MD01 and MD03
Dear Experts,
I have run Total Planning using TCode MD01 , it has created a lot of PRs for a lot of Materials , BUT some materials where not listed in those PRs however when I have run TCode MD03 for a Material it created A PR , So what is the reason of not creating it using MD01 ????
Please Advice
Best Regards
Hi,
This may be due to the problem with planning at plant level MD01 id the planning at plant level and MD03 is the planning at material level. Planning file entries will be created for the newly created materils. Please check in MD20/MD21. For detailed analysis please go through the link. This will definetely resolve your issue. Thanking you.
PR not created while running MRP plant level
Similar Messages
-
MRP Run in MD01 and MD03 is different
Dears,
I am new to MRP processes. Maybe the problem is trivial maybe not.
We have a 9 000 spare parts and would like to use a limited MRP to help operators to know which number of spare parts is coming to shortage.
I set material master and made some settings in customizing for the plant I use.
After that I choose one material which stock is below reorder point.
I run MD03 and system works fine - it creates a planned order.
However when I run MD01 (or se38 ->RMMRP000) with the same parameters as for MD03 , the system creates nothing. Only telling that MRP was run and which parameters I choose.
I run MD16 to see maybe there are some planned order that system created and did not tell me, but nothing as well.
Only MD03 works if I choose the material. However, collective run MD01 is not working.
Any ideas?Hi Zhargal,
Could you pls provide some more info on MRP control parameters you use while running MRP with MD01?
Also refer the following thread for more info on MRP
MRP: Frequently Asked Questions
Regards
Mangesh S -
Dear Experts,
Please guide me to understand the following issue:
When I run MD01 for a plant, there are no materials planned. No purchase reqn. are generated.
However when I run MD03, the MRP results for the given material (in the same plant) are coming and purchase reqn. is generated.
Shouldn't this material (used in MD03) be reflected in the MRP results generating in MD01 also?
Pls guide me, where I am missing something.
Thanks & Regards,
Rohit.Dear Sir,
But it is not happening, I am running MD01 after ticking the "Display Material List", then also the material is not reflecting in the results.
However when I run MD03, by giving the material code, the purchse reqn. is generated there.
Pls guide me.
Thanks & Regards,
Rohit. -
Differences between MD01 and MD02.
Dear SAP Experts,
Please tell me the various differences between MD01 and MD02.
In which specific cases, MD01 should be used??
Thanks and regards,
Kaushik Basu.Hi,
1. Md01 is the MRP Run for plant by giving planning scope.
2. Md02 is the mrp run for single Material from plant .
Also refer following T code for your information
Menu Nodes
Transaction
Activity
Master Data
MD25
Create planning calendar
MD26
Change planning calendar
MD27
Display planning calendar
MDSA
Display BOM explosion number
MDSP
Edit BOM explosion number
MEQ1
Maintain quota file
OPPP
Explode BOM by date
MDUS
Display project assignment
MDUP
Process project assignment
MDL1
Create production lot
MDL2
Change production lot
MDL3
Display production lot
Planning
MD20
Create planning file entry
MD21
Display planning file entry
MDAB
Set up planning file entry in background
MDRE
Check planning file entry
MD01
Total planning online
MDBT
Total planning in background
MD03
Single-item, single-level planning
MD02
Single-item, multi-level planning
MD43
Interactive single-item planning
MD50
Multi-level, make-to-order planning
MD51
Multi-level project planning
MF52
Display planning table
MF50
Change planning table
MF57
Planning table by MRP lists
MF51
Planning table by production list
Evaluations
MD04
Stock/requirements list
MD07
Collective access of stock/requirements lists
MD05
MRP list
MD06
Collective access of MRP lists
MDLD
Print MRP list
MD45
Planning result
MD46
Collective access of planning result
MD44
Planning situation for a material
MD47
Planning situation for a product group
MD48
Cross-plant planning situation
MD4C
Order report
MD09
Pegged requirements
CO46
Order progress
Planned Order
MD11
Create planned order
MD12
Change planned order
MD13
Individual access of planned order
MD16
Collective access of planned orders
MD14
Individual conversion of planned order into purchase requisition
MD15
Collective conversion of planned orders into purchase requisitions
MDUM
Convert planned order into purchase requisition in background
CO40
Convert individual planned order into production order
CO41
Collective conversion of planned orders into production orders
CO48
Partial conversion of planned order into production order
COR7
Individual conversion of planned order into process order
COR7_PC
Collective conversion of planned orders into process orders
COR8
Partial conversion of planned order into process order
MDVP
Collective availability check
MDAC
Execute action for planned order
Hope it clear to u.
Edited by: Atul Zod on Nov 21, 2008 6:59 AM -
Detail diffierence between MD01 and MD02
Dear all
Detail diffierence between MD01 and MD02
one material under Plant 1000, material master all ready
currently we have one planed order against this materaial as following:
25.12.2009 PlOrd. 0242458238/Stck 0050 7.400,000 3.000,000- 4491 23.12.2009 23.12.2009
run MD01
Parameter setting in MD01
Scope of planning
Plant 1000 **********
Processing key NETCH Net change for total horizon
Create purchase req. 2 Purchase requisitions in opening period
Schedule lines 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 3 Delete and recreate planning data
Scheduling 2 Lead time scheduling and capacity planni
Planning date 23.12.2009
after run MD01, I guess the planned order number should be changed since I setting Planning mode as "3", also scheduling of planned order should be carried out, but the planned order number and scheduling are not changed.
but, I run MD02 by single material, the parameter setting as MD01 screen.
This time, planned order number changed as well as scheduling of new planned order is carried out.
so I confused what the exactly diffierence btw MD01 and MD02
Thanks for your suggestion
BennyBenny,
MD01 requires a planning file entry, MD02 does not.
Check/create appropriate Planning file entries in MD20.
To create planning file entries for all materials in background, use MDAB. Depending on the history of your system, you might also have to fix inconsistancies using MDRE.
Planning Process
http://help.sap.com/saphelp_erp60_sp/helpdata/EN/5c/33b8371a2c9912e10000009b38f889/frameset.htm
Setting up a planning file
http://help.sap.com/saphelp_erp60_sp/helpdata/EN/f4/7d279044af11d182b40000e829fbfe/frameset.htm
Rgds,
DB49 -
Defaults for MRP parameters in MD01 and MD02
How do I set a default for the 'MRP parameters' on MD01 and MD02 screens without using MRP groups? Can this be defined in configuration?
thanks a lothi John Mastram
1 Go to Transaction Put the parameter in the Transaction which you need as default,
2 then Go to Menu Click SETTING and then Save.
3 The Parameter you have saved will saved for the User.
awd if usefull
rgds
BV -
Use of MRP Planning mode 2 and 3 in MD01,MD02,MD03
Hi
I am aware of Planning mode 1,2 and 3. . Planning file entry does the job of updating appropriate planning mode like Net change or Net change in horizon, BOM re-explode or reset proposal. But,I want to understand in what circumstances we prefer to go with planning mode 2 or 3 other than 1 in MD01 or MD02 or MD03 as anyway this is covered for all necessary items in planning file entry by system. I am fully aware of the functions of all three planning modes. Just I want to understand the situation in which it will be overwritten by user selecting 2 or 3 in MD01 or MD02 or MD03. Because I have never come across such situation where I deliberately run with planning mode 2 or 3 in MD01 or MD02 or MD03.
Thanks in advance.Hi Sudhar,
Planning Mode 1 is used when:
1.Changes in date and quantity
2.Requirement changes
3.Changes in the lot-sizing procedure or MRP type
Planning Mode 2 is used when:
1.Changes to the material BOM
2.Changes to the sales order BOM
3.Changes to the phantom assembly BOM
4.Changes to references assigned within BOM
5.Changes to material classification
Planning Mode 3 is used when:
1.In-house production time changes
2.Planned delivery time changes
3.Scheduling margin key changes
4.MRP controller changes
Regards
Vinod
Edited by: Vinod Mohan on Mar 1, 2010 6:41 PM -
I've encountered a problem that I'm hoping will help me understand the MRP process a bit.
I have a material with an independent requirement with no existing inventory. If I run MRP using MD01, MRP doesn't plan the material. However, if I use MD02, it plans it correctly, creating planned orders for it.
I'm hoping someone can tell me what's going on.
Thanks in advance.
RossRoss,
Display is MD21. If you are a planner, you should probably have access to MD20 Create planning file entry, MD21 Display planning file entry, MDAB Set up planning file entry in background, and MDRE Check planning file entry
You might have access to view the table that contains the planning file data. The name of the table is usually MDVM for regular MRP(not planning area MRP; not long term planning MRP). Use the table browser SE16N or SE16, enter the table MDVM, and execute. You are looking for a lack of an entry against your material/plant.
Best Regards,
DB49 -
Hi, pls advise my understanding is correct or not.
1. md01- instead of running md02 for individual header finish materials, we can combine all finish mat planning thru md01. aslo it covers all the materials of a plant for all types of requirements (pir's, s/o etc).
2. the difference between mdbt and md01 is background planning and fore ground planning. other than that there is no difference.
3. manual re-order point mrp type can also generate procurement proposals while running md01 or and mdbt run.
pls advis whether above undestanding is correct.Hi,
we can combine all finish mat planning thru md01. aslo it covers all the materials of a plant for all types
of requirements (pir's, s/o etc).
MD01 / MDBT / MD02 will plan not plan for materials with MRP type MPS (M0/M1/M2/M3)
Regards,
Dhaval -
Hi experts!
I need to disable Planning Mode option = 3 at my system, because users are not authorized to delete physically.
We have been investigating butwe didnt find any security point to limit this activity.
Do anyone know if there is any way to restrict the use of this option of the parameter at MD03?
Thank you in advance.
Best regards,
cecilHi,
One suggestion:
For any Organization the MRP Run is very crucial..
Only few people should be authorized to execute the MRP (MD02 & Md03)
Only system administrators can have authorization for MD01.MDBT.
So, remove authorizations for MD02 and MD03 for most of the users except the Department Heads..
Schedule MRP in the background at night..
Hope this helps..
Revert for further discussion..
Regards,
Siva -
hi,
What are all settings to generate Purchase Requisitions through MRP run? Also, if, i wanna automate creation of Purchase order from Purchase Requisition (not manually). how to achieve this?
thanks..Hi,
1. Get PR trough MRP run
1a, You have to have proper master data settings (e.g. material master: MRP type "PD", procurement type "F")
1b, Proper MRP creation indicator shoudl be used in MD01 / MD02 / MD03.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
1c, Your planning situation also influences whether you get PR or not. If there's no need to procure anything (e.g. you have sufficient stock level or you have no demand for the goods > MRP won't generate procurement proposal)
2. Convert PR to PO
It depends on your master data settings (material master, source list, QA, outline agreeemts, etc)
If you have proper master data settings and during MRP run it is possible to determine the source of supply, you can use ME59 to get the POs from the PReqs (otherwise you have to use ME57, ME58 too).
http://help.sap.com/erp2005_ehp_04/helpdata/EN/4c/420d29470a11d1894a0000e8323352/frameset.htm
But you can't get PO as the result of MRP run in standard system - you get PR (or PldOrd) and you have to convert the PR to PO (or PldOrd > PR > PO).
Regards,
Csaba -
Hi Gurus,
My client has a problem, MRP is running OK with MD02 and MD03 tansactions but no materials are planned when MRP is run through MD01at plant level.
Can anybody throw some light what could be the problem?
There is no error message either.
Thanks in advance
ShaileshDear PP and QM
I think there is a misunderstanding
The reason why the materials are getting planned via MD02/MD03 is because here you are forcefully running the MRP for the material,System wont look for the planning file entry where as when run through MD01 system will check for planning file entry
Just though to explain the reason behind such behavious, there is no intention to prove you wrong
Shailesh
Proceed as suggested by other expert,Even i feel that planning entry might be missing
I'm not sure how the materials were uploaded in the system,if it is via BDC then you normally one setting is there(update planning file) if it is not done then planning file entry will not get created ,we have to create it manually
Hope this helps !!
Thanks
SVP -
Give some pp module tcodes used in bdc and their purposes
give some pp module tcodes used in bdc and their purposes
thank you,
Regards,
Jagrut Bharatkumar ShuklaHi
Important PP tables are..
Master Data:
CRHD Work center header
MAPL Allocation of task lists to materials
PLAS Task list - selection of operations/activities
PLFH Task list - production resources/tools
PLFL Task list - sequences
PLKO Task list - header
PLKZ Task list: main header
PLPH Phases / suboperations
PLPO Task list operation / activity
PLPR Log collector for tasklists
PLMZ Allocation of BOM - items to operations
Production Orders:
STKO BOM - header
STPO BOM - item
STAS BOMs - Item Selection
STPN BOMs - follow-up control
STPU BOM - sub-item
STZU Permanent BOM data
PLMZ Allocation of BOM - items to operations
MAST Material to BOM link
KDST Sales order to BOM link
AUFK Production order headers
AFIH Maintenance order header
AUFM Goods movement for prod. order
AFKO Order header data PP orders
AFPO Order item
RESB Order componenten
AFRU Order completion confirmations
Planned orders and Independent requirements:
PLAF Planned orders
RESB Material reservations
PBIM Independent requirements for material
PBED Independent requirement data
PBHI Independent requirement history
PBIV Independent requirement index
RKPF header
Capacity Planning:
KBKO Header record for capacity requirements
KBED Capacity requirements records
KBEZ Add. data for table KBED (for indiv. capacities/splits)
Important Transcation:
CA usually reserved for routing type transactions. This includes reference rate routings and rate routings.
CA31, CA32, CA33: Reference Rate Routing Creationg
CA21, CA22, CA23: Rate Routing Creationg
CA63, CA64 Change documents for Routings
CA80, CA85, CA90, CA95, CA98: Where Used, Replacing Routings, etc.
CR Usually reserved for work center type transactions.
CR01, CR02, CR03: Work Center Creation
CR05, CR07, etc. Work Centers analysis, etc.
CS Usually reserved for BOM type transactions.
CS01, CS02, CS03 Bill of Materials
CS07, CS08, CS09: Extend Bill of materials
CS11, CS12, CS13: Explode Bill of materials
F Usually reserved for financial type transactions
A Usually reserved for financial type transactions.
LM Label Management type transactions
MB Usually reserved for inventory type transactions
MB51 Material document history
MB1A Goods Issue for Scrap
MB1B Goods transfer
MD Usually reserved for MRP type transactions
MD01, MD02, MD03, MDBT - MRP Run
MD04, MD07: Stock/Requirements List
MD05, MD06: MRP List (static)
MD11, MD12, MD13, MD16: Planned Order creation, etc
MD20, MD21: Planning file
ME Usually reserved for Purchasing Type Transactions
ME01, ME03, ME05 Source Lists
ME11, ME12, ME13 Info Records
ME21N, ME22N, ME23N: Purchase Order creation
ME31L, ME32L, ME33L: Scheduling Agreement Creation
ME51, ME57 Purchase Requisitions
ME38, ME38: Schedule Line display
ME37: Stock Transport Scheduling Agreements
ME27: Stock Transport Orders
MM Usually reserved for material master type transactions:
MM01, MM02, MM03: Material Master Creation
MM04 Change Documents
MM06: Mark for Deletion
MM60: Materials List
V Usually reserved for Sales and Distribution type transactions
VA Sales Orders
VL Deliveries
VT Shipments
VD Customer Master for Sales
VK Condition Records
http://www.sap-img.com/sap-pp.htm
http://www.erpgenie.com/sapfunc/pp.htm
Reward if usefull -
When MRP run through background process in MDBT open PR and PO not comming?
Hi,
When MRP run through backgroung process in MDBT open PR and PO not coming in MDBT result.
Pls advise accordingaly.
Regards
rkRam,
Either I am totally misunderstanding your statements, or your business people are misinformed.
The output of MD01 (MRP total run in foreground) and the output of MDBT (MRP total Run in Background) ARE IDENTICAL, provided you have selected the same parameters.
Neither output contains a discrete listing of open Purchase orders and Purchase requisitions.
Standard output of both MD01 and MDBT are:
1. List of materials processed, with exception messages
2. Statistics
In addition, both of these programs also write MRP records to the MRP databases, provided that the "Display Material List" parameter is set. In this case, both of these programs will produce data that can be further reviewed and managed in MD05 and MD06. MD06 is the tool that most planners use to process the MRP database info.
If you wish to see a listing of the entire MRP results (either MD01 or MDBT), then execute transaction MDLD. This will produce either a spoolfile or a printed document.
For the PO or PR listings, review my earlier suggestions.
Rgds,
DB49 -
Automatic production order creation and confirmation
Dear all,
I am in a situation where i have to configure the SAP system in the following ways:
1. From the planned orders automatically production order should be created today for the next day production and the end user will re-declare the quantity if there are any changes in the production order.
2. If there are no re declarations to be done SAP should automatically release production order and save it.
3. After the goods are produced the confirmation of the order should happen automatically from the measuring points.
4. In the order confirmation, the storage location for goods issue should be automatically captured from the goods issue slip.
5.After the confirmation of the order the goods receipt should happen automatically.
Please suggest me whether these are possible in SAP or not. If yes please tell me the procedure.HI,
I hope this will give you the clear picture
actually my scenario is:
Finished good= x
work centers involved = WC1, WC2.
HERE BOTH THE WORK CENTERS ARE IDENTICAL, INPUTS ARE SAME AND OUTPUT IS THE FINISHED GOOD "X" FOR BOTH THE WORK CENTERS.
I HAVE A ROUTING FOR THE FINISHED GOOD "X" WITH TWO GROUP COUNTERS AS (1)WC1 AND (2) WC2
When i create plan in md61 for 1 month and when i do mrp run in md02 it will create the planned orders and we can see the stock requirements in md04 and when we double click on the planned order we can convert them into production orders.
But my users requirement is, he want to run the mrp in md01 and after that automatically each day the production order should be created.
example with the above work centers and materials:-
i have done the mrp run for "x" for November and December months
i want to produce "x" of 200 kg on 30.11.2011.
so SAP should generate production order for WC1 AS 100KG AND WC2 AS 100KG on 29.11.2011 at 5 pm automatically and the user will release the order.
similar example:-
i have done the mrp run for "x" for November and December months
i want to produce "x" of 400 kg on 03.12.2011.
so SAP should generate production order FOR WC1 AS 200KG AND WC2 AS 200KG on 02.12.2011 at 5 pm automatically and the user will release the order.
Please suggest me how to do the configure settings for my users requirement.
Thanks,
Aravind.C
Maybe you are looking for
-
<blockquote>Locking duplicate thread.<br> Please continue here: [/questions/777244]</blockquote><br> I do not want recently typed pages in the URL Location Bar to remain there.
-
I have read all of the discussions regarding the invertors and getting power on a plane....and the airline I'm flying with (Malev) I doubt they will even have powered seats so I'm just going to purchase an extra battery and occupy my tiIme with books
-
Do you have to buy the Nike+ workouts?
Do you have to buy the nike+ workouts, or can you just use your own music with the voice still telling you your speed, etc.
-
How to display the real recording time of day in a video?
I want to create a video in which the real recording time of day is displayed though the whole video. I already tried with the timecode generator, but this shows the time progress of the video being played back. What I need is the real recording TOD
-
When I go to add my outlook email it is not listed as a choice so I click add new account and then once I enter my information, It says incorrect and I used the information settings off of here. I am using ios6