I am trying to use the macro option in MC8B to create a macro that will take one lines next month's value and use on another line as this month's value. The info structure is S076 and both of the lines are key figures in the table.
I have created/recorded a macro that will move within the same period but haven't had any luck crossing periods. Has anyone used the exit EXIT_SAPMMCP6_002?
Table P1  P2 P3 P4 P5 P6
Sales 10  11 12 13 14 15
Prodn 11  12 13 14 15
Thanks for any help,
Lorrie

It is some time since this post but since I found a solution:
If you first copy the whole table t_tab into t_tab_old if t_tab_old is initial.
Then when you add entries to t_tab you must also add entries to t_tab_old.
Then I cleared v-e-d-f fields for the new entry in t_tab_old.
Remember to sort tables by z and c fields too.
Then it worked for me.
Regards
Roy Olav Johansen

Similar Messages

  • How to create a macro for a planning type in MC8b transaction

    Hi,
    I am presently working for a product allocation demand, which have a information structiure with characteristic and key field.
    the characteristic are production allocation quantity, incoming order quantity, and open order quantity.
    i have created a planning type in which the data updation takes from the excel file to the planning type in mc95.
    but i need to create a macro for this planning type .
    can any body give the details information how to create a Macro for a planning type.
    Thanks and regards
    GopalKrishna

    Dear Gopal
    May be the link would be helpful to you.
    [Planning Types and Macros|http://help.sap.com/saphelp_46c/helpdata/en/a5/631cc443a211d189410000e829fbbd/frameset.htm]
    Drill down the left tab once you opened the link, for more information.
    Thanks
    G. Lakshmipathi

  • How to create dynamic calc account in multi-plan type application

    Hi expert,
    I have a planning application with 3 plan types.
    I created a calculation script which fixed on accounts in plan type 1 only and the calculation suppose to calculate a "dynamiccalc" account with a member formula attached. Everytime I run the script, it takes very long time and I found there are sessions at the back of essbase with "Process local xref/xwrite request" request to other plan types.
    It does not has this kind of session if I change the account to "store".
    Would like to check, is it possible to create a dynamic calc account to calculate for only 1 plan type in a multi-plan type application? Is there any special setting that I need to do to enable this? I already selected source plan type as Plan type 1 for my dynamic calc account. Please help!
    Many thanks!!
    My HP application is on version 11.1.2.1.

    Hi Jake,
    Thanks for pointing out the check box. Overlooked it and the checkbox was not unchecked, even I only wanted the account to exist in 1 of the plan type.
    However, after I unchecked and refresh now, when I run the calc script, it still trigger process at the back to the other 2 plan types with "Process local xref/xwrite request" request. What else could I have missed?
    I already added the "HSP_Nolink" UDA to all accounts in plan type 2 and plan type 3 and confirmed that there's no account with "Xref" member formula, I really don't know why it is trying to process local xref request. Can anyone help??
    Many thanks!!!

  • Test Note (Documentation Type) when creating Test Plan

    Hi Gurus.
    After we upgraded our SolMan 7.0 system from Support Pack (ST component ) level 19 to level 25,  I noticed this new field "Test Note" (Dcoumentation Type) when creating a Test Plan in transaction STWB_2.
    Initially, when I haven't chosen any project yet, this field has a list-of-values (i.e. Test Case Note, iTutor Document) but when I choose a project, the list-of-values only showing "ST". I also tried choosing another project and there is no value in the list.
    Does anyone know where this list is coming from or how I can configure this?
    It looks like project-related and but I couldn't find any settings for this.
    Can this field be turned off so it will not show in the screen?
    Thanks,
    Tess

    Hi Tess,
    The documentation type ST is the standard documentation type for test notes.
    Test notes are needed by testers to document results in detail during/after testing a test case.
    In SOLAR_PROJECT_ADMIN  there is the text menu 'GOTO - Project Template - Implementation Projects'
    and then there to the tap 'Documentation Types' to do the default settings for 'ST' for all implementation projects.
    Otherwise you'll have to change settings in the administration for each project!
    There you can assign your own documentation template for ST in the central settings.
    If you are using other project types for testing you'll have to do the same for each project type.
    Regards,
    Adelbert

  • Macros in Planning Type

    Hi, as we know, we can define Macros in planning type using T-code: MC8A, but I'm unclear about the following kinds of formulas in Macro:
    Operand          Op     Operand        Result
    Production O     L0     Sales O      StockLevel O
    Production M     L0     Sales M      StockLevel M
    I can understand the formula if the opreators are + - * /, but how to understand above formulas when the operators are L0, L1,L2... even though I know L0 means 'stock balance' and L1 means 'target stock/receipts'...
    So, would anybody tell me how to understand the formulas when the operators are L0, L1,l2...?
    Best Regards.

    Hi, Ian,
    Thank you very much for your advice.
    I had read this document before, basically I cound understood each meaning of the operators L0,L1...individually, but I still can't understand it when the operators L0,L1... are filled in the formulas, will you please explain an example when the operator is L0 or L1...?
    Please kindly advise.
    Best Regards.

  • By default how many plan types one can create in Hyperion planning applicat

    By default how many plan types one can create in Hyperion planning application?

    Hi,
    By Default,We can create 3 plan types in Hyperion planning application.

  • New feature aso plan type under planning V11.1.2.3

    HI all,
    I notice than there new feature under planning.
    the ability to create ASO plan type under planning.
    but in documentation i don't understand if this part is not available under planning licence .
    is this new feature involde to purchase new licence on essbase and in this case we have application user wich licence is needed (cpu) ?
    can some one help?
    on URL Introduction - Oracle EPM System 11.1.2.3 Documentation Library
    extract of
    Oracle Hyperion Planning New Features
    HTML
    Aggregate Storage Option Support
    Administrators can now add an aggregate storage option (ASO) database to a Planning application using Planning application administration.
    Administrators can create an ASO plan type during application creation, or they can add a new plan type using the new plan type editor. See Plan Type Editor. Write back to ASO cubes within Planning is supported.
    Note:
    To use ASO databases in Planning, you must have the required license.
    on doc I
    Oracle Enterprise Performance Management System Licensing Guide
    PDF
    Essbase Plus cannot be used to create Essbase cubes that do not
    contain data used by the Hyperion Planning Plus application.
    l The Aggregate Storage Option component of Essbase Plus may not
    be used.

    You also need the Essbase license to be able to use that functinality, probably best discussing with your Oracle account manager for the full details.
    Cheers
    John
    http://john-goodwin.blogspot.com/

  • Can a Financial Plan Type be attached to more than one Project Template

    We are working on Project Accounting through Self Service pages. For doing the Cost Budget we have created a Financial Plan Type. We attached it to a Time & Material Project. But later when we tried attaching it one more template, a Turnkey Template, it does not give us the Cost Budget-Financial Plan type in the drop down box.
    Hence, wanted to know whether we can attach a Financial Plan Type to more than one Project Template??? If yes, then why didnt we get the option in the drop down box?
    Chirag..

    Since you are not using Company code as the branch, and are using Profit centre as the branch, I dont think its right for you to set a default profit centre for any GL account in the Chart of Account for that company.
    all the SAP user in the company will be using the same company code to post, and thus, will be using exactly the same inventory account, if you set a default profit centre there, no point rite? You will need to implement a procedure to ask all the user to manually assign the profit centre during posting. Just like how we normally ask user to specify the company code before posting.
    The authorisation should be set by profit centre as well. hope this helps. Thanks.

  • MPS run, planned orders were created for all levels ?

    Hello PP members
    I ran a small scenario
    material    MRP Type     Low Level    SG           M/T Type
    A      M0         000             40              FERT
    B               PD              001              40             HALB
    c               PD              002               10             ROH
    Maintained PIRs(MD61) for material A, and ran MD41( Single Item Multi level Planning)
    As material A is an MPS item, I was expecting that it should create planned orders only for material A, but in this MPS run it created planned orders for material B & C. (Looked into MD04, where I see planned orders were created
    for all the levels)
    As per the MPS run, it will plan only for one level of BOM (in this scenario for material A)
    Any suggestions, why planned orders were created for material B & C
    please clarify

    Just check
    System must have created a dependent requirement planned order and not the planned order for requirement you put in demand management for B and C
    i.e. if you enter a demand in MD61 for B and C, run the transaction, system will not consider this requirement during MPS run. MPS run will consider the requirement if the requirement for the child is comming from parement where parent is MPS item.
    Hence you need to run MRPm for B amd C if teh requirement(not dependdent requirement from A) is to be considered.
    I hope you are clear
    Edited by: Rajesha Vittal on Jan 28, 2008 8:06 AM

  • AR Customer Setup: Communication Type Email Creates Two Email Entries

    Hi,
    AR Customer Setup: Communication Type Email Creates Two Email Entries, one with type as Email and other as E-mail.
    In AR Receivables > customer > entry > (B) account details > (T) communication or >Contact roles. While creating new customer contact communication type emai entry, upon entering email address, type as email and saving it, oracle defaultly creates another entry with same address and type as E-mail. So every time i create on email contact email address, it creates another similar with E-mail type.
    My question: Why does two entries get created and how can we avoid it.
    Thanks

    Hi and Welcome to the Forums!
    To use the proprietary RIM Push email capability, you must have an adequate data plan from your carrier. The carriers host BIS for their BB users. Typically, BIS is not available via generic data plans. Many carriers call what is necessary The Blackberry Data Plan. Whatever they call it, it is the carrier who delivers BIS to their BB users -- contact them for assistance. Once you have a BIS-capable data plan on your BB (at whatever fees your carrier will charge, btw), you will then have Personal Email added to the email setup wizard.
    Further, since this is a second hand device, you should read this and ensure that the prior owner fully conducted all steps in the Seller section...if not, then your carrier will never be able to register a BIS account to the BB.
    Good luck!
    Occam's Razor nearly always applies when troubleshooting technology issues!
    If anyone has been helpful to you, please show your appreciation by clicking the button inside of their post. Please click here and read, along with the threads to which it links, for helpful information to guide you as you proceed. I always recommend that you treat your BlackBerry like any other computing device, including using a regular backup schedule...click here for an article with instructions.
    Join our BBM Channels
    BSCF General Channel
    PIN: C0001B7B4   Display/Scan Bar Code
    Knowledge Base Updates
    PIN: C0005A9AA   Display/Scan Bar Code

  • Error validating business rules containing variable from another plan type.

    We have created few business rules in in plan type "Plan1" which we are using variable from plan type "Capex". This is how we are using it.
    "(@XREF(cpx,"Intangible Assets Finite, Gross","Unspecified","No Project","Information Technology (IT)","371064911-01"))"
    But when we validate this rule it gives the following error
    "An error occurred in: Rule:IFLJAN13.Plan1.B - Trail Balance - Capex
    A validation error was received from the Planning server 'http://hptstorg:8300/HyperionPlanning/servlet/HspAppManagerServlet?appname=IFLJAN13'.
    'Error:The member 'Unspecified' cannot be found.
    The member 'Unspecified' cannot be found.
    The member 'Intangible Assets' cannot be found.
    The member 'Unspecified' cannot be found.
    The member 'Unspecified' cannot be found. Rule IFLJAN13.Plan1.B - Trail Balance - Capex'."
    We have checked the location aliases using EAS Console and they are correct.

    Could you pls. check if you can see your BR in the location for the cube where you are unable to validate the rule?! (EAS console --> Administration --> Locations --> (right click) open)
    your user must be able to "validate or launch" the rule in this location (changeable with "Add Access Privileges") and the rule itself must be able to launch in this location (changeable with "Add rules").
    Kind regards
    André

  • Issue with plan type...

    Hi Guys,
    Unfortunately, I have clicked the "initialize workforce" command in planning webclient (v.9.2). Workforce plan type had been created. If I delete plan type now, What are implications i will see. please suggest me what to do.
    Advance many Thanks,

    To disable Workforce:
    - Edit the HSP_SystemCfg table in the application relational DB and change the values of the following fields to the given respective values. Before updating the table ensure that database backup is there to restore from in case there is a need to do so.
    - MODULE_SUPPORTED to 7
    - MODULE_ENABLED to 7
    - WF_KEY to NULL
    - WF_OPTIONS to 0
    - Go to the registry.properties usually located in C:\Hyperion\common\config and comment out the following line:
    - PLANNING_WRKFORCEPLNG_OPT=false,false
    This property is application specific and not user specific.
    Cheers,
    Jasmine.

  • Ability to restrict access to different Plan Types in Planning 11.1.2 ?

    Hi, we're running Planning/EPM version 11.1.2, with DRM and EPMA.
    We're creating a new Plan Type (Plan 2) within the Planning app, and if possible I'd like to restrict access to this 2nd plan type to only a small group of users. This 2nd plan type would be for additional what-if testing and we don't want their work to interfere with the main cube in Plan 1. Is it possible to use security provisioning or another technique so I can restrict who can have access to Plan 2?
    Also if I can do this, is it also possible to have Planning data forms that are only visible to Plan 2 and it's users?
    Thanks in advance.

    You can restrict forms easily using groups and/or direct provisioning.
    Typically you will always have security on your scenario dimension; I suggest using scenario or version security to restrict access to your data.
    Regards,
    John A. Booth
    http://www.metavero.com

  • ODI - Hyperion Planning  - Plan Type Option Missing

    Hi All,
    Iam not able to see the Plan Type option in the Hyperion Planning Application. For the application we have in planning has 5 plan types. A custom dimension is enabled for 3 plan types. When I reverse engineer the application under that dimension I should view Plan Type and Aggregation of that plan type. Currently Iam able to see only aggregation option of the 3 plan types but not plan type option.
    This plan type option would decide in which plan types members are to be created. "True" would create that member in that plan type. "False" would not create that member in that plan type.
    Any ideas ....
    Thanks,
    Ramesh

    Hi Willasi,
    Thanks for the update. I clearly understand the point you are trying to convey. Here is my scenario is that "Entity" is a standard dimension and "Department" is my custom dimension.
    As per your point
    "Entity" is enabled in "PnL","Capital","Workforce","Balance","Revenue" and when i add a entity i have a option to select in which database this entity should exist.
    "Department" is enabled in "PnL", "Workforce", "Revenue" and in this case when i add a department should that department should exist in 3 plan types is that mandatory.
    Is that any alternate option to enable that department can exist in one plan type ?
    As per my requirement some department should exist in one plan type not in other plan type
    Thanks,
    Ramesh.

  • Error in CREATE_DRAFT_FINPLAN Plan Type: Approved Cost Budget. Before you c

    I am getting below error when I call "pa_budget_pub.CREATE_DRAFT_FINPLAN"
    api to create a COST budge
    do I need to call any other API to create PLAN_TYPE.
    pls. help me if anybody has an idea
    Project: 60040107; Plan Type: Approved Cost Budget. Before you can create a plan version for the plan type, you must add the plan type to the project.

    Can you add the plan type in the project or template? That would be better than an API call.
    These need to run to perform a budget upload...
    - pa_interface_utils_pub.set_global_info
    - pa_budget_pub.init_budget
    - pa_budget_pub.create_draft_budget
    - pa_budget_pub.baseline_budget
    - pa_budget_pub.clear_budget