Methods of procuring an asset

Dear Friends,
I have gone through forum and reviewed all threads relating to capital/asset procurement but still i am unclear on the methods of procurement.
Can some one clearly give difference between why should we procure asset
1) with material code
2) without material code ( using short text instead)
I have referred the below thread Asset (Capital item purchase) for the same but have not found a precise reply for the same.
Please advise & help as this is one of the queries raised by our client..
Rgds
Nandu

Hi;
You can Procure asset with material code or without material code
As per my suggestion go with material code it will  help much better to track everything related to asset
check following link it will clear you
[http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/808c60ca-013b-2c10-34a2-94d1eb442e6f]
Regards
Kailas Ugale

Similar Messages

  • Procurement of assets

    Hi friends,
    Our client wants to handle the procurement of assets like computers, tables, chairs etc.. I feel this can be handled thru projects. But is there any advantage if I handle it thru PS?
    Normally how is this procurement handled?
    This is a bit urgent. Please help.
    regards
    Pratap.V

    Dear vishnu
    Let me illustrate, there two types of scenarios
    1) procurement of material, which needs to be capitalized. - Normally In this case(which are direct procurement type, ex: purchase of computer, chair, etc.), no need to use PS module. Its unneccarily complicating the process .
    2) procurement of material or services/material with long lead times (generally more than 6 months) with part deliveries, part payments, etc which needs to be capitalized.(ex: construction of new plant, office building) - PS module functionalites are very helpful.
    Regards
    Murali

  • Procurement of Assets and MRO items

    HI all,
    Can anyone share with me if return delivery is applicable to procurement of MRO items(acct assigned K) or Assets(acct assigned A)?
    Not sure if return delivery can be done for consumable materials..Hope to have a clearer concept on return deliveries..
    Thanks.

    Not possible with stadard functioanlity but you can make it work around
    like creating dummy non valuated material and take in the stock and when you need to return use this material
    but make sure that bussiness really want to da that

  • Procuring fixed Assets

    Hy
    How do you define fixed assets in inventory and what special attributes must be checked for it.How do we procure and recive in inventory please provisde details regarding this

    Hi,
    what could be the join b/w fixed asset and order management.
    Thanks in advance!!!
    Ramya

  • Procure to Asset  Complete Cycle

    Does anybody know all setups required to complete cycle from creating an item for asset ,creating PO, transfering asset to FA(rather than inventory) and paying this invoice etc .does any body have this test cycle-

    1.Create an item that is purchasable but not inventory item and assign and expense account which is equal asset clear account the asset category of your choice.
    2.Assign asset category to the item in the item master
    3.Enter a PO for this item
    4.Make sure accrue on receipt is not checked (which should be by default)
    5.Check the distributions that the account is defaulting as the account you have chosen in the item master
    5.Approve the PO
    6.Match the PO to the invoice and see that the account that you have used in the PO distributions defaults into the invoice distributions.
    7.Track as an asset flag should be checked here as well
    8.Validate and account the PO and transfer that to GL.
    9.Run the Mass Additions Create
    10.Run Mass Additions Post in FA
    11.Asset should be created.
    Thanks
    Nagamohan

  • Capturing of Excise for  Procurement of Assets

    Dear SAP Gurus,
    When excise invoice is captured, material is a capital goods and the
    material attracts more than two types of duty ( ex: BED and Education
    cess) . Error "Balance in transaction currency " (F5 702) is
    encountered while posting excise invoice if the duties are having odd
    numbers.
    Example: Total BED duty = 160.11, Total ECS duty = 3.23. Then while posting the excise invoice  error message is encountered.
    Our system is version 4.6C, and we have implemented SNote 763141 Note
    763141 - Error: Balance in transaction currency - J1IEX.
    We're not sure why we're still facing this error. Can you help? Will reward for any helpful suggestions. Thank you.
    regards,
    Jules
    Message was edited by:
            Ju Lee Tan

    Hi Kedar,
    My previous simulation shows that Debit and Credit Balance doesn't match because of this odd decimal reason. And when you do a simulation in J1IEX, it will be display mode, thus, user will not have a chance to adjust the values.
    Any idea how to resolve it?
    Thank you for your reply and time.
    regards,
    Ju Lee

  • Budget Check against Asset Procurement

    Hi,
    We have defined the budget profile and assigned the same in the project and we have loaded the budget against WBS element of AED 10000 and we define the tolerance limits as below
    Usage %    Indicator
    75              Warning
    85              Warning with mail
    100            Error message
    And also we assigned the same WBS element is asset master record and while we procuring the asset through PO for AED 9000 it is giving an error message of funds committments is less than 1500 by budgeted amount.And if we give lessthan  AED 8500 it is working fine and also for more than AED 10000.
    Why it is giving the error mesage number BP613 even the funds committments were less than budgeted amount.

    You can achieve your requirement thru PSM-Funds Management , by creating commitment items, you can control the asset procurement.
    First search on the web for the PSM-FM documentation and then configure it.
    And for the Acc Assign Cate A, change the field statuses for FM related fields.

  • Capital Goods(Asset) Procurement

    Hi all,
    I have a scenario where company is procuring an asset and the vendor from which the company is procuring the Asset is sending that Asset in different parts like for a whole machinery the vendor is dismantling at its end and then assemble inside the client premisis but sending in different shipements
    Now requirement is In the PO there is only one line item with Asset code, GR is to be done for all the Dismantled parts and for that parts material master is not maintained, on some of the dismantled parts excise entry is required.
    When is Asset is assembled i have to show the GR entry for complete asset and have to update my RG23C register for both Part1 and Part2 entry.
    How to map such a scenario??
    Regards
    Akshit

    Dear ,
    I feel u want to take the Credit for the Parts material.
    In J1IEX  use the option without PO & take the credit.
    In this u don't ahve to create the material code,by using material Description of u can take the credit.
    Pi. use this .
    Biswajit

  • Asset calculate depreciation by unit of production method

    Hello Everyone,
           since SAP go live , our SAP system use calcuation depreciation by straight line method in all asset class
    but now we would like to change  asset class "Machine" calculate depreciation by unit of production method .
    we want all asset in asset class "Machine" have their own depreciation also.
    such as Machine A can produce 10,000 unit in life time  , 2014 period 1 produce 500 unit , 2014 period 2 produce 200 unit ,so each period have different depreciaiton value
    Machine B can produce 300 unit in life time , 2014 period 1 produce 22 unit , 2014 period 2 produce 14 unit , so each period have different depreciation value
    so each asset number should their own depreciation value.
    I read some SAP document about unit of production calculation method such as http://help.sap.com/saphelp_46c/helpdata/en/dd/ea2c7dd435d1118b3f0060b03ca329/content.htm
    and other sources.
    it's look like that SAP use depreciation key ,and transaction code AO25 ( to specify production unit in each period)
    so if we have 10,000 asset number that want to use calculate depreciaiton by unit of production method.
    do we have to configure 10,000 depreciation key  and then use transaction code AO25 to specify production in each period ?    
    do we have better solution to calculate depreciation by unit of production ?     If possible we do not want to configure 10,000 depreciation key.
    Thank you in advance

    Hi
    Check this out
    depreciation calculation Unit of Production Method (Remaining No. of units)
    http://scn.sap.com/thread/429831
    Cheers

  • Asset Procurement  Cycle need info in sap mm

    Hi All.
    Thanks  in advance for all sap mm dudes.
    Need Asset procurement cycle steps in sap mm.
    From creation of asset,
    Then any inforecord, source list, etc.
    Next Purchase order,
    Next MIGO details like FI Documents,
    FINAL MIRO  with Transaction details.
    Regards.
    Parameshwar
    Note : Search forum or in other sap resources(articles,sap help,wiki etc.,) before posting.
    Edited by: Jeyakanthan A on Jul 22, 2011 2:36 PM

    steps to process the procurement of Assets:
    1. Create requisition ME51N
    2. Release PR if release procedure applicable- ME54N
    3. Create Asset Master by Finance department.- AS01
    4. Create PO (ME21N) with ref to the requisition. Ensure that you select the Account assignment category as 'A'. Enter the asset number, in account assignment tab. The PO can be created without material or if it with material to keep a track on the stock, you can use Non-valuated material type.
    5. Release PO - ME29N or ME28
    6. Print PO (ME9F)
    7. Carry out GR against the PO (MIGO)
    8. Advise finance to update the Asset Master (AS02)

  • Asset material procurement

    hai,
    Anybody knows the procurement of Asset materials.
    Tell me the steps from material creation to Invoice verific..
    Thanks

    U can do it many  ways . For example
    1) Non valuated( UNBW Material type) Material code can be created for this purpose and can be used for asset procurement . Probably this materials will have qty tracking . Procurement will happen with asset account assignment. when ever GR or IR is done , cost is booked to the asset.
    2) U can procure the material and keep it in inventory and the material can be issued to the asset account from the inventory by movement type 241.
    3) asset procurement can be done without creating the material also . in this case the tracking of the asset by material is not possible.
    Based on the requirement , any one of the above can be adopted
    Regards
    Mani

  • Two procurement methods in B1

    Hi,
    Is it possible for us to have more than one procurement method in SAP B1? Instead of make and buy, can we have make/buy in one category? If no, is there an addon or anything we can do to make this possible?
    Also another question is it possible to group production orders into similar groups like in the bom structure?
    Thanks,
    David

    Hi David,
    Not Possible to Create UDF on Planning Data Tab of Item Master for Planning Method or Procurement Method.
    Please check with your Developer so that he can Create More Options with the help of SDK.
    Hope this help
    Regards::::
    Atul Chakraborty

  • Exporting library assets to frame 1 causes delay

    I'm fairly new to Actionscript 3, just trying to puzzle something out.
    I have several small movie clips saved in the library of myCS4 Flash.fla file, I want to make them available to dynamically add to the display list as children, based on the button clicks of the viewer. I can get it all to work fine via Symbol Properties > Linkage > Export for Actionscript.
    BUT - When the movie clips are set to "export for actionscript" from the  Library, playback seems to hang on frame 1 until all of these  exported assets have downloaded. The big problem is that I have an ultra-simple but totally custom preloader/progress animation coded in a loop in the second and third frames, which kicks out to frame 4 and continues playback as soon as the download is complete.
    Because of this, the preloader has essentially become useless - because all that can be seen is several seconds of empty stage, until the vast majority of the bulky assets have downloaded. Then the preloader flashes onstage for just an instant, and disappears because the content is already up.
    So, my questions are:
    A)  Is there a SIMPLE alternate method to load these library assets in such a way that it doesn't cause this major lag on frame 1?
    B)  Failing that, I suspect I may have to retool my preloader to run as an ENTER_FRAME event in frame 1.  Is this worth the effort (can this potentially resolve the lag issue and allow for a meaningful preload progress animation, despite the lag from the asset export?)
    Any advice, thoughts, ideas (sample code?) would be greatly appreciated!!
    Thanks in advance,
    </a>
    **Edit follows**
    OK, so after a little more research, I have basically answered this question for myself. I'm updating the post for the benefit of others who may find themselves in my shoes somewhere down the road.
    The solution (as far as I can see) is to pretty much just avoid using the "Export for Actionscript" option for exporting assets to the timeline, as much as possible. Maybe it's fine for a few small assets, but not the best choice for large stuff, which in my case was the lions' share of the content!!
    Or at least don't use the default setting of exporting to frame one!!  This will likely foul up ANY preloader, because essentially Flash player will not display any of the content on frame one until ALL of the content on that frame has fully downloaded - You'll be stuck staring at an empty stage for ages, then when the preloader finally does show up on the stage and run, it will zip by in an instant while (probably) doing its job properly, but it's really only updating on the load progress of the balance of the SWF file.
    The info I found suggested one easy method of making the assets available to Actionscript -- simply just place all of the required library assets into some unseen frame in the timeline, shortly AFTER your preloader runs.  Then Flash Player will load them after the preloader has done its thing, and they will be available to be accessed by Actionscript later in the timeline when you really need them.
    Also FYI -- I also tried changing the export settings to have Flash export the assets in question in frame four instead of frame one, with the unfortunate and unexpected result that my published SWF began skipping playback directly to frame four, which also effectively killed my preloader (which was running in frames two and three.) This glitch remained, even after reverting the export setting back to export the assets in frame one!!  It seems like my .FLA file was irreversibly altered (contaminated??) by changing the export frame setting?!?  Yikes!!
    Luckily I had an earlier version saved under a different file name, it was relatively easy to go back to that version and bring it up to date.
    Anyway - that's all for now. Hope this info can help someone else....
    </a>

    See edit at bottom of original post....

  • Asset acquisition value is not updated in Profit center as well as segment

    Dear All,
    I procured an asset through MM, (MIGO and MIRO). the acquisition value is updated in the asset master as well as GL account. but no value is updated in the profit center and related segment.
    I did the following (using ECC 6, document spiltting activated)
    1. Asset master data created and cost center assigned. Profit center is assigned in the Cost center and Segment is assigned in the profit center master data.
    1. me21n - po created
    2. MIGO - done
    3. MIRO - done.
    Can any one help me to solve this issue
    Looking forward your valuable reply
    Thanks in advance
    regards
    Govan

    Hi
    Please check whether cost center is suppressed field for the respective GL Account. Also it seems that you have not made profit cneter as mandatory field. Goto IMG> Financial Accounting (New) > General Ledger Accounting (New) > Business Transactions > Document Splitting > Define Document Splitting Characteristics for General Ledger Accounting . Here you can make the mandatory field as per requirement.
    Warm Regards

  • JE Passed in case of Standard valuation method in 2007B

    Dear All,
    I am bit confused---
    The scenario is i have done one transaction for A/P invoice.The JE passed in case of A/P invoice  & in case of item having valuation method standard  & procurement method make is hitting material variance account instead of hitting inventory account since the tax say cst is inventoried.This issue is occurring only in case of standard valuation method.In case of other valuation method the accounting entry is correct, so what might be reasons behind it.
    Also, if anyone could provide me sap portal link which will help me out to identify the changes which took place in different PL's.
    Regards-
    Mona.

    Hi Mona ,
    The quick thing is to check :
    1. What is the standard price of the item
    2. Is your GRPO  price is difference than AP invoice
    Everytime you purchase it will check against your standard price and if it is different it his variance account .
    Hope this helps
    Bishal

Maybe you are looking for

  • Can not see the Time Capsule disc in Time Machine what can I do??????

    I just set up my new TC with my MacBook Air. The Wireless network is working fine but I can not find (see) the TC hard drive on my MacBook air so I can not set up Time Machine to back up my stuff. :=( Can someone help me with this... ?

  • Using a second blog for a testimonials page

    Hi, I'm building a site for someone who will be purchasing the webMarketing hosting plan so I won't have access to any webApps. To get around this problem, I've created a second blog to be used to manage testimonials. I've created a page and have ins

  • How to use oracle forms(.fmx) in a servlet

    Hi, I am using tomcat application server for developing my web application.I have some forms which are designed in oracle-d2k(.fmx). Clients wants that instead of designing new GUI, use .fmx form for displaying on the web. Can i use .fmx form inside

  • JDBC Sender adapter question

    Hi, Scenario: JDBC-XI-R/3 I am trying to run the JDBC sender adapter every 3 minutes based on the poll interval to select rows from Oracle db. In the select and update statements when I use the rownum < '11' and flag condition (Y or N), then I see XI

  • Bind variable not declared - please help

    Hello, I have wrote a PL/SQL script to update some order_id's in a table. I have declared all my variables but get an error -- bind variable not declared. Can anyone tell me what the problem might be? DECLARE          last_ship      DATE ;          l