MD04 problem

Gurus
i have scenario were in i have a production Order and associated with it is purchase requisition . Now the Porduction Order is  Arcived but the MDO4 stikll shows the Purchase Requisition that is associated with this Porduction Order , do SAP have Any Fix Program apart from  Fix Program SDQR....which is being used to correct the Demand .
Thanks in advance
Milind

Hello Milind,
SAP Note No. 115899 should help.
Best regards
Gabriel

Similar Messages

  • MD04 Problem(MRP Parameters for plant not maintained)

    Sir in tcode MD04 i am getting error message no. 61273 (MRP Parameters for plant not maintained).What to do?
    i am online.

    Hi
    Maintain plant parameters in T code : OPPQ
    or copy plant properly
    Tarachand

  • Fullfil sales order and deliveries are still appearing in MD04.

    Hello Experts
    After an upgrade Ehp6.4 to Ehp6.6 the fullfil sales order and deliveries are still appearing in MD04.
    We runned SDRQCR21 and released the documents from MD04 but when the users create new sales orders and deliveries and completed them the reservation does not disappear from MD04.
    My Availability Check is CH
    Check.rule (SD order) and (SD delivery)
    Somebody could tell me how can I solve this issue. 
    Thanks for you help

    Please check the document status in VBUK or VBUP table may some of the documents partially PGI'id
    Also please refer the below document which is very helpful.
    MD04: Problems with sales orders
    thanks,
    srinu.

  • Dependent requirements not clearing up

    Hi gurus,
    I was wondering if someone could throw some light on this strange behavior. I tried to check all settings and it did not make any sense to me. we have a material A and material B. material A is the component in the BOM of Material B. We get sales orders for material B. I see in the document flow of sales order of material B that it was PGI'ed yesterday and we have MRP job NETCH that runs everynight. I do not understand why the MRP element with CUS ORD still shows up in MD04 for material B and as a result the dependent requirements also shows up for material A in MD04. what could be the problem. Oh and by the way we use strategy group of 52 on the material master for B.
    Any ideas?
    Thanks
    Ravi

    Hello Ravi
    Take a look on the following documents that I wrote about the most frequent issues on MD04:
    MD04: Problems with sales orders
    Frequent issues on MD04
    If the sales order itself is still displayed on MD04, you should try to run report SDRQCR21 to check for inconsistencies.
    If the sales order itself is not displayed on MD04, but the sales order special stock is displayed on MD04, you should take a look on note 1723507.
    If you still cannot solve the issue, please provide a screenshot of MD04.
    BR
    Caetano

  • Fix for SDRQCR21

    Hi All,
    Has SAP come up with permanent fix for this MD04 problem?
    Please let me know. I would really appricite any response on this. We are getting this issue quite frequently. We need to run this report quite frequently. We want permanent fix.
    Thanks,
    Sanjeev

    Hi,
    the requirements errors often occurs when, sales order and/or delivery processing user-exit , are implemented incorrectly.
    The following OSS note
    [Note 415716 - User exits in delivery processing|https://service.sap.com/sap/support/notes/415716]
    contains the guidelines for the  proper implementation of the exit routines in delivery processing.
    The same rules, with the exception of some methods and table names, are also applicable in the sales order processing.
    Andrea

  • MRP type change from VB to PD - Problem in old requirements MD04

    Hello Experts,
    For MRP run we were using VB as MRP type in material master. We upload schedule in scheduling agrrements. At time of MRP run system was only considering based on reorder point only.
    Now business disicion is change and we have changed MRP type as PD. So at time of MRP run system should consider based on requirements i.e. from scheduling agreement. Now here is our problem. System consider and shows old scheduling requirement also in MD04. Let me explanin you in detail. Before changing MRP type from VB to PD, there were some schedule  available in system. after that we have uploaded 2 3 more schedule. But system still shows old schedule availabe at time of MRP type change.
    Can you please help me how to resolve this?? How can we clear old requirements from system.
    Thanks in advance for your reply.
    Regards,
    Piyush

    Hi,
    Not too sure but , try # SDRQCR21
    Regards
    Chandrasekhar

  • Problem:FM - ME_CONFIRMATION_INSERT_GR,changes are not reflecting in MD04

    The problem with the Function modules ME_CONFIRMATION_INSERT_GR is that it updates the table EKES directly because of which the data in MD04 has two lines even if we confirm the full quantity. One line with MRP Element as ShpgNt (shipping notification) and another line with MRP Element as POitem. Instead it should display the full confirmed quantity in one line with MRP element as ShpgNt.
    Also, BAPI_PO_CHANGE doesnu2019t work for updating the confirmation data.
    Is there any way to reflect the change into MD04 through my Zreport .

    The problem with the Function modules ME_CONFIRMATION_INSERT_GR is that it updates the table EKES directly because of which the data in MD04 has two lines even if we confirm the full quantity. One line with MRP Element as ShpgNt (shipping notification) and another line with MRP Element as POitem. Instead it should display the full confirmed quantity in one line with MRP element as ShpgNt.
    Also, BAPI_PO_CHANGE doesnu2019t work for updating the confirmation data.
    Is there any way to reflect the change into MD04 through my Zreport .

  • Problem in MD04 with schedule lines ME38

    Hello gurus,
    I've got a problem with ME38 and MD04.
    ME38 shows some quantity schedules on a date but in MD04 these schedules are not shown.
    Thanks for support.

    Hi,
    Check the GR column on the far right of the display of the schedule lines (MRP doesn't display lines where the sched line qty = GR qty)
    Hope that answers your question
    Alex Dixon

  • Problem when trying to run MD04

    I am experiencing problems when trying to run my MD04 Collective access, for vendor say X & Y.
    I buy many products from these vendors and I therefore need to have access to place these orders anytime of the day (as it can take more than one hour to raise the orders) and it is only allowing me access last thing in the day for some strange reason.
    Please can you look into this - I'm not sure if there is a server issue due to the size of the job, but I must have the ability to undertake this task.
    I tried to limit the selection further but still the problem is not getting solved.
    please tell me what else can be done?
    Thanks in advance.
    Regards,
    Sonal.

    Basically when i am trying to do collective access thru MD04 I am putting plant and vendor.
    the sys is not displaying the stock reqmt list but is getting time out.
    I tried limiting further by putting delivery dates, MRP controller but still it is not working.
    What else can be done?
    Thanks & Regards,
    Sonal

  • MD04 calling CO40 to convert PLOR to Prod Order Problem

    Hi,
    I have the following Problem,
    When converting Planned Orders to Production Orders in MD04 and calling C040 this does not take account of my BOM status which is set to block, but if I create a Production Order directly in CO01 the BOM status is referenced and the creation of the Production order is denied but this does not happen with MD04 calling CO01.
    I have searched OSS and found Note 453755 which is the exact problem I am having, but the note only refers to version 4.6c however we are on 4.7.
    Anyone have similar problems please let me know how you resolved it.
    Thanks

    Pls. check whether same Alternative BOM is used
    1) While Directly using CO01 &
    2) While calling CO40 from MD04
    It might possible that one Alternate BOM have 'Deletion Flag' and another doesn't have.

  • MD04 to CO40 - PLOR conversion to Prod Order Problem

    Hi,
    I have the following Problem,
    When converting Planned Orders to Production Orders in MD04 and calling C040 this does not take account of my BOM status which is set to block, but if I create a Production Order directly in CO01 the BOM status is referenced and the creation of the Production order is denied but this does not happen with MD04 calling CO01.
    I have searched OSS and found Note 453755 which is the exact problem I am having, but the note only refers to version 4.6c however we are on 4.7.
    Anyone have similar problems please let me know how you resolved it.
    Thanks

    Hello,
    Even the Note is applicable to only 4.5Version, Check if the Code is already incorporated in your current version. if not you might need to implement that note.
    Hope this helps.
    Rajeev

  • MD04 release reject problem

    Sir in MD04 when i am converting planned order to production order i am getting following message also release is rejecting :-
    No valuation variant found for valuation area AMBA
    Message no. C6015
    Diagnosis
    The system could not find a valid valuation variant for valuation area AMBA.
    If the valutaion variant is not assigned to a valuation area, this will have the following effect on the valuation of the goods receipt of the finished product:
    u2022     If the price control indicator in the material master of the finished product is S, it will lead to price differences.
    u2022     If the price control indicator in the material master of the finished product is V, the goods receipt will be regarded as a delivery free of charge.
    Procedure
    Assign a valuation variant to valuation area AMBA in the configuration menu.
    Can u please tell me in which tcode i have to do customization to overcome above error message.
    I online wait.

    Dear,
    You must  check the maintenance of "Valuation variants for order  (Transaction OPK9)", which you can also access via the Customizing path "Production --> Production orders --> Integration --> Define valuation of goods received":it may be that an assignment valuation area - valuation variant is missing."
    Regards,
    R.Brahmankar

  • Shedule lines problems in md04

    hi all,
    even thru we split the dep remqt from the monthly to day wise from the planning table entry for the final product and run mrp
    instead system create the daily schedule line , it give it the single schedule line for the whole month.
    what will the reason. pls give suggestion on this.
    Edited by: raj on Aug 5, 2009 10:27 AM

    Hi,
    should be only a draft problem.
    i updated already hundreds of other documents (Invoice / Orders / ...) and never faced that problems.
    follow Petr's suggestion and make a bug report.
    lg David

  • MD04 overview tree problem

    Hi SAP experts i hope you can help me on something, i need to know the requirements for the Overview tree to work with my materials, i have a group order that i would like to view in the overview tree but i can only see the FERT material, i cant see the other two HALBs, i hope you can help me out, if you need more info please tell me.

    German ,
    It does not matter if your MRP type is M0 or PD. You should be able to see the entire Order structure if you have the MRP  element (planned order/ production order ) for that material. 
    If there is no such MRP element either due to no requirement ( sale order /dependent requiremnt) or Excess Stock (stock more than requirements) then you cannot see the Order Tree in the Overview screen. The Order tree will display only if there is a order( plan or production).
    Hope this explains your issue. If you have further questions please come back.
    Thanks,
    Ram

  • Planejamento de necessidades - MD04

    Prezados, bom dia.
    Estou com uma situação nova para mim, na tela de planejamento de materiais (MD04) está aparecendo uma necessidade para uma ordem de venda (OrdCli) tipo de necessidade 011 - Necessidade remessas.
    Porém não mostra qual a ordem e possivelmente é um erro/ problema pois a necessidade é de 2008.
    Já rodei o programa sdrqcr21 mas não corrigiu o problema.
    Alguem tem alguma sugestão do que pode estar acontecendo ?
    Tks,
    Rodrigo

    Olá Rodrigo,
    Por favor, veja se o grupo MRP está associado no mestre do material.
    Transação OVZI é onde o "requirement" é associado (nota 207942).
    Você também pode rodar o programa report ZSUMBD_INITIAL_FIND como explicado na nora 907053.
    Esper poder ter ajudado,
    Ruy Castro