MPS & MRP

As i understand, MPS is single item, single level planning generally done for expensive items. we have md03 also in mrp for single item single level. then wht is the difference between two? thanks in advance.

Hello,
Yes what you have observed is right but there are also following additional features of MPS which can be used (these are not there with single item multilevel run - md03.
Planning Time Fence
You can protect the master plan from any automatic changes to master schedule items in the near future by using a planning time fence. Within the planning time fence, the system does not automatically schedule or change the procurement proposals. Therefore, the MRP controller has time to plan the master schedule items manually. However, to support the MRP controller, the system can create necessary procurement proposals and schedule them for the end of the planning time fence. You can then schedule these procurement proposals manually as you wish.
Processing the Planning Result Interactively
With interactive planning, you can check the results of the automatic planning run for master schedule items with simple and easy-to-use tools and simulate changes and regenerative planning. The system does not save the planning data in the database until you save the interactive planning.
Interactive planning is especially useful for adjusting dates of planned orders falling within the planning time fence.
Evaluating the MPS Run
With the help of the user-friendly structure of the planning results, you can react quickly and efficiently to any problems that may occur. A series of standard evaluations are available within MPS to achieve this. You can also generate individual evaluations according to your specific needs.
Hope this satisfies you. Award points if benefitted.
Hemant

Similar Messages

  • Sales orders ans reservations not taken into account on MPS / MRP

    Hello,
    I am implementing the MPS / MRP and I have the following problem:
    I have modified the necessary material master fields to take into account some materials on the MPS / MRP execution. These fields are MRP type, Lot Size, Strategy group and Availability Check.
    Then, executing the MPS / MRP I have realised that only the sales orders and reservations created after the material master modifications are taken into account when I execute the MPS / MRP.
    I suppose this is because the sales orders and reservations created before the material master modifications did not create the requirements because the availability check was not set for the material and so on... but I need to take into account these "old" reservations and sales orders .
    Is there any way to "update" these orders and reservations?? Or I need to delete them and create new ones??
    There are several sales orders and reservations created before the material master modifications. I think there have to be an standard way to update them.
    Thank you very much in advanced,
    Jordi.

    Dear,
    Are you getting these reservation in MD04?
    Check the Planning file entry for these material in MD21 if not then create it through MD20 and take MRP run with planning mode -3 Deleted and recreated. And Processing key NETCH.
    Also check the The firmed receipt is within the rescheduling horizon. The rescheduling horizon is set in Customizing for the MRP group (Transaction OPPR, Table T438M). A default value can be predefined in the Customizing of plant data (Transaction OPPQ, Table T399D). define the longer duration for it.
    The firmed receipt (the MRP element) participates in the rescheduling check. You can set which MRP elements participate in the rescheduling check in the Customizing of the plant data (Transaction OPPQ).
    Else you can carry out modification A using the MD_CHANGE_MRP_DATA BAdI and the CONSIDER_RESB method without making a modification.
    Regards,
    R.Brahmankar

  • MPS & MRP - Whats the Difference.

    Hi..
    I am a beginner in PP , can anyone of can explain with clear steps after Demand Management triggering demand programs, which inturn will pass data to either MPS or MRP .... Under what Conditions MPS or MRP triggers, what are the main transactions involved for these Demand Program , MPS & MRP.
    I want to whats the main differnece between MPS & MRP ....( Is MRP a subprocess of MPS??)  Please anyone Can elaborate it  in detail.
    Links & Any Crisp detailed overview will be highly appreciated.
    Regards
    Balaji

    Hi
    There are three types of MRP levels...MRP (Material Requirement Planning), MPS (Master Production Schedule) and CBP (Consumption Based Planning)
    <b>MPS is part of MRP</b>
    In MPS you can plan important assemblies sepeartely (critical parts and which has much influence on the profit A type). You can mark the assemblies as MPS parts by assigning the <b>MRP types M0 to M4</b> in the material master MRP1 view.
    The main difference between both MRP and MPS is that MPS is only good for single level BOM explosion and used for mainly Type A materials which has higher value and importance and planned carefully and greatly influence the company profits or those that require critical resources whereas MRP is used for mainly Type B and C materials
    Main Idea is that Master production scheduling (MPS) is a form of MRP that concentrates planning on the parts or products that have the great influence on company profits or which dominate the entire production process by taking critical resources. These items are marked as ‘A’ parts (MPS items) and are planned with extra attention. These items are selected for a separate MPS run that takes place before the MRP run. The MPS run is conducted without a BOM explosion so that the MRP controller can ensure that the Master schedule items (MSI) are correctly planned before the detailed MRP run takes place.
    <b>Transaction codes</b>: MPS can be run from MD41 (single item multi level) MD42 (single item single level) and MDBS (Background plant level MPS) & MD40 (Foreground / Online plant level)
    Normal MRP can be run from MD02 (single item multi level), MD03 (single item single level) and MDBT (Background plant level MRP), MD01 (Online plant level)
    Hope now u r cleared.....Please reward if found useful
    Rgds

  • MPS/MRP : OPM Schedule Parameters

    Hi Folks,
    "If you accepted the default organization from the previous field, the code for the
    default schedule parameters assigned to the user/planner (in User Profiles)
    displays here."
    Above Paragraph i copied from OPM - MPS/MRP user guide.
    My query is :
    Where i can find the "User Profiles"?
    Please reply me, this is urgent i have to continue my setup.....
    Razzy

    Hi Razzy ,
    May be from Session Parameters > Default Values > Schedule
    Regards,
    Ram

  • MPS/MRP Recommendations in 11i

    When suggesstions are made in MPS/MRP what criteria is used to establish what jobs get cancelled and what jobs get rescheduled if net WIP is checked? Haven't been able to figure out the logic. Does it have to do with due date on job...or order quantity or what?
    Thanks in advance.

    Hi,
    We also need help on the logic of MPS. We have a scenario as below which we can't understand why system suggests to reschedule out discrete jobs. Please kindly give me your advices.
    Thks,
    ITEM A
    Demand = 0
    Supply:
    -Job A=100, start day = plan day + 3 days
    -Job B=100, start day = plan day + 3 days
    -Job C=5000, start day = plan day + 3 days
    We run MPS under the following situations and get some result we can't figure out why:
    1. all jobs are not firmed:
    ==> system suggests to cancel 3 jobs
    ==> this is OK to us
    2. firm job A & B, and job C is not firmed
    ==> system suggests to cancel C
    ==> this is also OK to us
    3. firm job C only
    ==> system suggests to RESCHEDULE OUT job A & B
    ==> why??
    We don't have min/max order qty for item A.

  • Not able to do Pegging for both MPS & MRP Workbench

    Hi Experts,
    We have implemented SCP (Oracle EBS 11.5.10.2).
    Loaded the forecast, then ran the MDS.
    Also ran the MPS (for finished goods). Later opened the MPS workbench, cannot see items for pegging.
    Please do the needful.
    Thanks.

    Chk the pegging attribute in the organization items screen (mrp/mps planning tab) for that item.

  • MPS/MRP Module

    Dear All,
    What would be the impact on MDS driven 1) MRP and 2) MDS driven MPS, MPS driven MRP?
    Also what would be the significance of using Relieve, Feedback and Production.
    Regards,
    Saravanan

    Hi Saravanan,
    Basically when defining a MRp,when you have your Feedback checked it means that you can keep a track on the qty of the planned order which has been relased to a discrete job or a requistion inpo or a purchase order .When have your production check box enabled it means that you are dropping the qty in the planned order directly ie.automatically to release.But here only those planned orders falling within ur release time fence will be released.
    Regards,
    Bala.

  • Filtering MPS / MRP proposals.

    Hello!
    In my system we have set following MRP parameters:
    MRP Type = M0
    Lot size = FX.
    Fixed lot size = 100000 PC.
    Every planned order has qty = 100000 PC.
    When sometimes appears planned dependent requirement for 1 PC, system automatically generate new planned order for
    100000PC. It is very bad situaton.
    Is there any parameters in master data where I could to eliminate this cases?
    I would like to decide, that when planned dependent requirements are less than 10% of fixed lot size, system will not generate any planned orders.
    When planned dependent requirements are greater than 10% of fixed lot size, system must generate planned order with fixed lot size equal to 100000 PC.
    How to solve this problem?
    Regards
    Bogdan

    Dear,
    "Last lot exact" (V439A-LASTL) into the Customizing of the MRP lot sizes (Transaction OMI4). Via this indicator you can define whether the last lot at the end of the net planning or gross planning segment is supposed to be planned exactly. In this case, rounding value, fixed lot size, minimum lot size and so on are not used for the calculation of the last lot. The MRP run creates the last procurement proposal exactly in the amount that an available number of zero results at the end of the planning segment.
    Or you can use the MD_CHANGE_MRP_DATA BAdI to consider or to exclude special MRP elements other than the ones that are defined in the standard system depending on a certain selection rule IM_SFILT import parameter. Here you need to apply your own logic.
    For more details solution use the BAdI documentation.
    Hope it will help you.
    Regards,
    R.Brahmankar

  • MRP & MPS PROBLEM

    Dear ,
    In my company we using MPS & MRP TWo planning mode.
    Also we use two type of planning .one SO base & other one is on PIR.
    I working with Process IND.
    In our company only for packing Mat. we use SO,meansfor
    FG we use MPS
    SFG we use MPS.
    ROH we use MRP.
    Here we got problem.
    Because by MB50 we got PLANNED ORDER for FG(A LEVEL ITEM).And SFG & ROH (B LEVEL item) we got Dep Req.And for ROH(C LEVEL ITEM)we not got any change.
    So my problem is that for B level item i have to run MRP or MPS agin.
    if it is single material then its ok but 10 or 12 material its become difficult for me that i have to run mps then again MRP.
    So what i can do after A level MPS.
    For B & c level material.......????????

    Hi ,
    Do this setting in your system , set up a back ground job for MPS materials and them set up the same for MRP materilas , this will solve your problem ., because MRP will run after the MPS run by which all your materilas will be planned accordingly .
    Thanks and Regards,
    Mallikahrjun.

  • MRP and MPS Run

    Hi all,
    I found some materials in my 'Quality Environment' which has their MRP type to 'PD' but the problem is planning run for those materials work with Transactions 'MD02' and 'MD41' as well .How is this possible ? Is there any provision in 'SPRO' to enable such ? If so what is the point in doing so ?
    Regards,
    Rahul

    Hi Rahul,
    MD02 = Single Item multi level.With use this transaction you can run MRP for single material but system will planned up to its last level of BOM.So its called as single item multi level.
    But most important condition is MPS mrp types (M0/M1/M2) are not allowed this run.
    While MD41 is also a Single Item multi level and can be used to run MRP up to last level of BOM.
    But its advantage over MD02 is it can be used for both PD and M0 types of MRP types.
    Thanks & Regards,
    Ramagiri

  • MPP, MPS/MPP, MRP/MPP Type(In Item Attribute)

    What is the difference between we use MPP, MPS/MPP, MRP/MPP Type(In Item Attributes)?

    Lokesh,
    ASCP Release 11i10 included a significant number of enhancements related to master scheduling, two level scheduling, and hub & spoke processes. At that time, Oracle was also planning the release of a major new product offering Distribution Planning (also called Deployment planning), this was introduced in Release 12. As part of these improvements, Oracle changed the traditional name for DRP plans to MPP (Master Production Plans) to avoid any confusion with the newly created DRP product. The old functionality of having multiple plans work together (DRP,MPS,MRP) in a chained fashion still works, but the names are now (MPP,MPS,MRP)
    The item attributes were changed as shown below:
    - Not Planned
    - MRP Planning
    - MPS Planning
    - MRP/MPP Planned
    - MPS/MPP Planned <<-- formerly MPS/DRP planned
    - MPP Planned <<-- formerly DRP planned
    These attributes have the same meaning as before and a full description can be found in the Oracle MRP/Master Scheduling User Guide
    Regards,
    Kevin Creel
    www.inspirage.com

  • MRP planning components at multiple plants

    I would like to present a unique scenario, we have a plant and a warehouse both are created as two different plants in SAP.
    When we run MPS/MRP at a Finished product (FERT) level at the mfg plant, I would like to
    1) Consume inventory of components (Packaging material - VERP) at the plant first
    2) It should then consume inventory of packing material from warehouse
    3) Only then it must creates a procurement proposal for the remaining qty at the mfg plant.
    4) There shall not be procurement proposals created at a warehouse, all proposals should be directed to the plant.
    Most of them would advice to create the warehouse as a storage location within the manufacturing plant but that is not possible due to financial reasons.
    Flood me with ideas.

    Hi Manoj
    The standard MRP cannot consider stock in different plants for the same material.
    Please observe that this issue has been already discussed on several thread on this forum. Check  for example my answer on the thread below:
    MRP Run considering Stocks for Multiple Plants and Requirement maintained for Plant Cluster
    BR
    Caetano

  • Problem with MPS Run

    Hi PP Gurus,
    A FERT material say u201CXu201D has following details.
    Type: FERT, MRP type: M3 (MPS fixing Type 3),
    Planning time fence- 14 days
    Material u201CXu201D is a subcomponent of say u201CYu201D (Parent Material)
    Material u201CXu201D has a subcomponent say u201Czu201D
    Back ground job is getting executed on daily basis for both MPS/MRP.
    But all the materials are not getting planned on daily basis.
    So , I need clarifications for below questions
    *a) what are all the prerequisites for planning MPS/MRP run*
    *b) Is it the requirements gets planned daily or incase of any changes occur in the requirements?*
    *c) How planning time fence works out?*
    Thanks and Regards,
    Kiran

    Dear Senthil,
    Good day
    Thanks a lot for your immediate response and got clarified, However could you please elaborate on following on our specific issue?
    As Indicated in previously, the BOM has folowing material combinations.
    " X"is the parent material (FERT)MRP type: M3 (MPS fixing Type 3),
    " Y" is the subcomponent of "X"(FERT)MRP type: M3 (MPS fixing Type 3),
    "Z" is the subcomponet of "Y"(HALB)MRP type: P3 (MRP fixing Type 3),
    Scenario:MRP/MPS is getting run on daily basis.But on specific date,we noticed that material"Y" has not planned and planned orders exists ( as per previous MRP run) within the time fence only(MD04).But if we run  MRP on "Y" material individually, the planned orders got shifted to outside of the time fence!!! This means some changes occured for planning file!!! and subsequent quanties being planned outside the time fence.
    As per your response, we assume the following.
    Since , no changes occured for materail" Y" no MRP being carried out on specific date.right?
    But, how come the planned orders being moved outside of the time fence, if no changes occured in planning file?
    Thanks,Kiran

  • Set Sales Order as non-MRP Relevant

    Hi Folks,
    Ive been researching for the right discussion/instruction how to set this up, but no luck. 
    Requirement is that we need to set a certain type of SO to be NOT relevant for MPS/MRP Planning.  The SO should still show up in MD04, but will have NO effect to MRP calculation.
    Any thoughts experts?
    Thank you.

    Hi Manoj,
    we can achive this through Schedule Line category. go to VOV6 there select the schedule line category which you are using. in that under  Transaction Flow Tab Uncheck req/assembly By this we can control the Display of Sales Order in MD04.
    if we do this it will Affect All the Sales orders which are using this shedule line category. so you configure the new Schedule line category and new Item category And Do new Item category Determination by using The Sales order type which you want to implement and  New item category and schedule line category.
    this configuration mainly relavent to SD so take halp Of sd consultant.
    Thanks&Regards,
    Venkat.

  • Detailed information on MRP error

    Hi,
    I'm trying to understand why some materials show up in error in the report following our MPS/MRP run through MD40. I have a number of materials that are permanently stopped (both X-plant and plant specific material status), that aren't in any BOM, but nevertheless show up in error (exception 8) in the report.
    Could you help me understanding:
    - how can I further investigate the output of this report so I can understand what goes wrong?
    - what exactly determines whether or not a material is taken into account during an MPS/MRP run? Is it simply defined by the scope of planning and then everything which has dependent requirements? Or is there another way to control? (I'd like to understand why the permanently stopped materials are still showing here).
    kind regards & thank you very much!

    Hi Himanshu,
    see [this link|https://public.sn2.livefilestore.com/y1pGBOy37cozZG2xh_f4k54Le5fCdjqay5LkcVj5GMqZFr_lQf0NZnETGaIE3ell4bNbf3PNghiMXwi1NguU6ZZZA/575074%20Error.JPG?psid=1] the screenshot from MD05 and the [MRP list|https://public.sn2.livefilestore.com/y1pjXQjaDRcwRHkDdP2feCpFAQF66L7d5G4UAr4A27yNF9xZxWVyKMQpPua4U_40QNotC3VzrKPJubcn4cDSSJ3Uw/575074%20MRP%20list.JPG?psid=1] (which I took while putting the material temporarily active and run the MRP.
    I do understand that the error is now because the material is permanently stopped. However I do not understand why the material is showing up here anyway, as it does not have any dependent requirements. I have plenty of other permanently stopped materials that do not show up in error and I don't see the difference.
    Thank you very much for your time,
    Nico

Maybe you are looking for

  • SQL 2012 SP1 installation quick questions

    I am installing my first SQL 2012 SP1 Enterprise Core (x64). The installation failed to install some services due to an error installing .Net framework 3.5. It was able to install successfully several features including Analysis Services and Integrat

  • Dropdown list in dialog programming

    Moved to correct forum by moderator.  Subject amended.  Please use meaningful subjects in future Hi Experts, How to get a drop down list in Dialog Programming. I need a drop down list for a field called country. Should it be done in Layout Editor or

  • Print Pages as spreads without Print Booklet???

    I have a document made up with 6 page spreads and 4 page inside. Trying to ouput a proof. I the 6 pages printed fine. But I want to print pages 3-6 as spreads, as in 6,3,4,5 and to print back to back. But pages 4,5 came out as spreads and 6,3 came ou

  • My gift cards are not being redeemed.  Still charging my credit card.

    My gift cards are not being redeemed.  Still charging my credit card.

  • My computer has 8g of photos but I don't know where they are!

    I think I may have done something in the past to mess up the library since I can't figure out what is going on. My disk is full, only 1.7 g left- I downloaded whatsize to see why, and it shows over 8 gigs in my photos, but I only have 500 photos, jpg