MIGO Error for subcontracting PO

Hi,
  This is regarding the error which I am getting when I am doing a GR using MIGO for a subcontracting PO.
  The Error message is as *'of the required quantity of material &, && quantity is open'*. This error comes for few plants.
  I am working on 46C version of SAP.
  OSS note 526850 says this is a program error in version 46c but then why this error is not comming for all plants .
Any helpful inputs related to this issue will be rewarded with points.
Thanks in Advance.

I think it is still possible to place the cursor on the message and to click the icon with the question mark, this should then hopefully bring a pop-up with the message number.
from there you can investigate further. e.g. if it is a Z or Y message, then it is a home made message, and you can get the info who created it from transaction SE91.
In any case you should do the following in Migo:
Open the sub-items before you press Save or before you click the Check button. Only then you can know whether the message belongs to the header or to the item.

Similar Messages

  • MIGO Error for subcontracting scenario through PO

    Hello All,
    We have PR PO process where PR is created for subcontracting and then PO with BOM explode in PO for same material for in and out.
    User is getting error while posting MIGO for Subcontracting GR though PO.
    Though 541 stock has been transferred to vendor
    and though PR PO process we are doing subcontractor PO and MIGO 543 movement
    getting error with blank message in migo
    Message no. M7895
    Due to this not able to complete MIGO and stock transfer to plant from vendor
    Please check the attached file for error
    Thanks and regards
    Hard Vora

    I think it is still possible to place the cursor on the message and to click the icon with the question mark, this should then hopefully bring a pop-up with the message number.
    from there you can investigate further. e.g. if it is a Z or Y message, then it is a home made message, and you can get the info who created it from transaction SE91.
    In any case you should do the following in Migo:
    Open the sub-items before you press Save or before you click the Check button. Only then you can know whether the message belongs to the header or to the item.

  • MIGO error for Import purchases

    Hi All,
    This is regarding doing Migo for Import Purchases.
    the error is coming as" Account determination for entry TI00 _ 0001 _ 3000 not possible" while posting.
    Message no. M8147
    Diagnosis
    The system did not find an account for this transaction. This means that the account determination for key TI00 _ 0001 _ 3000 is not maintained in MM Customizing (Valuation). The key is made up of:
    u2022 Chart of account
    u2022 Transaction key (= Posting transaction)
    u2022 Valuation grouping code
    u2022 Account grouping code
    u2022 Valuation class
    System Response
    The system cannot update a G/L account for this transaction. You cannot post the transaction.
    Procedure
    Contact your system administrator.
    If you have the authorization, check the Account determination in Customizing for Valuation.
    Proceed
    Note
    The relevant posting transaction can be found in Table T030A.
    Checked OMWD , setting is proper i.e Valuation Grouping code has been assigned..
    In BSX, WRX, PRD and FR1 for 3000 G/L accounts have been assigned.
    The above error is not occuring for Domestic Purchases.
    Please respond immediatly, we are in urgency.
    Thank you,
    Shiv

    Hi
    What are the other conditions you entered in purchase order? Have you maintaied account & accrual keys in pricing schema and GL accounts in OBYC.
    I hope BSX, WRX and PRD are enough for your material postings. But check with other conditions like customs etc...whether they have been maintained properly or not.
    Thanks

  • No error for subcontract PO when we do GR without issuing components.

    Hi experts,
    The system is not giving any error message when we do a goods receipt for a subcontract PO without even issuing the components to the vendor. i have a PO which had 4 components to be issued. 1 material is of HALB material type and the rest 3 were UNBW material type. i did a GR without even issuing the components to the vendor and the system allowed me to do the GR without giving any error message which shoud not happen.
    Any idea why the system is not giving the error message?
    Thanks
    Mahendra

    When a goods receipt is done in SAP, then there was usually a truck in your plant and the material is physically placed into your goods receipt area.
    You are looking for a solution to block the receiver from doing his job (to receive the material). because someone else (maybe shipping manager) has not done his job (forgot to record the goods issue to the subcontractor in SAP, physically the material was probably shipped, otherwise you could not have phyiscally received the finished material).
    Do you really think that preventing to post a goods receipt is the best option?
    In my opinion, you should try to control that everything what leaves your company is goods issued.

  • Runtime error in MIGO for subcontracting order

    Hi All
    We have an issue in subcontracting process. We are trying to complete goods receipt for the multiple line items for subcontracting PO.
    These multiple line item contains serialized materials. When we are trying to complete the GR, We are getting runtime error saying u201COnly 0 serial numbers entered instead of 1u201D
    Any pointers in resolving this issue will be a great help to us.

    Mohandevegowda wrote:
    Hi All

    > We have an issue in subcontracting process. We are trying to complete goods receipt for the multiple line items for subcontracting PO.

    > These multiple line item contains serialized materials. When we are trying to complete the GR, We are getting runtime error saying u201COnly 0 serial numbers entered instead of 1u201D

    > Any pointers in resolving this issue will be a great help to us.
    Hi,
    Pls check whether you have maintained the serial no for the material in mm01 tcode. When it comes to subcontracting process you will create a BOM by listing all your materials but when you take GR from subcontractor after some action is performed on that list of materials then definitely you have to manually give the serial no in MIGO or check automatic serial no there.you might have not placed anything over there.
    Thanks

  • Account determination error in Subcontract PO-MIGO.?

    Hi all
    While doing GR, i mgetting error i "Account determination for entry LDCA BSV 0001 ___ 5010 not possible".
    The above PO is subcontract PO .
    Thanks
    sap-m

    Hi,
    For subcontracting..maintain these keys..so that you will not get any problem..
    BSX, BSV, WRX, PRD, FRL
    Regards,
    Prasath

  • Error showing - No price could be determined for subcontracting in CK11N

    Hi,
    We are facing a problem in CK11N that while we are creating Material Cost Estimate with Quantity Structure, getting an error message..
    No price could be determined for subcontracting
    Message no. CK468
    Diagnosis
    The system could not calculate a price for the subcontracting because none of the valuation strategies in valuation variant 001 was successful.
    System Response
    If the system issues a warning message or an information message, the costing item is used in the cost estimate with a zero value.
    If the system issues an error message, it sets the status "KF" (costed with errors).
    If the system issues a termination message, the cost estimate cannot be processed.
    Procedure
    If you have authorization for Customizing, check the valuation strategy for subcontracting in valuation variant 001.
    I read many thread already, but no solution is suit my requirement..
    please help..

    We run the transaction OPN2 and select 001- Planned valuation - mat. Valuation Variant. Db Click on it and select Subcontracting tab.
    There Strategy Sequence is defined as under:
    Priority......Strategy Sequence
    1...............Effective price from Purchase Order
    2...............Net Purchase Order price
    3...............Effective price from Quotation
    and in Quotation in Purchasing option, there is selected - Auto quota arrangement.
    please guide.

  • Problem in Posting of GR for Subcontracting PO Through MIGO

    Hi All,
    When I am posting 101 through MB01 for Subcontracting PO The system is creating three line items in Material Document( 101, <b>543 & 545</b> ) which is correct.
    But if i am doing the same through MIGO it is posting three line items as (101, <b>543 & 543</b>) - Which is wrong.
    I am using SAP R/3 4.7.
    Please let me know if there is any OSS note to fix this.
    Thanks a ton in advance.
    -Nirupam

    Hi,
    I can't belive it....543 is showing Credit indicator and 545 is showing debit indicator.  Which is perfect.  So, when we receive a subcontracting PO, if at all there is any byproduct that is going to be received, it has to be either debit or credit (only one way) whether we receive from MB01 or MIGO.  If you see 545 in MB01 that means, you are receiving by-products along with ....However, in MIGo you are showing only 543 (consumption of components).....Are you missing any by-products comingup in mIGO?  Is the PO the same you are using in both MB01 and mIGO....very minimal differences in terms of functionality we may encouner between these two transactions but I strongly doubt about posting two different movements types for exactly the same data....I am not doubting you; just curious to work on such problem.  Please cross verify again and let me know.
    Regards

  • How to desable ok check for subcontracting child parts in MIGO

    Dear SAP Experts,
    my client is having one issue regarding disable OK check for subcontracting child parts in MIGO transaction  ,In MIGO subcomponenets are attached to main component , my client is asking for disable that OK check box user shouldnot remove that check box tick mark when system showing message deficiate of subcomponents at subcontractor  because some times users removing that check box tick mark  and proceeding further, with that they are not able to reconcile the sub challans.
    Plz let me know how disable OK check for child parts in MIGO

    chandu
    while making the po we are explode the BOM and we defined the parant and child mateirlas in bom.
    system will show the same in migo . i think there is no standard configration to block the option.
    Regards
    laxman

  • MIGO: Default quantity for subcontracting component

    According to OSS Note 329928, There is no component quantity adjustment in Transaction MIGO, except if you changed the quantity of the material produced for subcontracting before the first time it was opened.
    The quantities that you saw are no longer changed automatically.
    That causes a problem for us, because the people who updates materials just type in the quantity and don't verify if it goes correctly, so that is causing problems in the subcontracting process.
    We checked and there is no BAdI or exit to do that, so we understand that the only solution is to disable the option to expand the subcontracting components. Now the question is: How to do this? Is there any customizing option? Or we'll have to treat it in the BAdI? Or would be better in a screen exit?
    Thanks in advance!
    Rafael Schaffer

    Hi Rafael,
    Did you find any solution?
    We are having the same dificulty, but we need to control components quantity not only at MIGO but also at bapi BAPI_GOODSMVT_CREATE.
    Please share your solution!
    Thanks in advance,
    Carlos

  • Doing MIGO for subcontract item

    Hi Friends,
    When I am doing MIGO for Subcontracting items, I can explode the BOM & see the child parts. At that time I can change the qty. & unit of measure for child products. Is it possible to restrict these.
    I make BOM for the mail item & made PO accordingly.
    Because of this the value of the main item may be valued at higher or lower, which is not correct.
    Regards

    hi,
    the component u r attaching in the SC po, is planned consumption ratio, which is going to be used for conversion of finished goods-child material.
    here when u r making the GRN for child material, always there should be flexibility of changing the component conusmption, as there is always differance in planned and actual conumption.
    when u r sure that there is a change in conusmption pattern, u need to change the qty of the component while making the GR.
    (as per SC challan referance)
    if at after all goods receipt is done , and u observe the differance in component consumption, u can always adjust the same by MIGO_GS against PO-GRN.
    u cant make the component field in MIGO as blank and which is not advisable tooo.
    Edited by: manipal on Jan 8, 2008 6:15 AM

  • Standard Cost Estimate for Subcontracting

    Dear Sir / Madam,
    We are in the process of migrating from our normal R/3 operations for Production Planning to Execution inclusive of Costing of materials by using iPPE functionality for repetitive scenario. We have our BOMs for painted body currently in R/3. The painted body falls under subcontracting scenario.
    In this scenario the body in white produced from our bodyshop is sent out to the subcontractor along with certain paint items and is received as painted body and consumption of the body in white and the paint items sent needs to be shown during the goods receipt of painted body.
    For this we have maintained the BOM for the painted body in iPPE. Also in the costing variant "ZD01" in order to arrive at Standard cost (CK11N) for the painted body we have maintained the following settings for Valuation variant for subcontracting :
    Priority     Strategy Sequence     
    1          Net Quotation Price
    2          Effective Price from Purchase Order
    While running CK11N for the material (painted body) we are receiving the following message
    Message no. 28501 : Error in dependency processing: condition 0000062388 is empty
    We wanted to verify whether the message raised is normal or would it have any adverse impact.
    Your assistance would be highly appreciated.
    Regards,
    Bhavika
    Edited by: Bhavika Goyal on Feb 7, 2009 12:20 PM

    Dear All,
    Control Key is important for inhouse producrtion and Sub Contract.  Check it once and when ever u have given the Product (semi fisished) to Sub Contractor, along with Paint. 
    Here one thing is important what is your process? how much portionis involced in Sub contracting.  why because
    Paint issue to the sub con is captured by the way for migo or miro
    Payment to sub contract is capture all the cost of the Sub Con., then is there any cost is missed for this process.  Let me know the remain things?
    thanqu
    raj

  • Good receipt problem for subcontracting purchase order

    Good receipt problem for subcontracting purchase order
    with account assignment type ‘E’.
    After update to ECC 6.0. Do good receipt for subcontracting purchase order with account assigment 'E'.The system show the error message(KI235)----Two cost elements (Change in Stock (Subcontracting)&Outside processed fee) haven't CO account assignment.but the field status  for sale order is option entry , when I default cost center for the cost element  in OKB9.the system post the material document and generate the following accounting document.
    Doc.Type : WE ( Goods receipt ) Normal document
    Doc. Number    5000056065       Company code    1000         Fiscal year     2007
    Doc. date      2007.12.04       Posting date    2007.12.04   Period          12
    Calculate Tax
    Doc.currency   HKD
    tm PK Account    Account short text   Tx Cost Ctr   SaleOrder               Amount
    1 89 13500000   Stock-Work in proces                   1007823  10             274.4
    2 96 21210010   GR/IR Clearing                             1007823  10             205
    3 91 41010102   Chg in Stock(Subcon)    10901099  1007823  10            274.4
    4 86 41031000   Outside processed fe     10901099  1007823  10            205  
    5 99 13500000   Stock-Work in proces                    1007823  10            69.4
    6 81 41010101   Cost of Prod (Subco)                      1007823  10           69.40
    My problem is:
    When use MIGO to do good receipt for subcontracting Purchase order, for consumption account((Change in Stock (Subcontracting)-41010102&Outside processed fee--41031000) ,why the system don’t recognize the sale order filled as CO account assignment?

    Dear fanny chen
    Did you get a solution for your open question?
    I`m facing the same problem, so any help yould be appreciated.
    Regards

  • MIGO - Account Determination Subcontracting

    I have a problem....
    When the material is being posted using MIGO an error in account determination is determinated and cannot post the document.
    It said:
    Account determination for entry SSM FRN not possible.
    I check my schedule agreement and review the ZOA1 Customs %. And its Account determination said:
    Account key     FRE
    Accruals           FR3
    From where is taking the FRN!!!!!
    I also check in customizing the following:
    Material Management>Purchasing>Conditions>Define Price determination process>Define Transaction/Event keys...
    From where could it get the error!!!

    Hi,
       This is due to OBYC setting issue as FRN key is used for Incidental costs of external activities
    For subcontracting following should be OBYC settings:
    1. Stock Account (finished Account) BSX - Debits
    2. GR/IR clearing Account WRX - Credits
    3. Change in Stock Account BSV - Credits
    4. Processing Charges/Sub Contract Charges FRL - Debits
    5. Stock Account (Raw Material) BSX - Credits
    6. Consumption from stock of material provided to vendor GBB (VBO) - Debits
    In Case of Sub contract while doing Transfer Posting (Providing material to vendor) in MB1B or ME2O only Material document will be generated. No Accounting Document will be generated.
    While Receiving the Finished / Semi finished material both Material and Accounting documents will get generated and the accounting entries will be as under
    Check along with your FI consultant OBYC.
    Regards
    Rajesh

  • Excise Invoice Tab is not displaying in MIGO Display for 541 material docs.

    Dear All,
    Excise Invoice Tab is not getting displayed in MIGO Display for 541(Transfer posting to Vendor) material documents.
    I did tranfer posting of some raw materials to the Vendor in MB1B with the movement type 541
    and after that i have created a Subcontracting Challan with the reference of the above created transfer posting
    material document. 
    Now i need the Sub contracting challan number to be displayed in the Excise Tab of the transfer posting material document.
    But if i display the Transfer posting material document in MIGO, the Excise Tab is not getting displayed.
    Kindly help on this so that i can view the Sub contracting challan number in the display of the respective Trasfer posting material document in MIGO.
    Thanks & Regards.

    Pls confirm if you are following the SC process sequence :
    u2022     Creation of Subcontracting PO, here in conditions tab maintain the price (Subcontracting charge) (ME21N)
    u2022     Transfer Posting of Components to Subcontractor ( Movmt Type - 541) (MB1B/ME2O/MIGO)
    u2022     Creation of Subcontracting Challan w.r.t. Transfer Posting Doc (J1IF01) - This challan will have the details normally company needs, in case client need more ... ABAPer have to develop customized smart form
    u2022     Goods Receipt w.r.t. Subcontracting PO and Refer Subcontracting Challan at the time of GR (MIGO) {GR with 101 and auto consumption of components with 543 movement}
    u2022     Reconciliation of Subcontracting Challan (J1IFQ)
    u2022     Completion of Subcontracting Challan (J1IF13)
    u2022     Generation of Annexure IV (J1IFR

Maybe you are looking for

  • SAP J2EE Engine JTA Transaction Xml for table TABLE could not be ana

    I'm having a weird case. I created 3 entity bean. In my R/3 will call this JCO.Function to do the insert to database. But out of 3 entity bean, only 1 entity bean got error where it unable to insert to database and have this error in the log. The cas

  • External mail contacts not recieving mail.

    Email delivery to external contacts from external emails is not being delivered. If I send an email to the external contact from within the organization it arrives to the external contacts email (gmail, cox etc) but if I send an email to that same ex

  • How I fixed the missing Flash.exe in Extension manager 5

    I was surprised to see that Flash 5 was absent from the list of programs in Extension Manager 5 First I ran Adobe Utilities-CS5/ExtenScript Toolkit CS5 BridgeTalk.__diagnostics__; In the relevant section in Result: BridgeTalk Diagnostics flash-11.0:

  • Please add white balance adjustment to brush tool!!

    Please add to the brush tool the ability to adjust white balance.  I know you can currently paint a color over areas, but I would like to see a true white balance control in a brush.  This would be quite useful for wedding or event photographers who

  • I can't find my app in ios6 but in ios5 I find it!

    Hello! When I search my app (Cambrils 24h) in the apple store of a ios6 i can't find it. Althought, If i search it in ios5 I find it! I look it in the itunes connect and its ready to download. I've to do anything to it's visible in ios6? Thank you!