MIRO with reference to MIGO number

Hi All,
I want to have MIRO with respect to MIGO Number.
e.g
PO QTY 1000
GRN 1 -
10 Qty
GRN 2------5 Qty
Required scenario:
If we run MIRO then Qty would be 15 Qty
We have a requirement that MIRO is done GRN wise.
like  for MIGO # 1 -
MIRO reflects 10 Qty
for MIGO #2----
MIRO reflects 5 qTY

Hi ,
In standard SAP it is not possible to select MIGO no to do MIRO .
Only you can use the Delivary note no. as reference for doing MIRO .
Else , purchase order is always taken as reference and non required line item is deselcted at the time of MIRO .
So please check how best you can use the filed delivary note in MIGO for doing MIRO .
Regards,
Dewang T.

Similar Messages

  • Posting MIRO with reference to MIGO document number

    Hi,
    Is there any way of posting a vendor invoice in MIRO, taking MIGO document number as the reference instead of PO or Delivery Note reference?
    Muru

    Hi,
    In MIGO you mention the delivery note in the header part.
    There is a drop down in MIRO transaction where we enter PO number, please check and you will find the "Delivery Note" option in the drop down list.
    you can do the MIRO with reference to this Delivery Note number from this option.
    (Just make sure, that you have selected the "GR based IR" indicator in the PO line item.)
    Doiong MIRO with reference to material document number of MIGO is not possible in standatd SAP.
    Regards,
    Gaurav

  • Forwarder Invoice details with reference to Shipment Number

    Hi All,
    Currently i am working on shipment and new to shipment.
    I would like to find the invoice details of the forwarder with reference to Shipment number. Currently we have flow like shipment document>shipment cost document to the forwarder>PO (created in background and entry sheet)-->Invoice of the forwarder.
    Could you please provide the exact table where can I find the invoice w.r.t. shipment number or forwarder of the shipment.
    If we require any otehr changes, pls provide BADI.
    It will be appriciated for quick and right solution.
    THank you
    Regards
    Kishore

    If you create the invoice using MIRO transaction, then the table for the invoice is RBKP (header data) and RSEG (item data).
    Outbound process - To link invoice to shipment/shipment cost, you will need entry sheet which will be created when service acceptance document is created
    Inbound process - use the PO number then from PO go to delivery -> shipment -> shipment cost.
    VTTP-VBELN contains delivery docnument (shipment item table)
    VFKP-REBEL contains shipment number  (VFKP is shipment cost item table)

  • MIRO with reference to delivery note in import case.

    Hi,
    While doing the invoice verification in case of import scenario for main vendor we are facing the problem.
    We have created the PO with a 3 line items , but the material code entered is same in all three line items. We have done the GRN with reference to the PO for each line item seperately with different delivery notes in each case.
    Now while doing the MIRO when i gave the reference of delivery note number system is showing all  3  quantities in MIRO screen instead of single line item with qty 1.
    Why it is so.Please guide.

    Select GR by vendor with posting date in miro.
    Check this SAP note 393431 - MIRO - Vendor
    Edited by: Jeyakanthan A on Jul 6, 2010 9:45 AM

  • Billing with reference to Shipment number?

    Hi Guru's,
    Can somebody help me?
    During Shipment processing we like to create a commercial invoice (required in some countries). In this shipment are several deliveries. The requirement is to print all deliveries in the shipment document. Is there a possiblity within standard SAP to create a billing document in reference with an shipment number? In other words all underlaying deliveries will automatically selected.
    Thank you for reading my question.
    Regards,
    Eric

    Hi,
    This is not what I mean. Business example:
    Shipment 123 has delivery 123,124,125,126,127,128.
    during Goods Issue I like to create a commercial invoice, because
    the end user requirers the commerical invoice. At the shipping department
    they want to print all deliveries which belongs to shipment 123. How to print
    them the easiest way?
    Best regards,
    Eric van Zundert.

  • Miro with reference to PO

    hi,
    i have 2 scenario for credit memo and subsequent credit which is referenced to PO.
    the item purchased is based on moving average price.
    1) when vendor invoice comes in, quantity difference, say missing 5 box (original 20 box). i will create the invoice by changing the quantity in miro to 15 box. then later when vendor sends in the credit note, i will create the credit memo. in credit memo, i need to call out the PO and change the quantity to 5 box. correct?
    2) let say the invoice comes in and found out the price is printed wrong by mistake of higher price which is not due to quantity. i will create the invoice by changing the price in miro. then later on when vendor sends in credit note, i need to create subsequent credit. may i know i still need to call out PO when do subsequent credit?
    3) as this is based on moving average and not standard price, the variance will go to stock account. the double entry for point 1 and 2 will be both also debit vendor credit stock?
    thanks

    Hi,
    1) If you are to post a credit memo on receipt from the Vendor, then at the time of original invoice, there should n't be any changes made either in qty. or value, it should be done in line with the GR qty and value.
    2) Invoice to be raised for the original qty and value, subsequent credit to be raised on receipt of the credit note from the supplier,
    Both the Credit Memo and Subsequent credit to be referred from the PO both entries will be debit vendor credit stock
    Regards
    Merwyn

  • How to see MIRO No with reference MIGO

    Dear experts,
        how to see miro number with reference to migo number  in mass, is there any table to see ?, please  help.
    regards
    rajakarthik

    Hello,
    Use T.Code SQVI
    Then give a quick view name and click create.
    In the pop up block, give the description and select the data source as 'table join'
    Make sure, basis mode is selected.
    Then in the subsequent screen, select table join and give the tables u need to join in the sequence.
    Once the table selection is over, make the fields to be needed in the report and in the selection screen and go for the report by executing.
    Can contact your abaper if support needed.
    Regards
    Gregory Mathews

  • MIRO - Invoice Verification with reference to Delivery note.

    Dear All,
    In our organisation we are doing MIRO with reference to Delivery note. As same number of delivery note is being submiited by multiple vendors, after entry of that delivery note in MIRO system shows large list (Closed & Open for MIRO). This becomes difficult to select the required delivery note.
    Is it possible to make display of only those delivery notes against which MIRO (Invoice verification has not done).
    Also MIRO with reference to GRN number is possible or not ?
    Please suggest.
    Regards,
    Shekhar Kisan Gaikwad

    In our organisation we are doing MIRO with reference to Delivery note. As same number of delivery note is being submiited by multiple vendors, after entry of that delivery note in MIRO system shows large list (Closed & Open for MIRO). This becomes difficult to select the required delivery note.
    Is it possible to make display of only those delivery notes against which MIRO (Invoice verification has not done).
    Also MIRO with reference to GRN number is possible or not ?
    HI,
    To avoid difficulties post miro with Reference document (PO Reference Tab) - Delivery note click on Radio button a possible entries for delivery note screen will appear. Here you can search specific delivery note by a lot of criteria which will save ur time and effort also you can see MIGO Document.  Click and put tick to adopt and post Delivery note / migo and enter required field.

  • MIRO (Credit Memo) with reference to delivery note

    Hi,
    Our problem is that we are not able to post miro (credit memo) pertaining to return delivery 122 movemnt type with refrerence to delivery note, however it can be posted with reference to purchase order.
    How can we do it.
    regards
    GR

    Hi,
    Thanks for the answer. Please note down the complete scenario.
    First we made PO of A item for 1000 Pcs, then we post migo and miro for 1000 Pcs. In migo suppose I have entered 123 as delivery note number and I have posted miro withreference to delivery note no. 123.
    Now suppose, we made return delivery of 500 Pcs (122 movemnt) and put delivery note no. 124. Now when I post credit memo (miro) of the return delivery I am not able to post miro with reference to delivery note number, but when I try to post withreference to Po, I am able to post. But I have to change 500 Pcs Qty and its amount manually, which we don't want, we want that the credit memo should be posted withreference to delivery note number as we have posted for 1000 Pcs. and we also want that return delivery qty and value should automatically come in miro screeen.
    Regards
    GR

  • MIRO posting with reference to Purchase Order

    Dear Experts,
    I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not coming which I mentioned in Purchase Order!!
    How can I post MIRO with reference to Purchase Order Number? Is it possible?
    Best Regards.
    Ripon

    As above it sounds like a GR gasn't been posted but you can still process invoice.  Just manually enter the quantity and value as per invoice.
    Note the invoice will block for payment pending the GR.
    See transaction MRBR if you want to release the invoice for payment immediately.
    Regards,
    Nick

  • MIGO PROBLEM in the Good Receipt  with reference to purchase order

    Hello Everybody.
    i m getting one problem with reference to MIGO tcode.
    Might be anyone notice or not but i want to share with you.
    in MIGO selected goods receipt then beside it ask for the different actions.
    I use the purchase order no.
    suppose i given po no 1
    enter
    now it will display the details of that po number (1) but at the same time po number field is again in the input mode and you can give more po number .
    suppose now i have given po no 2.
    enter
    Then in same gr we will be having the item details of both po number( 1 & 2) .
    This is my problem .I want to make restriction that in single gr it should take only one po number not more than that ,after giving one po ,it should make that field in display mode.
    How to do that please guide me .
    I will be grateful to you.
    Thanks a lot

    You can use a field exit on any field that gets filled when the first PO is entered
    check that field (Something like challan Number , Delivery date)
    if is if filled use the "screen" Table to make the PO Number field Display only .

  • Invoice number of the forwarder with reference to shipmnet document

    Hi All,
    Currently i am working on shipment and new to shipment.
    I would like to find the invoice details of the forwarder with reference to Shipment number. Currently we have flow like shipment document>shipment cost document to the forwarder>PO (created in background and entry sheet)-->Invoice of the forwarder.
    Could you please provide the exact table where can I find the invoice w.r.t. shipment number or forwarder of the shipment.
    If we require any otehr changes, pls provide BADI.
    It will be appriciated for quick and right solution.
    THank you
    Regards
    Kishore

    If you create the invoice using MIRO transaction, then the table for the invoice is RBKP (header data) and RSEG (item data).
    Outbound process - To link invoice to shipment/shipment cost, you will need entry sheet which will be created when service acceptance document is created
    Inbound process - use the PO number then from PO go to delivery -> shipment -> shipment cost.
    VTTP-VBELN contains delivery docnument (shipment item table)
    VFKP-REBEL contains shipment number  (VFKP is shipment cost item table)

  • Credit Memo request with reference to Billing Document number via IDoc

    Hi,
    I want to create credit memo request with reference to billing document number via IDocs.
    I have tried through ORDERS05, but when I process I saw that it is only processing with reference to contract  number or quotation.
    So is any other way of creating credit memo request creation with reference to Billing document number via IDocs?
    Thank you in advance.
    Regards,
    Santhi

    Please Help... it is Urgent...  Thank you

  • Payment Posting with Reference to Purchase Order

    Dear Experts,
    I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not coming which I mentioned in Purchase Order!!
    How can I post MIRO with reference to Purchase Order Number? Is it possible?
    Best Regards.
    Ripon

    >
    riponkp wrote:
    > Dear Experts,
    >
    > I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not coming which I mentioned in Purchase Order!!
    >
    > How can I post MIRO with reference to Purchase Order Number? Is it possible?
    >
    > Best Regards.
    > Ripon
    Seems like you are doing MIRO before GR. If GR is done, it will pick the amounts, if GR is not done, the amounts are not picked. You enter the amounts manually with reference to PO.

  • Invoice verification with reference to material document

    Dear Experts;
    i want to make invoice verification (MIRO) with reference to good receipt document not the all quantity in the purchase order. is this possible ???

    Hi,
    Option - 1
    If you have done 3 separate GR's for the above qtys then if you do MIRO with reference to PO then 3 line items will appear with the respective qtys. You select the one you want & delete the rest.
    Option - 2
    Check whether you have entered any values in the delivery note field while doing GR. If yes then do MIRO with reference to Delivery note rather than PO so that qty in the GR material doc will flow to MIRO automatically.
    Thanks & Regards,