MM Purchase order amount is without VAT amount in Cash management

Hello colleagues!
SAP says (note 009161) that PO amounts can be updated manually. But it is to much manual work. Is there some other solution for on line updating PO inclusive TVA?
Please help!

Thanks for your response. I have read 9859 note. Here is the explanation how integration of MM/SD and CM is realized.
But the question is:
PO data is updated in the CM. Data of PO positions appear in CM. If in PO position VAT deductible is selected amount without VAT appears in the CM. But the outflow cash planning we should do with Amount + VAT.
The note 9861 says how this problem can be solved. But it is not good solution (much manual work). It should be updated correctly during PO saving. I do not know, my be somewhere in the Functional models (mentioned in 9859 note). But it is not possible without crushing standard system.

Similar Messages

  • Payment amount is more than Purchase Order Amount

    Dear FI Expert,
    We are getting the error "Payment amount is more than Purchase Order
    Amount" w hen a single payment through one check is being made against 2
    purchase orders.
    System is considering only the 1st purchase order and disallowing
    payment.
    For e.g. 2 Purchase Orders are created w ith 100% DP condition: First
    one
    for USD 200000 and second one for USD 100000.
    2 Dow n Payment requests are created through ME2DP against these 2
    Purchase Orders.
    At the time of making payment through F-48 by selecting both open items
    it takes the reference of only one Purchase Order and generates the
    error
    "Payment amount is more than Purchase Order Amount."
    Please suggest how entry w ill be made in such cases.
    Thanks
    Kamlesh Jangir

    Hi kamlesh,
    You are using EHP 4 or higher package. in this case you can use FPDP_CREATE instead of ME2DP.
    You can go through Business function LOG_MMFI_P2P
    https://websmp109.sap-ag.de/~form/handler?_APP=00200682500000002672&_EVENT=DISPLAY&_SCENARIO=01100035870000000122&_HIER_…
    Down Payment and Down Payment Request - Purchasing (MM-PUR) - SAP Library
    I hope this will be help full
    Regards
    Raheem

  • Miro to be booked @ purchase order amount.

    Dear All,
    I had a query related to MIRO-when we book MIRO on a purchase order , we can only book as per the quantity in GR.Is there a way that i can control the amount while booking the MIRO i.e tolerance +- 15000/- or smaller amount.right now i can manually change the value and book excess amount or can i control that any point the MIRO value should not exceed the purchase order value.
    Need your help on this.
    Thanks,
    Priya

    Hi,
    Maintain tolerance limits as ZERO in OMR6 t.code for the tolerance key PP ( for Price variance) & DQ  ( Exceed amount: quantity variance)
    Also you can  set message as ERROR in OMRM t.code for messages M8 -081 {Quantities invoiced greater than goods receipt & maintain GR-based IV in the PO item level}  & M8 -087 {( Invoice quantity greater than PO quantity) is for material without GR only}
    NOTE:
    If message setting not work, you can set ERROR message for M8 -081 & M8 -087  in OBMSG t.code.
    Regards,
    Biju K

  • F-58  posting using spl gl indicator G 7 clear purchase order amount

    Hi sap gurus
    Requirement is as below:
    fi -p2p-scenario- Usi ng spl gl indicator as G-which is configured 
    1. Create a Payment term for
    I. Part Payment as advance u2013 10%-on creation of PO
    II. Part payment against Proof of Dispatch; and -15%-create inbound delivery, make some advance payment
    III. Balance against receipt of material on production of Invoice, MDCC u2013 75%-at time of GR/IR-final invoice
    2. Use this payment term in the Purchase order(say rs.100)
    3. Create advance payment request u2013 F-47 for 10%-say rs.10
    4. Make advance payment for the request u2013 F-58-
    5. On Receiving the Proof of dispatch, Create an Request again for 15% - F-47-say rs.15
    6. Make payment for the request for 15% - F-58
    7. After GRN and Make LIV for 100%
    8. Make the Final payment for 75% after adjusting 10% and 15% payment line items
    in F-58 directly.
    9. Display the accounting document.
    with  one payment term,i have done the  partial payments for rs.10 & rs.15 using f-47 & f-48.Finally  
    how to clear the  payments in F-58  -the  adv amounts posted through spl gl indicator say 10 & 15 -shows cr against vendor & also the case after MIGO-for the 100 being a credit item ,how to clear the items as the amounts are getting reflected as" not assigned" in partial paym ent tab.
    Please suggest if i am wrong with flow or entries.
    Please suggest the is there any other to clear using spl gl indicators.
    thanks
    Nagesh

    please clear those open items by giving spl GL indicator in the inut screen as G.
    System will shows open items.and you can clear those.

  • Invalid format in Purchase order Amount colum

    Dear Guru's
    In my one of purchase order doc in print preview the amount showing:
    10.100,00
    How can I solve this. Please advice your procedure.
    Thanks and B/R
    Bishnu
    19/01

    The logic of SAP is to display the quantity, prices and values in the format that is used in the vendors country, so that a CSR of your vendor can easily understand how much you want.
    Example:  in USA the format for 1000  is  1,000.00, while in Germany the same is written 1.000,00
    Assume an US company  orders in EAches at a German vendor.
    The US company has customized their unit of measure to have zero decimals
    And has changed the decimal settings for the countries.
    The German company is used to have 3 decimals for a quantity.
    The order arrive and shows 1,000 EA
    The American expects to get 1000  the German CSR would create an order for just 1.
    (it had happened, I am telling you experience I made)

  • MR11 - can't clear a Purchase order amount

    Hi,
    When we try to execute the transaction MR11 for a specific purchase order, we have the following error message:
    System status CLSD is active (ORD 13002723)
    Message no. BS013
    Diagnosis
    Object ORD 13002723 has system status CLSD (Closed).  According to this status, transaction 'Incoming invoice' is not allowed.
    Procedure
    You can only carry out the requested function if this is allowed according to the status of the object.
    How can I change this status?
    Thanks,
    Julien

    I tried, but I get this error message:
    Order 13002723 is not an internal order
    Message no. KO101
    Diagnosis
    You can only process orders belonging to the following categories using the menu "Controlling -> Internal orders":
         01 Internal order
         02 Imputed cost order
    Order 13002723 belongs to neither of these categories.
    System Response
    You can display order 13002723 but you cannot maintain it.

  • Sending Purchase Order in mail without the spool generation

    Dear All,
    When i create a Purchase Order using Tcode ME21N, the PO should go by mail to an external email id as a pdf attachment.
    A Z sapscript is used . The spool request is not generated.
    Could anyone please let me know the method/code to use the script data for creating Purchase Order and send it via email without spool generation.
    Waiting for solution.
    Thanks & Regards,
    Bhavika

    Hi,
    as i said:
    create an printer with devices type PDF1, set  host spool access method to M (E-Mail to Receiver/Owner).
    Use this printer as output-device.
    To create and use a printer with PDF1 try searching in SCN or use SAP OSS.
    Regards Dieter

  • Restriction of Payment to Vendor above Purchase Order Amount

    Hi Experts,
    I have a requirement where my user wants an error message to appear when a Payment to Vendor is made in excess of the PO Amount.
    An Information message appears when posting an advance payment through F-48 for the same but can I get a similar message when making payments through F-53,F-58.
    Awaiting your inputs...
    Regards,
    Rahul

    Hi Rahul
    In T code OBBH:
    Prerequisite: BKPF-BUKRS = `your co code` and BKPF-Tocde = `F-53` or BKPF-Tocde = `F-58`
    Substitutions:
    User Exit : U300 in modification pool ZGGBS000 add logic to check PO amount greater then Invoice amt
    Regards,
    Santosh

  • How to fix order value not to exceed a specified amount in a Purchase Order

    Can you please let me know the config steps required to fix a certain amount in a purchase order ( I mean to say one designated General Manager Purchase has got delegation of powers to issue purchase order for an amount of Rs. 10 lacs only).  Is it possible in MM or in FI BCS? Kindly provide config steps in detail if available in MM

    Dear Colin
    Would you please detail config steps to use OTB function since I am not MM guy but from FICO.  In release procedure value is not indicated in our case.  After creating the PO at one level Purchase Officer releases the order, next it goes to finance guy he just sees the terms and conditions then releases finally it goes to the GM he also verifies certain terms and conditions and finally releases.  Value is not incorporated at any stage.  Now we would like to have value.  Think it becomes difficult now to meddle with the release procedure.

  • Commitment in Purchase contracts and purchase order

    Hi,
    We are loading contract through LSMW. As account assignment we are just passing the cost center and the account is configure in OKB9.  However for some contract the flag is set in items affect commitments and the wrong account is determine. I want to know if this behavior is normal and why? How do you know how commitment is set up in the system?
    I have also seen that for some purchase order there are commitment lines that have been created in table COOI. Those pruchase order has been created through idoc and here again we do set the commitment flag.
    Thank you for your help

    Hi,
    Please consider that purchasing documents which do not have facility of GR, can not create commitment, hence commitment is not available for contracts.
    In case you want PR commitment to be adjusted against PO, please ensure that along with contract, PR number should also be filled in PO.Here I mean for EKPO-BANFN should be filled in PO then commitment would not be double.
    Case 1 with contract:
    When you post Purchase requisition.
    - Purchase requisition updates commitment.
    - You see purchase requisition amount in the report S_ALR_87013558.
    When you post Contract with reference to the Purchase Requistion:
    - Purchase requistion commitment stays as it is.
    - Contract doesn't update the commitment.
    - You see purchase requisition in the reprot S_ALR_87013558.
    When you post a purchase order with reference to contract:
    - Purchase requistion commitment stays as it is.
    - Contract doesn't update the commitment,
       When PO posted with reference to contract, there is no   commitment reduction for the contract either.
    - Purchase Order commitment is updated.
    - You see purchase requisition and order in the report S_ALR_87013558.
    Case 2 without contract:
    When you post Purchase requisition.
    - Purchase requisition updates commitment.
    - You see purchase requisition amount in the reprot S_ALR_87013558.
    When you post a purchase order with reference to requisition:
    - Purchase requistion commitment is reduced by PO posting
    - purchase order commitment is updated.
    - You see only the purchase order amount in the report S_ALR_87013558.
    The  attached note 151451 describes also the system behaviour.
    regards
    Waman

  • How to fix/control Purchase Order value as per delegation of powers?

    Can you please let me know the config steps required to fix a certain amount in a purchase order ( I mean to say one designated General Manager Purchase has got delegation of powers to issue purchase order for an amount of Rs. 10 lacs only). Is it possible in MM or in FI  to fix that amount of Rs.10 Lacs while creating Purchase Order  Kindly provide config steps in detail if available in MM or in FI?

    Three levels of release procedures have been configured in our company from purchase officer to finance and from there to the next higher level but not included any value/amount validation is included.   Is there any other option other than release procedure since I think meddling with the release procedure which is already working fine does not sound proper by our MM guys.

  • Posting againt asset purchase order

    Hi,
    We are careating purchae order against assest.When u are posting f-48 with same purchase order then get following error
    " Enter value will be exceeded"
    if i given less amount against purchase order amount then simulate document .
    could u give suggestion u are very urgent
    regardsf
    cvs reddy

    Dear CVS,
    Syatem giving u the error because u r exceeding the value of the PO coz u r giving down payment thru F-48. Meaning, u decided to purchase the asset for INR1000, and against that u r giving advance of INR200, then only system will allow you to post the down payment. How can u give down payment more than value of ur asset.
    So during a document entry, put the amount less than the PO amount.
    Regards,
    Ajay Gupte

  • SAP MM Purchase Order custom field pulling through to FI

    Hi
    I have no idea where to start.  I need to create a custom field in the Purchase order which has to pull through to FI.  I've created an Account Assignment category I - Insurance and need to have a field on the Purchase order where the users can fill in the Claim Number. (Reference field).
    I thought I could maybe use the Unloading point field as we don't use it currently, but it doesn't pull through to reports on FI.
    Secondly I would like to link my Account assignment category to a specific General Ledger account (when the user choses Aac I, I would like a G/L to automatically populate and be grey (no changes possible)
    Thanks so much!
    Carina

    I Actually think I found the answer here - http://www.bluemarlinsys.com/ns/0603-03.asp
    1) How to default a General Ledger account on a Purchase Order account assignment for an inventory item?
    When you create a standard Purchase Order using ‘K’ account assignment to expense an inventory item with GL account and cost center, the system expects you to key in GL account number and the cost center. In case you don’t want to use the account modification ‘VBR’ assigned GL account number, it is possible to default a separate GL account with standard configuration steps.
    a) Transaction: OME9 (Maintain account assignment categories)
    Create a new account assignment category ‘Z’ by making a copy of account assignment category ‘K’.  Change account modification to ‘ZBR’.
    b) Transaction: OMGO (Define combination of item categories/account assignment categories)
    Assign account assignment category created in previous step to an item category blank or space.
    Note:
    This is an optional step, if you don’t want to touch the standard ‘K’ cost center account assignment.
    c) Transaction: OBYC (Automatic account assignment configuration)
    Choose account transaction key ‘GBB’ by double clicking the existing entry and choose the appropriate chart of account for your company. Assign the GL account that needs to be defaulted for general modification ‘ZBR’ and valuation class ‘RAW’ (use appropriate valuation class set-up in your company).
    d) Transaction: ME21N to create a purchase order to test the configuration.
    When you create a PO with account assignment ‘Z’ for an inventory item, the system should default the above-configured GL account.
    2) How to default a GL account for a material group when a purchase order is created without a material master?
    If you want to create a purchase order without a material master (service/expense items), the standard SAP R/3 4.x and higher releases, offer functionality to assign a valuation class to a material group. This way automatic MM account assignment can be set-up to drive the appropriate GL account for a material group/valuation class in your company.
    a) Transaction: OMSK (Define valuation class):
    b) Transaction: OMQM (Entry aids for items without a material master):
    Assign the appropriate valuation class for a material group.
    c) Transaction: OME9 (Maintain account assignment categories)
    Create a new account assignment category ‘Z’ by making a copy of account assignment category ‘K’.  Change account modification to ‘ZBR’.
    d) Transaction: OMGO (Define the combination of item categories/account assignment categories)
    Assign the account assignment category created in previous step to an item category blank or space.
    Note:
    This is an optional step if you don’t want to touch the standard ‘K’ cost center account assignment.
    e) Transaction: OBYC:  (Automatic account assignment configuration)
    Choose account transaction key ‘GBB’ by double clicking the existing entry and choose appropriate chart of account for your company. Assign the GL account that needs to be defaulted for general modification ‘ZBR’ and valuation class ‘TRF’ (use the appropriate valuation class set-up in your company).
    f) Transaction: ME21N to create a purchase order to test the configuration.
    Standard order type, Account assignment category ‘Z’ and Material Group ‘TRAFFIC’.
    Account assignment screen:
    Note:
    Before configuring account assignment, please discuss this with your SAP FI/CO functional contact and Accounting department key user for mapping valuation class to General ledger account numbers etc.
    Some of my colleagues in MM Purchasing liked this configuration and I thought your company might also benefit from this in case you want to default the GL account in purchasing to avoid wrong account coding.  

  • How to accept purchase order in mail

    Hi Experts,
    We need to accept purchase order in mail, without login into system.
    Is there any way to do it.
    Thanks
    R.Sundaravel

    I believe this can be achieved thru workflow notifications and inbound response processing. Pl see these MOS Docs
    221268.1 - How To Make Use Of The E-Mail Function In The Purchase Order/Requisition Approval Form
    267159.1 - 11.5.x Upgrade to 11.5.9 -- Changes to Links in Requires Approval Notifications
    352594.1 - Email Approval Notifications In 11.5.10 are Different From 11.5.9 - How to force users to login to system?
    268085.1 - Configuring the Oracle Workflow 2.6/11i.OWF.H Java-based Notification Mailer with Oracle Applications 11i
    and the necessary PO and Workflow Guides at http://www.oracle.com/technology/documentation/applications.html
    HTH
    Srini

  • Rate Contract Purchase Order ! Urgent

    Rate contract purchase order –
    My Client Don’t wants to enter quantity in the Purchase Order –
    The purchase order is called as Rate contract purchase order (Contract for Per Unit rate of material only). Purchase order is created without entering the quantity. It has specific validity period and overall value limit (It is not compulsory). The multiple Deliveries from vendor are accepted (GR) and invoices are posted against this purchase order, for certain period of time.
    It is not possible in standard SAP configuration to make “Quantity” field optional or hide, because this field Mandatory in standard SAP program. 
    I suggested option of creating “Contract” and “Contract Release orders”, but our client doesn’t want to create the purchase orders on daily or monthly basis.
    Also scheduling agreement option is not working, because schedule lines are not final.
    Please suggest me the solution on this issue !

    Hi Vijay,
    to clear your doubt, SAP can make the Quantity display instead of Hide function. It not necessary to put Required, it can be Optional or Display.
    This also will work if you have PR for all of your PO, so PO QTY will be copied from PR QTY.
    you may need to check your configuration.
    IMG-MM-Purchasing-PO-Define Screen Layout at Document Level
    Regards,
    Maia
    Edited by: Maia on Apr 14, 2008 5:24 PM