SAPAPO/SCC05
    Choose the radio button choose PLAN via PPM
    Enter the product and location combination and use of a plan and click display
    Drill down the PPM and click on the PPM and on the right side of the screen u can find the lotsize in the production process model tab.
    If you want to use BAPI_PPMSRVAPS_GETLIST
    Enter some valid data and execute the bapi...
    the relevant data gets populated in the structure of the BAPI under the fields MIN_LSZ & MAX_LSZ.
    Regards,
    Srinivas

  • 'Start of Lot Size Grouping' and 'Lot Size Strategy' parameters

    Hello,
    For "by period" lot sizing procedure, could anyone explain the difference between:
    - "Start of Lot Size Grouping" flagged with  "Lot Size Strategy": 1
    - "Start of Lot Size Grouping" flagged with  "Lot Size Strategy": blank ?
    I  have played around with  both options and both produced the same result. If anyone could provide some insight , I would appreciate it.
    Many thanks in advance.

    Hi Datta,
    Thank you for your help.
    You indicated that the "The first period of the grouping horizon can be different than the period in which demand exists".
    How would the first period be different? What other elements could be considered for the start of the horizon?
    For example,   Periodic Lot of 4 weeks, Lot Size Strategy 1 or blank  and Start of Lot Sizing Group Flagged produced the exactly same result. What is interesting about it, is that with Lot Size Strategy "blank" the group production quantity is placed in a bucket where there is no demand. The results with Lot Size Strategy "1" makes sense as I have the grouped quantity placed in a bucket where I have shortage due to Safety Days requirement and not necessarily demand.
                                 w1     w2     w3     w4     w5     w6         w7            w8
    Total Demand     125     42     42     41          110     37     73
    Production (Planned)     223                    244               
    Days´ Supply     58     53     48     43     58     53     48     43
    Safety Days´ Supply     43     43     43     43     43     43     43     43
    Any thoughts? Many thanks in advance.

  • Min max lot size time based for use with SNP and PPDS

    Hi all, Is there anyway to set up time based min and max lot sizes? ie we want to have a Max lot size which is small for use with the first 3 months of our plan which starts life in SNP and then converts to PPDS and into blocks for block planning, but months 4 to 36 we want to leave as large max lot sizes as there is no need to have the small max lot sizes for the different horizon.
    As far as I can see there is only a material/plant lot size  and Max lot size and no way to have a different setting in a different time period.
    Thanks
    j

    Hi John,
    As you know, in the product master, the lot size maintenance is time-independent, so that obviously can not be used for your scenario. As per my understanding, to meet this using standard functionality, you can maintain multiple product specific t-lanes (for STRs) and PDSs (planned orders) with required lot size ranges and validity dates (for short or long term horizon). But, again since the validity of t-lanes and PDSs will not be automatically rolling forward so the updating the validities will be a challenge.
    The other option could be to enhance the heuristic functionality at lot size selection step while creating order.
    Regards,
    Umesh

  • Wrong purchase order item in inspection lot record

    we have a purhase order in which item no. 1 & 2 have the same material code .
    GR  has been done against item no. 2 in MB01.  Also the usage decision has been done
    in QA11 for the inspection lot no. generated. Now when we see  the purchase order data in
    inspection lot in qa13 the value in  purchase order item no. is  1,whereas the GR has been
    done against item no. 2.
    Please tell why the inspecton lot is picking wrong reference of Purchase order item.

    Thanks Jürgen L.     for your reply.
    I have made some test cases on development server but they are showing correct reference.  To me also  it looked program bug,

  • Print paper size for Purchase order

    Hello,
    We have purchase orders for Japan, Sweden. The requirement from business to print for A4 size and Legal size. What does Legal size mean? Does it mean 'Japan Legal Size' and 'Sweden Legal Size'.
    Sincerely,
    Sanjay

    It is a size of paper
    Non-ISO size typing paper, 81/2 inch wide and 14 inch tall, used almost exclusively in the UK, USA, and commonwealth countries. Also called foolscap size after an early trademark carried as a watermark.

Maybe you are looking for

  • Program associated with the creation of a virtual instrument of Lab View. Please help me

    I have a question with program associated with the creation of a virtual instrument of Lab View. 1.Create of virtual instrument based on the NI 9401 module fitted to the chassis NI Compaq DAQ (Ni-cDAQ-9172). Creating a virtual tool needed to implemen

  • WRT54G router IP address is the same as my modem's IP address. how to change the routers IP address?

    The broadband modem got broken and the ISP changed it to a new modem. Now my problem is I cannot use the router when they changed the modem. The ISP won't provide support since they didn't provide me with the wireless router. I've read through the fo

  • Best parent controls for iPads and iMac running on BT Home Hub

    Hi, Despite the great sounds coming from the big ISPs about parental controls, they're determined to make a really simple concept absolutely impossible. Firstly, I'm not trying to lock-down my family's access to the net, but I have two boys aged arou

  • Changes not reflecting in JSP page

    Recently we upgraded our server from orion to oc4j.When on the client side any changes were made in the java bean its not reflecting immediately in the corresoponding jsp page or the application. We tried to look at all angels like class file in web-

  • Report on several applications

    Dear Experts, I have one issue related to reporting. It is possible to report on two applications (with the same dimensions) with one evdre. If I use to EVDRE how I can get the same number of rows (members in row) when I use supress 0 if the data is