MRP Apportioning purchase requisition .

Hi friends,
I would like to ask for your help redgarding the process or function, its possible I apportioning (purchase requisition )  per vendor.
Example 1:
Vendor A = 30%
Vendor B = 70%
Requeriements = 100 Ton
Split:
Purchase requisition 1 Vendor A = 30 Ton
Purchase requisition 2 Vendor B = 70 Ton
Example 2:
Vendor A = 25%
Vendor B = 25%
Requeriements = 100 Ton
Split:
Purchase requisition 1 Vendor A = 25Ton
Purchase requisition 2 Vendor B = 25 Ton
Purchase requisition 3 = 50Ton ( no vendor split)
Your help is highly appreciated.
Thanks,
Molina

Hi,
It is possible by using  Quota Arrangement, so first you need to active  Quota Arrangement in MRP2 view and lot size with quantity split. Then define quota arrangement MEQ1 with diffrenet % of material for different vendors.
After that MRP Run and check the result.
Regards,
R.Brahmankar

Similar Messages

  • MRP - Single Purchase requisition for multiple Items

    Hi
    We have recently introduced MRP module in SAP .In some specific scaeanrios , we want to create a single Purchase Requisition for multiple items .Standard SAP generate different Purchase requisition for each item
    Is there any way out

    Sandeep,
    This topic has been covered numerous times in this forum and in the MM forum.  You evidently have not used the search feature.  There are thousands of posts in these forums, and the search function will be very helpful for you in future questions.
    To answer your question, No, nothing is available to make standard SAP MRP create Purchase requisitions for multiple items.
    Most companies address this issue during the conversion of Purchase Requisitions to Purchase orders.  During this process, you can add many items to a single purchase order.
    Rgds,
    DB49

  • MRP and purchase requisition document type.

    Hi
    where can I set the purchase requisition document type for
    MRP?
    MRP generates purchase requisitions using document type NB instead of
    a custom document  type.
    <b>How can I set the system so that generates purchase requisitions with
    a custom document type?</b>
    Best regards

    hi,
    in Tranasction : OPPQ, you can assingn the user defined document type.
    here standard is NB. There you can change the doucment type to ZNB like.
    hope this may help you,
    Regards,
    Srinivas

  • Problem in MRP generated purchase requisition.

    Hi Friends,
    We have run MRP via MD02 transaction for one material.
    MRP generated purchase requisition created.
    In that MRP generated purchase requisition, under item level in the status tab we are getting below field values is like below.
    Processing status : No edited
    Block ID: Blocked by requester.
    Due to above values we are not able to convert this MRP PR to PO.
    Could you please let us know is there any master setting is cause of this?
    Thanks in advance.
    Regards
    Jegen Mohan

    Hi Friends,
    After debugging MRP programme, we came to know that there is BADI implemented to block the MRP PR's intially and then z programme called for adding secondary materials/services to that MRP PR's.
    After addition of secondary materials/services to MRP PR's,  Status will be unblock automatically then save the PR.
    This is my client specific scenario.
    Thanks & Regards
    Mohan.

  • MRP no purchase requisition generated

    Dear Experts,
    I have a problem that I can't generate purchase requisition after MRP run.
    Example : I have a finished goods material FG and under which has 1 component Mat 1.
    The setting in material master of Mat FG is internal procure(E), MRP type = "PD".
    Mat 1 is external procure(F) and MRP type = "ND"
    I entered the forecast requirement in MD64 for Mat FG  and I set the Create PR indicator to 1 in MD02
    and start running MRP.
    Planned order created for Mat FG, but no PR created for Mat 1 which only shows dependent requirement for Mat FG in MD04.
    I can't see there is Mat 1 in the planning file(MD21) under Mat FG.
    Any settings I missed and can anyone help?
    Thanks a lot.
    Claude

    Hi,
    IF you  do not maintain mrp type PD then system wont consider the material during MRP run, so convert it to PD.
    Also go through the below link which will clear your doubts of master data maintenance for MRP.
    [http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/30f4d6c1-0808-2d10-2ea5-f9b2863cfed8?QuickLink=index&overridelayout=true&47034186922243]
    Please check and revert.
    Thanks
    Hrishi

  • MRP: Delete Purchase Requisitions and Create Planned Orders

    Hi there,
    I have a scenario, where in a material (HALB) was marked as externally procured. MRP was run for FERT material. The dependent requirements for FERT were created. Planned orders of the HALB material were changed to Purchase Requisitions.
    Later, the procurement type of material was changed to Inhouse Production.
    Now, I want all the Purchase requisitions that were created to be deleted and Planned orders should be created when I run MRP.
    I tried all the possibilities, but of no success.
    Please lemme know if there is any possibility to delete the P.Rs and Create Planned orders by running MRP.
    Regards,
    ABC

    I Haven't read the Plan order is converted in to PR Before
    If YOU convert the plan order in to PR, system will firm the Requirement, YOU need to remove the firm indicator FIxed iD in PR Before doing the MRP Run Again
    Do the following thing in PR
    In PR Remove the  Fixed ID in Quantities and Dates tab of the item
    and Rerun the MRP with Planning Mode 3 It will create a plan order
    Edited by: Sundaresan . E. V on Oct 29, 2010 6:39 PM

  • MRP and Purchase Requisitions..

    Hello,
    I want to know
                 When MRP generates the Purchase Requisitions which has many due dates per lines,  how does the dating logic work. Can we state create one PO for all lines due on a specific date and create a second one for other dates.  So there for a Purchase Rec, could turn around multiple PO based on dates. We want one PO per due date, not nested due dates within the PO. It is also my understanding that this can be automated. If you automate rec to PO, can you do this per question above on PO per due date
    Thanks
    Kris

    Please see response below:
    When MRP generates the Purchase Requisitions which has many due dates per lines, how does the dating logic work.
    [ANSWER] The due dates or delivery dates are completed as follows:
    Delivery Date = PR Release Date + Purchasing Processing Time + Planned Delivery Time
    with the following notes:
    1. PR Release Data -> Time that the PR is ready for conversion to PO
    2. Purchasing Processing Time -> the period it takes for the purchasing department to convert the PR's into POs; measured in work days and is maintained in Materials Management under Consumption-Based Planning u2192Plant Parameters u2192 Carry Out Overall Maintenance of Plant Parameters.
    3. Planned Delivery Time - period it takes from the receipt of the PO (by the supplier) to the delivery of the goods onsite. This is measured in Calendar days and is maintained on the Material Master Record, Vendor Master Record or the Purchasing Inforecord
    In addition, the Material Availability Date is computed as
    Availability Date = Delivery Date + GR Processing Time
    where
    GR Processing Time - time it takes to process the delivery (i.e. unpacking, storage, etc) for internal use; measured in work days and is maintained in the Material Master Record
    Can we state create one PO for all lines due on a specific date and create a second one for other dates. So there for a Purchase Rec, could turn around multiple PO based on dates. We want one PO per due date, not nested due dates within the PO.
    [ANSWER] We can do that by using the delivery date as one of the parameters for PO creation. Although, please note that there are a lot of factors to be considered for PO creation, not just the delivery date
    It is also my understanding that this can be automated. If you automate rec to PO, can you do this per question above on PO per due date
    [ANSWER] Yes, this can be set in ME59N, to create a new PO per delivery date. Again, please take note of the other dependencies/requirements for creating POs as well as the other requirements for automatic generation. Note that your business processes must be healthy enough to allow the system to automatically create the Purchase Orders
    Hope this helps
    Regards,

  • MRP split purchase requisition with same date

    Hi guru
    When I run MRP, if there are more requirements for the same material with same date, the system creates one purchase requisition grouping requirements.
    So, if I have two requirements of 3 and 2 pieces for material A, with date 18042015, the system creates one purchase requisition of 5 pieces
    I tried to use a BADI in order to split purchase requistion and have in this case a purchase requisition of 3 pieces and another one of 2 pieces but maybe I wrong something because MRP works wrong.
    Is there anyone that could give some tips about this request? Is there anyone that had same problem?
    Thanks
    Regards
    Raffaele

    Hi,
    Hope your BAdI is working now.
    MD51 is used for project. It creates replenishment orders against a WBS element. After this, you can run MD01 which will create replenishment order by material/plant level.
    If you have a question related to PS, maybe you can post your thread in this space:
    SAP Project Systems (SAP PS)
    Kind Regards,
    Mariano

  • Document type for MRP generated Purchase Requisition selection

    Hi,
    when I  run MRP ,for externlal procurement items system is creating Purchase Requisition with Document type NB.How to make system to take different Document type automatically with MRP.
    Thanks and Regards
    Raghavendra Pai

    Dear,
    Follow below steps to fullfill your requirements:
    1) Go to Tcode OMDT.
    2) Click on MRP group
    3) In front of your plant  maintain your  doc.type purchase requisitions for standard purchase ord which you want to generate at the time of MRP --PR generation.
    4) Go to Tcode MM02---maintain MRP group  same as above parameter in MRP-1 view .
    Now run MRP..it will pick the defaulted Document type for PR generation via MRP.
    Regards
    Utsav

  • Document type selection for MRP generated Purchase Requisition

    Hi,
    when I  run MRP ,for externlal procurement items system is creating Purchase Requisition with Document type NB.How to make system to take different Document type automatically with MRP.
    Thanks and Regards
    Raghavendra Pai

    Dear,
    Go to SPRO-Materials Management--Purchasing Purchase RequisitionDefine Document types
    Copy the NB and create and New Document type
    You can default the document type from the MRP group.
    Customizing is done in OPPZ transaction.
    Once you have entered the MRP group to your material master MRP view, then next MRP run will create the requistions using the document types maintained to the MRP group.
    Please refer the OSS Notes- 46919 and this thread,
    Purchase req doc type in MRP
    Regards,
    R.Brahmankar

  • MRP Put Purchase Requisition date one day before the Independant Req

    Hi Experts,
    There one  Independant Req per month dated the 1st day of the month.  When I run the MD02, the Purchase Requisition is placed the 1st day of the month. we do not maintain Planned delivery time. We would to have as Purchase Requisition date ; the last date of the previous month.
    We have :
    01.12.2010     PurRqs     0010011236/00010
    01.12.2010     IndReq     ZLS1
    We would like to have
    30.11.2010     PurRqs     0010011236/00010
    01.12.2010     IndReq     ZLS1
    Pl explain me what to do!
    Thank you for your help!
    Rgds
    Thibaut

    Thibaut,
    The easiest way to offset the date of the supply element from the date of the demand element by one day is to put one day into "Goods receipt processing time" in the Material master of each material.  (purchasing tab or MRP2 tab).
    Rgds,
    DB49

  • Purchase requisitions are not created for Component by MRP

    Hi,
    I have created planned orders for assy. When I run the MRP the purchase requisitions are not created by  MRP for the components. If I check the planned order the components tab is showing all the raw materials list as per the BOM. The master data tab shows the BOM,Routing,Production version etc. But when I run the MRP the components planned orders/purchase requisitions are not created.  There is no stocks available for the components in the plant, still the purchase requisition are not created by MRP.
    I have tried in both transactions MD01 and MD02.
    I could notice one thing. Supoose if I enter 31.12.2009 is the order finish date, the system creates exception mesage 10- Rescheduling in with proposed date 01.12.2009.  Why the system is propsoing rescheduling in with date 01.12.2009 which past date.
    Please sugest.
    thanks and regards
    Murugesan

    Hi,
    I am using MRP type PD  for assy and components. There is no planned orders for assy.
    If I run MD02 the planned orders created for assy and purchase requisition are created for raw materials. But if I run MRP in MD01 neither  the planned orders nor the purchase requisitions created.
    I tried the Control keys NETCH,NEUPL but still the planned order and purchase requisitions are not created if I run using MD01.
    Please suggest.
    thanks and regards
    Murugesan

  • Purchase Requisitions created instead of Schedule lines

    Hi Experts,
    When I run MRP for materials with mrp type as PD, MRP creates Purchase Requisitions instead of Schedule lines
    I have Scheduling agreement in place.
    Kindly let me know what could be the possible reasons for this
    Thanks & regards,
    Shashidhar

    Hi
    While running the MRP, Check the input parametrs.
    Check the MRP control Parametrs
    Delivery schedules - ensure that Schedule lines has been created.
    Check it out.
    Raman

  • Mass Deletion of Purchase Requisitions

    Hello Gurus,
    I have a unique issue. Our SAP system creates multiple MRP generated purchase requisitions on a daily basis and we do not have the manpower to delete each single PR using the ME52N transaction. I checked the MEMASSRQ transaction which is used for mass changes of PRs. However, in MEMASSRQ, there isn't any field mentioned particularly for deletion or blocking of purchase requisition. I found a BAPI, BAPI_REQUISITION_DELETE, but even this BAPI is used to delete the PRs one by one. Not for mass deletion.
    Right now, there are around 4000 PRs in our system which are lying and we have to delete them all. So, I want your help in finding out whether there is a transaction/report available for mass deletion of purchase requisitions.
    Your suggestions would be very much helpful for us.
    Thanks and Regards,
    Umakanth

    Hi,
    Perhaps you can try to archive them. Check archiving object MM_EBAN. See not Note 123900 - Archiving purchasing documents/purchase requisitns for futher information.
    I hope this helps you
    Regards
    Eduardo

  • Purchase Requisition - Stock Tranport Order - Valuation Price

    Hello,
    The creation of the Purchase Requisition regarding the STO is carried out either by the Material Requirement Planning (MRP) or manually.
    When it occurs manually, the purchase requisition have the following parameters in the tab Source of Supply:
    - Agreement = 46xxxA
    - Purchase Organisation = 1000
    - Fixed Vendor = 9000
    - Supplying plant = 5000
    When it occurs with the help of the MRP, the purchase requisition have the following parameters in the tab Source of Supply:
    - Agreement = 46xxxA
    - Purchase Organisation = 1000
    - Supplying plant = 5000
    The Material is managed with a different standard price on the receiving plant and the supllying plant:
    -Supplying plant: 0,14
    -Receiving plant: 0,34
    When the PR is created manually, it seems that the system picked up the standard price of the supplying plant which is equal to 0,14 whereas during the MRP process, the PR seems to pick up the standard price of the receiving plant.
    Could you confirm my point of view?
    Thank you in advance for your help
    Regards
    Pierre

    Hi,
    What is your process of STO. Is it Intra company or Inter company.
    For your knowledge in intracompany process the valuation occurs as per the price of issuing plant and in Inter company process the valuation happens in the supplying plant as per the price maintained in material supplying  plant and in receiving plant it happens as per the price maintained in Receiving plant.
    Thanks,
    Atal