MRP and Factory calender question

Hi all,
When MRP runs  to replenish stock from planned orders using production planning and/or Purchasing (Planned orders to Requisitions or production orders), is it replenishing stock based on lead times in a 20 day per month (excluding SAT and SUN and company holiday) format or full calendars days? This would also be an input to contracts/agreements etc.
Please advise.

Hi ,
While planning MRP takes inhouse production time  for inhouse materials and is calculated in work days which referes to actual working days from factory calendor.
normally for purcahsed parts, planned delivery time ( PDT) is maintained in material master and this is actual calendor days. This does not consider the actual holidays from factory calendor.
Regards,
Santosh Sarda

Similar Messages

  • Difference between Holiday Calender and Factory Calender

    What is the difference between Holiday Calender and Factory Calender.

    Holiday Calendars is used in Time and Payroll. It is Holiday Calender which is used in defining Work Schedules Rules for different regions.
    In simple, we can say... it is defined for Employees.
    Factory Calendar in turn in used in Shift Planning concept, T&E Mng, in defining/planning for Units.
    In simple, we can say... it is defined at Unit(Area) Level.
    Eg: Employee can be on holiday based on holiday calendar assigned to his area. But Factory may be running/open on the same day.
    Regards
    ...Sadhu

  • How to get past date based on duration and factory calender?

    Hi All,
    when i enter the duration ,i want to get the past date based on factory calender w.r.t current date
    i.e if current date is 26th jun and duration is 10 , the past date should be 12th jun (which should exclude all holidays and weekends).
    Thanks
    Vasumathi

    Hi,
    Please check this FM: I think this will resolve ur issue.
    END_TIME_DETERMINE
    Cheers,
    Vijay.

  • Changes in holiday and factory calender ?

    Hi Gurus,
    i have to delete a holiday from my holiday calendar ? i  have some doubts about transporting the changes to quality and prd can anybody explain how we have to trans Port CALENDER

    Hi Mahesh Kumar,
    The Best Practice in mantaining Factory Calendar is to Transport the calendar from development to quality and to Production. However, it comes with it's own share of risks as it is a table transport.
    To avoid those risks, it is suggested to block SCAL via SM01 for users and give access when the changes need to be moved. There is a process which needs to  be set up which creates the necessary checks and balances involving the change.
    Now, when you transport, you need to make sure that the changes you are moving are only the changes you did currently. Changes which have been done by someone else in the FC would remain with the object as FC object does not ask for transport when you are saving the changes.
    So, in order to accomplish the above objective, you need to compare the Factory calendar , Holiday calendar tables. Compare the tables of Development & Production, download the tables to excel. Use some excel formulaes to match the entries of table in one worksheet with the entries in other worksheet. The conclusion of the comparison would be that only changes which you are doing currently are moving with the transport and no other changes are moving.
    There are 3 important tables out of 13-14 which need to be compared: TFACS, TFACD & THOCI.
    BR
    Rahul

  • Holiday Calender and factory calender

    Hello Experts,
    I have one scenario in my current implementation for one of the textile industry,
    Here management and staff have total 5 public holidays in a year
    But for workers its 2 public holidays in a year (in deewali  -- for that 2 days only plant will be shut down).
    How to do that in SAP?
    Do I have to define 2 different holiday calendars?
    Or something else?
    Please let me know
    Thanks and Regards
    Jaydeep Jadhav

    Dear Jadhav,
    You should create
    one Holiday Calendar for Corporate
    one Holiday Calendar for Plant
    I guess, once the plant is shutdown, even the managers will also get the holiday who are working in plant!!
    ESG Grouping for MGRS, STAFF and Workers can be only One.
    Holiday Calendar for Plant is different
    thus, Managers in Plant will also get the holiday.
    FACTORY CALENDAR is nothing to do with Employee Holidays... its only HOLIDAY CALENDAR which defined holidays to employees.
    Regards
    ...Sadhu

  • Factory Calender and Planning Calenderr

    Hi,
    i want to plan my production for 7days a week. and want to plan for Raw materials also 7 days a week.
    but here my requirement is that i dont want to receive raw materials on weekends. i mean no one will be in Factory to receive raw materials on Weekends.
    If i maintain Planning Calender for 7 days and assign to Raw materials in MRP View 2 and Factory Calender for 5 days can i achieve this requirement?
    for in house production i have to plan for 7 days a week. (Scheduling and Capacity Calculation)
    i dont want to receive rawmaterils in weekends.
    Please suggest.
    Thanks
    Nag

    Dear
    Based on your business requirement ,  you should have the following set up :
    1.One Factory Calender  with Work Days Monday-to-Friday  Let say FC1 .This will be used on all the organisational level starting from Materials Planning to Sales  .But will not be assinge to Capacity Requirement Planning Purpose or Any Production Activity in Work Centre .
    2.You should have one more Factory Calander with work Days Monday to Monday ( 7 days week ) with some special rule like Plan Shutdown Days , Breakdown Maintainnece  etc  and this should be assinged to  all the work centres -CR02-Capacity Tab -Capacity Header -Factory Calader ID -Let say it is FC2.
    You need to ceate Calander in OP03/SCAL .It does nto have any transport and  it will be a Cleinet level changes  which requires proper approval .Please rememeber , you need to assing only FC1 to Plant assingement in OP03 where as FC2 will be asisnged only in Work Centre level  .
    Steps : Goto -OP03
      1.Identify all those Public Holidays frist with Fixed or moveable as per business requirement
      2.Goto Holiday Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
       Add all those holidays as per Public holidays as applicable in your business  with proper valididty  and finally SAVE
    3.Goto Factory Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
       Asisng Hioliday Calander . In case of FC2-Work centre Calander , here you can hit the Special Rules .Include Special Activity like Plan Shut down of factory with Validity  etc and SAVE .
    4.Come back to OP03 main screen -Assing the factory Calender in plant .
    5.Goto -CR02-Capacity -Capacity Header -Available Capacity Header -Factory Calander-Assing FC2
    I do not  think you should have planning calander seperately if you do not have any specific reason .
    Hope it helps
    Regards
    JH

  • Schedule a process chain using factory calender

    Hi All,
    My requirement: the user wishes to see the report every month, 1 working day prior to the month end.
    I am trying to do this usnig processing chain and factory calender to restrict it.
    1. How can a factory calender be used ?
    3. how do i give the offset of 1 working day prior to month end?
    2. If you have any such experience please share.
    Please help.
    Rohit Kumar.

    Hi,
    In the start process open the start time parameters screen. Then click on the button '>>' next to 'at operation mode' button. In the following screen, give the factory calender. In the workday column give 2. Choose radio button 'end of month'. In the period field give the frequency of the loads, i guess it should be 1 for you as you want to load monthly. So the job runs on the day before the last working day.
    regards,
    Murali.
    Edited by: Murali Krishna K on Jun 23, 2008 5:27 PM

  • Factory calender transport- not allowing

    I have created a holiday calender and factory calender.
    I have assigned the holiday calender to factory calender.
    In the initial screen of factory calender, when i selected calender from the menu
    the transport option is greyed out.
    So i am not able to create transport request.
    Please sdvice how to solve this?
    Regards
    Govindarajan

    Hi,
    Its related to authorization,check with BASIS guys,they will help you.
    Refer this SAP note
    https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=86621
    Hope it helps

  • How to Transport Factory Calender to QTY and PRS systems

    Hi All,
    I had done a small change to Holiday calender in SCAL. I have read that it's not suggestive to transport it. Can any one let me know the procedure to transport the change to QTY and PRD systems.
    The transport button is greyed out .
    Best Regards,
    Sri

    The following OSS Notes have also been checked.
    356483 : Customizing: Current settings in the test system.
    077430 : Customizing: Current settings .
    328916 : Cust Changes despite "System cannot be changed" setting
    Can any one provide an input on the procedure to move a factory calender - Individual entry..
    Thanks in advance
    Sri

  • Factory Calender and Time Stream

    Hi,
    I Maintain a factory calender A
    where monday to friday is working
    and holiday on 1/1/2009
    My Distribution centre is working 1/1/2009
    How do i set up in APO?
    thx

    Maintain Production calendar (For Factory) and Distribution calendar (For DC) using transaction
    S_AP9_75000138 - Maintain Planning Calendar (Time Stream)
    In calculation rule maintain 5 days as working day using calculation rule "Weekdays"
    then go to bucket delete day 1/1/2009 if showing as working day in Production calendar and keep this day as working for Dist calendar.
    Then go to Location master in Calendar tab
    assign Production calendar for factory location and distribution calendar (in shipping and recving) for DC.

  • Set factory calender and user requirement date calculation

    Hi Gurus,
    I've requirement to do calculation for start user requirement & end user requirement. The calculation must exclude public holiday and weekend. Therefore factory calender need to be maintained.
    Please guide me into doing this.
    regards,

    Dear
    Based on your business requirement ,  you should have the following set up :
    1.One Factory Calender  with Work Days Monday-to-Friday  Let say FC1 .This will be used on all the organisational level starting from Materials Planning to Sales  .But will not be assinge to Capacity Requirement Planning Purpose or Any Production Activity in Work Centre .
    2.You should have one more Factory Calander with work Days Monday to Monday ( 7 days week ) with some special rule like Plan Shutdown Days , Breakdown Maintainnece  etc  and this should be assinged to  all the work centres -CR02-Capacity Tab -Capacity Header -Factory Calader ID -Let say it is FC2.
    You need to ceate Calander in OP03/SCAL .It does nto have any transport and  it will be a Cleinet level changes  which requires proper approval .Please rememeber , you need to assing only FC1 to Plant assingement in OP03 where as FC2 will be asisnged only in Work Centre level  .
    Steps : Goto -OP03
      1.Identify all those Public Holidays frist with Fixed or moveable as per business requirement
      2.Goto Holiday Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
       Add all those holidays as per Public holidays as applicable in your business  with proper valididty  and finally SAVE
    3.Goto Factory Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
       Asisng Hioliday Calander . In case of FC2-Work centre Calander , here you can hit the Special Rules .Include Special Activity like Plan Shut down of factory with Validity  etc and SAVE .
    4.Come back to OP03 main screen -Assing the factory Calender in plant .
    5.Goto -CR02-Capacity -Capacity Header -Available Capacity Header -Factory Calander-Assing FC2
    I do not  think you should have planning calander seperately if you do not have any specific reason .
    Hope it helps
    Regards
    JH

  • Factory Calender and Holiday calender

    Hai experts,
    I am new in CRM. Can anyone tell me what is Factory calender and holiday calender in detail? And how to create it?
    Anoop

    Hi
    this below blog will solve ur problem
    How to create a new Factory Calendar in BI system
    hope above solves ur issue
    regards
    prakhar

  • How to extend factory calender to a plant ?

    Hi Ranga:
    How to extend factory calender to a plant ? ( Tcode: SCAL, The calender is not client specific)
    I check marked US factory calender, where after can you tell how to extend factory calender to plant
    Note: I am using IDES ( International Demonstration & Education System)
    Thanks

    Hi Sandeep,
    you need to use the following path
    Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
    Here you need to assign the factory calendar. The assignment in work center will only applicable for capacity not for MRP and others.
    <b>For information how to create a factory calendar</b>
    Pl follow the steps
    1.Go to SCAL transaction
    2.there will be three options.
    Click first public holidays and go in change mode.
    Click create and create your holidays there and save.(Generally fixed date will be used in the pop up)
    3.Now click Holiday calendar and go in change mode.
    Click create and give holdiay cal id and description.
    Click assign public holiday and add your holidays one by one and save
    Now holiday cal is created.
    4.Now come out and choose fact calendar and go in change mode
    Click create and give Factory calendar id and description, and validity period.
    Give the holiday calendar ID.
    If you want to give special rule like any of the specific date/ day is the holiday or work day (which is different from holiday calendar you can define)
    and save.
    5.You have to assign factory calendar to PLANT
    Go to SPRO>ENTERPRISE STRUCTURE->DEFINITION> LOG GENERAL>DEFINE COPY,DELETE AND CHECK PLANT>DEFINE PLANT
    Choose your plant and go to details-
    You have to define factory calendar there
    Hope this will help you
    Regards
    Ranga

  • Infocube or ODS and abt Calender days

    Hi Experts,
    1. I have a question regarding summarising data.. In reality we summarise data by week or month or by any chracteristic values.. Can anyone tell me which Object ODS or Infocube is best for summarising data.?
    2. My client wishes to move to normal calender from Fiscal/Factory Calender. Has anyone done that before.?. what are the impacts we may face and hwo can we overcome this???? Where can  i start so that i have least impacts.??
    Thanks in Advance
    DV

    HI DVMC,
        To summarize records based on Time or Normal Characteristics value it will be best to use cubes rather than ODS. When user prefer detail level of data they will be going for ODS if they want summarized historical data than they will be going for reports build on cube I mean to say that Cube will contain summarized data while ODS contain Detail data.
       Most of the companies will use Factory calendar rather than normal calendar because the fiscal period of each company differs. When Normal calendar changes to Factory calendar than  fiscal period start, fiscal variant will be changing for example: In my company fiscal period starts in May and end in April so Fiscal variant is 05(May) and Fiscal period 001/2005 is June 2005 etc...Let me know if u have any questions.
    Please assign points if its helpful.
    Regards
    Satish Arra.

  • Factory Calender assigned to Plant & resource/Work center

    Hello,
    If we have assigned the Factory Calender "XX" which has 5 working day(Monday to Friday) with no Special rules & no Holiday Calender to Plant & "YY" Factory Calender to Work center which has 365 days working with no no Special rules & no Holiday Calender.Now, when MRP creates Planned Orders for FERT material It did not create it on Weekends(i.e. on Saturday & Sunday) though the factory calender assigned is  "YY" (which has 365 days working )in work center.Why?
    Actually it should have consider the Work center assigned Calender for Capacity planning & Schedulling purpose.
    If I assign the Factory Calender "YY"  to plant then it will create the procurement proposal on weekends which is not acceptable to external procurement MRP Controller as plant office works only 5 days.
    Please guide.

    Dear
    Goto CR02/03 , select the Capacity tabe "hat" and u will fined there is tabe "Available Capacity " .U have to maintain the Active version ok.
    Basically , the active version is used for scheduling and capacity planning. If you have not entered an active version, the standard available capacity is used, even if an available capacity version has been entered.
    At the same u have to check out the below requirement :
    you must maintain the following data in the capacity header:
    1.The grouping, that defines which shift sequences and shift definitions can be used to maintain the available capacity
    2.The number of the active version of available capacity
    3.The base unit of measure of the available capacity
    3.The factory calendar, that is the basis of the available capacity-Workcentre
    If you do not enter a factory calendar , the system uses the default calendar for the plant.
    I hope in your case , u have the shift sequence of 5 work days for the calander you have assinged in work centre .
    Please check all those n come back .
    Reward points if usefull.
    Regards
    Jia

Maybe you are looking for

  • How to create job to run daily based on form values entered and send mail.

    Hi, In DB we have 3 columns: creation_date, name, approved_or_not. Default for approved_or_not is 'No'. In the application form page suppose I fill in sysdate for creation_date and leave default for approved_or_not and click [create] button. Now a jo

  • Three monitors, one G4, cant seem to make it work, HELP!!

    i have one G4 desktop that has been using two monitors for some time now, but tonight i tried to add a third and the whole thing has gone to ****! the second display that was originaly working is no longer showing up, the new one (the third) seems to

  • Idvd 8 can't burn crashhh

    Can,t burn disk image or burn direct to DVD. He crash after learn theme he don't go to movie??? he crash after just 1 minutes??? before from 1 year never problem?? Solution please! Michel

  • Error during material determination for sales document item - RRB

    Hi Iam getting following error when trying to create a billing request using DP91. Error during material determination for sales document item 40001560/000010 Message no. AD01155 Diagnosis An error occured during material determination for a dynamic

  • At Windows startup it tells me that it can not find zchvwceaw.dll

    After windows loads a box pops up on the desktop titled: RunDLL In the box is a message: X There was a problem starting C:\Windows\system32\config\systemprofile\AppData\Roaming\Mozilla\Mozilla\zchvwceaw.dll I have uninstalled Firefox and the box stil