Microsoft Project 2013

Hello. I am very new to Microsoft Project and only have been using it for about a week or so. I am creating a timeline and there is no indication that there is any error with my timeline. But my start and finish dates are not right, but the duration is correct.
I have my duration as 200 days. My start date is 10/15/2013. My end date, however, is 2 years ahead and is 6/7/2015. The duration between those two dates is 600 days, when the project is only supposed to be 200 days. I somehow have a 400 day gap, which I have
no idea how that happened. I could really use some help. I have been trying to fix this for hours. If it helps, my schedule is:
Default start time: 12:00 AM
Default end time: 12:00 AM
Hours per day: 24
Hours per week: 168
Days per month: 30
and I have a fixed duration and my work is entered in days.
Also, I have weekends as working days, so I have a 7 day work week.
Help would be most appreciated!!

Duplicate thread, for response see the thread below 
http://social.technet.microsoft.com/Forums/projectserver/en-US/03fee77b-99c4-4c72-a9ac-1189f652dbb1/microsoft-project-2013?forum=projectprofessional2010general
Thanks | epmXperts | http://epmxperts.wordpress.com

Similar Messages

  • Can't Create PDF from Microsoft Projects 2013

    I am trying to PDF a Microsoft Projects 2013 files.  I've tried print PDF and save as PDF but both options give me a pop up window that says "Creating Adobe PDF" with a progress bar displayed with 3 blue bars filled.  I leave it that way for about an hour and nothing happens.  I've tried updating the Adobe Acrobat and Repairing it in the Programs and Features menu.  Any help will be greatly appreciated.  Thank you.

    Thanks for the prompt response.  I don't know how to print-to-file and open the file in Distiller.  The printing as PDF doesn't even work.  It gives me the "Creating PDF" pop up window to which there is no end to. (see photo above)  As for updating to version XI, my colleagues who are running Acrobat X Standard with MS Projects 2013 do not have a problem at all when printing.  I want to avoid upgrading if version X is still usable.  Any other thoughts?

  • Lync with Microsoft Project 2013

    Hi,
    I have Microsoft Lync 2013 and Microsoft Project 2013.
    Can anyone send me the steps to integrate these two so that i can get the updates from the team members without leaving Microsoft Project?
    K.Gokulraj

    In addition to Ben his answer.
    The integration with Lync is not supported in Project Standard only in Pro & Web App:
    http://blogs.office.com/2012/10/19/project-and-lync-together-reducing-communication-barriers/
    https://technet.microsoft.com/en-us/library/ee683978.aspx
    - Dennis | Netherlands | Blog |
    Twitter

  • HELP! Microsoft Project 2013 on windows RT with Lenovo Yoga 11

    Hello, I recently purchased a brand new Lenovo yoga 11. I tried downloading Microsoft Project 2013 via dreamspark, but I get stuck when I try to install secure download manager. It says "the app you are trying to run is not supported on this version of windows". What can I possibly do about this? Thanks.

    Dear Babi
    Welcome in Lenovo forums
    It seems that the version you are trying to install are not compatible with the installed windows (RT) , so please try to contact the service provider for ( Microsoft Project 2013 ) to get the applicable one
    Thanks
    Alaa
    Did someone help you today? Press the star on the left to thank them with a Kudo!
    If you find a post helpful and it answers your question, please mark it as an "Accepted Solution"! This will help the rest of the Community with similar issues identify the verified solution and benefit from it.
    Follow @LenovoForums on Twitter!

  • Cannot install Microsoft Project 2013 Trial

    Hi everyone,
    I'm having a nightmare trying to install the Microsoft Project 2013 trial. I've read various forum posts, but can anyone give me a basic step by step guide to installing the trial!!!! I keep getting an .img file which does not open anything relevant! all
    i want is a microsoft project icon to click on...please!!!!!!!!!

    Matt --
    I think your question is the most repeated question in this public user forum.  Most people download the Microsoft Project 2013 trial version and expect to find an EXE file, which is not what you get.  Instead, for some reason only known to Microsoft,
    you end up with an IMG file.
    To install the software, you have the choice of burning it to a disk, or you can use third party software to unzip the contents of the IMG file.  I have opted for the second choice, and used the free software from 7-Zip.  If you use the 7-Zip software,
    you can unzip the contents to a folder, and then run the EXE file you will find in the folder.  And no, I do not work for 7-Zip; I have used their software successfully and like it.  Hope this helps.
    Dale A. Howard [MVP]

  • Microsoft Project 2013 Cash Flow Reports

    Whilst I read many positive comments regarding the enhancements to Microsoft Project 2013.  I can't help but find myself frustrated that simple processes seem to have disappeared!  All I want to do is access a Cash Flow Report that will tell
    me how much cash is required every week.  In Microsoft Project 2010 this was a simple matter of running a Cash Flow Report and reading the requirements from an easy to view table structure.  Select the Project Tab / Reports / Costs / Cash Flow.
    Using Microsoft Project 2013 I get a lovely looking chart to view but really no useful information to view!  Can anyone help please, surely there must be an easy way of doing this in 2013?  Am I missing something?

    Thanks for replying.  I'm trying to use the View Reports function. Report Tab / View Reports Group / Costs / Cash Flow. Didn't really want to go out to Excel.  Its complicated, we actually use MSP 2010.  However I am evaluating MSP2013 in
    a Virtual Computer Window on the same computer.  Am unable to run Visual Reports as there is some problem I dont understand "Building Local OLAP Cubes" which stops Excel form generating the Visual Report. 
    Back to the problem, I cannot see the purpose of the MSP 2013 Cash Flow Report if all the report gives you is Name, Remaining Cost, Actual Cost, Cost, ACWP, etc.  I dont think that really provides useful Cash Flow indicators.

  • Microsoft Project 2013 trial 64-bit download file is corrupt

    I downloaded the 64-bit trial version of Microsoft Project 2013, but when I try to burn the .img file to a DVD, I get the message: "The selected disk image file isn't valid." 
    When I use winrar to expand the file and then run setup.exe, i get the message "Setup cannot continue because a required file is either corrupted or not available."
    I've repeated the download several times, each time with the same result.
    (The 32-bit version downloaded fine, and I was able to burn it to DVD, but it's not the version I need to install.)
    My OS is Windows 7 Professional.
    Any ideas?

    Hi FKA-PBR,
    Sorry you are having issues.  I managed to download OK from
    http://technet.microsoft.com/en-us/evalcenter/hh973401.aspx and extracted without any issues and could run setup .  Worth deleting what you have downloaded before just in case it is trying to over-write something.  If it happens again then
    getting logs from you might help establish what it thinks is broken.
    Best regards,
    Brian
    Blog |
    Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter |
    Project Developer Center |
    Project Server Help | Project Product Page

  • Microsoft Project 2013 Installation failure Exit code 259

    Hello guys,
    I encountered an issue regarding the Project 2013 installation.  It always gives the Exit code 259. I checked the meaning of 259, it means
    No more data is available.
    Does any body see the same/similare problem?
    I also seeking a parameter which could allow me to create the log for Project2013 installation, thus maybe some helpful infor could be provided in the log. The source files is as below,
    Any help is appreciated.
    Ethan.

    Project? It looks like it's a folder for Visio 2013. Maybe you have upload the wrong screenshot?
    And what's the files like Passive.MSP and Passive_orig.MSP?
    Also check if there are other files in the updates folder, if they didn't create anything, just empty the
    updates folder (back up first), and try to run setup again.
    Meanwhile, by default, Office (Project) will create log files in the \Temp folder during setup. The log files have names that are similar to
    SetupExe(201304251107012350).log
    Other than that, we can also use the Process Monitor to capture the real time info during the setup:
    http://technet.microsoft.com/en-US/sysinternals/bb896645.aspx
    Max Meng
    TechNet Community Support

  • Microsoft Project 2013 - Finish-date drop-down arrow

    When I enter a finish date with year at 2000, 2001, ... and beyond, then click the right drop down arrow, to adjust the date via., calender view, the calender view is at 2079.  I have no
    idea why it jumps forward 79 years, but obviously it makes it impractical to use the calender view to make minor date adjustments.
    Any ideas would be appreciated.
    Thanks,
    Scott 

    Scott,
    Pardon my bumping in but let's make sure we're talking about the same thing. You use the term "calendar view" but I don't think that is what you meant. In Project the Calendar View is a whole separate defined view. You can find it on the ribbon under View/Task
    views group. One of the reasons I don't think you really mean the Calendar View is that I'm not aware of any right drop down arrow anywhere on that view, but then I don't have Project 2013.
    So, for clarity sake, do you really mean the small calendar that pops up when you activate a date field cell (e.g. Start, Finish, etc.) and then hit the selection arrow, (which is on the right side)?
    This may seem like a small thing but more than once have we gone round and round trying to help a user when part of the problem was a misunderstanding due to incorrect terminology.
    One other thing. I assume you realize that by entering dates directly into the Start for Finish fields, you will be setting a constraint on that task.
    With that, I'll leave it to Guillaume.
    John

  • Microsoft Project 2013 - Text under Task Names not formatting for Critical Path to different color (e.g. red)

    I am working with MS Project 2013 Professional
    I am trying to format the text for Critical Path items under the 'Task Name' column to stand out as red - but it does not seem to be working
    This is what I do - I go to "Format" tab,  "Text Styles" "Critical Tasks" and then set Color as red, click OK. The text does not change form the default black.
    Earlier, I had formatted the whole of that column "Task Name" as "Automatic Color" - that seems to have triggered this off
    See attached screenshot
    How can I fix this?
    Thanks
    HardCore Scheduler
    P.S. I couldn't find the answer to any similar question in this forum

    HardCore Scheduler --
    Your mistake was formatting the Task Name column with Automatic Color, as this overrides the setting in the Text Styles dialog.  Here is how to fix it:
    In the View section of the Task ribbon, click the Gantt Chart pick list button (drop-down arrow) and select the Reset to Default Item on the menu.
    Click the Yes button when prompted in a confirmation dialog.
    Widen columns as needed and scroll the Gantt Chart pane back to the beginning of the project.
    Click the Format tab to display the Format ribbon.
    Select the Critical Tasks checkbox in the Bar Styles section of the ribbon.
    Click the Text Styles button in the Format section of the Format ribbon.
    In the Text Styles dialog, click the Item to Change pick list and select Critical Tasks.
    Set the Color pick list to Red and then click the OK button.
    This should display what you want to see.  Hope this helps.
    Dale A. Howard [MVP]

  • Microsoft Project 2013: Project Server Stress Testing

    Hi
    I hope someone can help me. We need to perform some stress testing on Project Server 2013.
    All the articles I found on TechNet suggest that I use the Project Server 2010 Performance Lab Kit
    But it seems like the solution has been archived. (pj14stresstesting)
    All the links refer to http://archive.msdn.microsoft.com/ but the solution is no longer listed.
    Does anyone still have a copy somewhere that they can share with me?
    Or maybe know where I can find it online?
    Thanks
    Pieter
    Pieter de Klerk MCP PMP

    Indeed PS2010 Performance lab kit has been archived. I don't have it so I can't send it to you, but just in case, I found this documentation:
    http://www.microsoft.com/en-hk/download/details.aspx?id=36431
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Save Microsoft Project (2013 - STD) as html file

    Hi,
    is it possible to save project file as html, using project standard ver. File, Save As doesn't have this option though, but are there any ways or methods to achieve this ? Any idea if professional version has this features as I didn't find this in standard
    If not a default or inbox feature of project not available, any other customization or work around to save project as html file ?
    Thanks, Vasu
    Vasu

    In VBA you can create a .html by writing the text required but it would be fairly verbose code. Sort of thing you need to pay someone (like me :) ) to write provided the html is fairly simple and doesn't need jscript etc as well, though if you provided it
    it can be copied verbatim.
    What do you need to see in the page, just tasks and resource etc? Do you have a .css file to go with it (that would reduce the code development time and testing times significantly)
    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

  • Microsoft Project 2013 Reports Print Page Setup Issue

    Hi Guys,
    I'm trying to print multiple reports together, is there any way i can setup the print page setup ( headers and footers ) so that i don't have to set it up for each report? 
    another issue i'm having is also say i set a print page setup( header and footer) for a specific report, then i change to a different report, then when i go back to the first report to print again the page setup settings is gone! 
    any help would be much apprecaited

    Hi Reza,
    This should be possible if you have applied headers and footers to a non-enterprise view, such as the Gantt Chart view, resource sheet view etc. In this manner we can retain the Header and Footer information in the project after
    saving and closing it. (The header and footer information will be available only from the view in which you have applied it) 
    Hence, if we have customized the Header and Footer in the Gantt Chart view, you will be able to view the same in Resource Usage view.
    Regards,
    Dinesh S. Rai

  • Microsoft Project 2013 trial has a download error

    Downloads from this link do not work right now. Please fix:
    http://technet.microsoft.com/en-US/evalcenter/hh973401
    I spent the whole day trying to extract the ProjectProfessional_x86_en-us.img file. Burning DVDs, using 7-Zip and chaning the file name to .ISO are not the answer in this case. Microsoft and TechNet need to check for a download error and post when there's a
    solution.
    This is $1000 software. It makes no sense that there wouldn't have been a fix sooner.
    Grant

    Grant, I went ahead and downloaded this to see if it worked for me, and it didn't. But I did find that you can download this free utility and then mount the .img file with it so you can install. Try it and let me know if it works.
    Virtual CloneDrive (Freeware)
    http://www.slysoft.com/en/download.html

  • Reports in Microsoft Project Professional 2013

    Hi,
    Is there a link which explains the reports in Project Professional 2013?
    I need the detailed description of the chart in each report.
    K.Gokulraj

    Hi K.Gokulraj
    Please find the links,
    I hope you will find those helpful.
    Pick the right report in Project 2013
    and
    What’s New in Microsoft Project 2013?
    Thanks
    Manish