Hi MM Experts,
we want to upload consumption per storage location. Are there any tables where you can find the consumption per storage location?  (in the table mver Consumers are  per plant).
thanx in advance.
SDA

Hi,
No, there is not any related table which keeps track of consumption per storage location.
Cheers,
HT

Similar Messages

  • Help required -for MRP Run at storage location level

    Hi ,
    we need to have separate MRP fro two storage locations with direct procurement from Storage locations. Right now we have MRP run at Plant level for all the storage locations. we donot want the materials in these two storage locations to be planned at Plant level only with Separate storage locations. Plant level MRP will run for the other storage locations .
    I have created separate MRP areas for the storage locations & activated MRP for MRP Areas client level. material masters for the two storage locations have been asigned the MRP areas & maintained the MRP area data in material master .
    When we run the MD01, the Planned orders are getting created at both MRP areas plus at the Plant level.we donot want the planned orders creation at Plant MRP area level-only at the storage location level for those two storage locations MRP areas.
    Can anybody guide me -how to achieve that ? Did we miss any configuration?
      I tried to maintain scope of planning & getting error for parallel processing .
    Do i need to maintain parallel procesing with servers ?
      Pls need your input on this. Any help will be highly appreciated .
       Thank you in advance.
        Regards,
        Krish.

    Hi,
         Go to IMG settings 'Materials Management + Consumption-Based Planning + Planning + Define Storage Location MRP per Plant' Enter your Plant, It will show list of storage location in that Plant, then select 2 in 'MRP Indicator' field for storage location for which u want to plan seperately.
    Hope It will clear Your Problem
    Regards
    Sunil Kumar

  • RLM MRP execution at storage location

    Hello Friends,
    Need help - I am configuring RLM with MRP - need help with below:
    Requirement: I need to run MRP at the main storage location first (requirement is from Plant Maint order), followed by another MRP run at secondary storage locations. I want to deplete stock in the main storage location before using up stock at secondary storage locations.
    This is not for re-order point planning (VB) for both storage locations, I know that I can plan MRP separately at storage location levels, but that only works with re-order point replenishment.
    Is MRP area configuration my only option?
    If possible I want to avoid MRP area configuration - I hear once it is configured we can revert back!

    Hi Joe,
    As per your client requirement, you need to run MRP at Main storage location, and want to avoid performing at storage location, here you can define the supply chain derivation via plant Mainteniance order by using using item category and transport requistion in RLM Configuration. you have option to select the order type order type item category  ( ), item category change rule ...( newer change item category) & direct prourement type ( SAP Std ).
    Yes MRP Area is the only option, the MRP first as plant level is the option, check in setting ie Step-3 Supply process derivation via plant ( supply type PD).
    The parameters for the RLM Supply Process are a combination of the following:
    · Material requirements planning (MRP) type at the requesting plant or storage location (the plant making the request for materials)
    · MRP type at the supplying plant or storage location (the plant or storage location supplying the material)
    · Special procurement type at the demanding plant or storage location.
    For more information pls check this link..
    http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
    http://help.sap.com/saphelp_oil472/helpdata/en/83/496c3a411aab70e10000000a114084/frameset.htm
    BR
    Satish

  • MRP Relevance for Storage Location

    All SAP Gurus,
    In SPRO where we need to maintain MRP Relevance for Storage Location?
    Regards,

    Dear,
    Check transaction OMIR - Storage location - MRP relevance.
    In detail:
    To control whether a particular storage location will be included or excluded from the MRP run.  (MD02/MD41).
    To exclude it from MRP run follow the steps:-
    OMIR - Define storage location MRP per plant
    Put the MRP ind. as.         1 - storage location stock excluded for MRP
    To include it from MRP run:-
    OMIR - Define storage location MRP per plant
    Put the MRP ind. as.      space - storage location stock also planned at plant level and save it
    Next go to transaction MM01 - tick only view MRP 2
    Key in Plant and Storage Location
    Look at the Storage Location MRP section
    change the SLoc MRP indicator to space  and save it
    MMD1 - Create MRP Profile - MRP profile is a useful entry aid and makes it easier to manage MRP data.
    You define which fields are filled with values when MRP data is entered in the material master record, which of these values can be overwritten and which not.   You use the information stored in a profile is standard information that is needed again and again in similar constellations when material master records are maintained.
    Regards,
    Syed Hussain.
    Edited by: Syed Hussain on Sep 20, 2008 12:51 PM

  • Forecast per storage location

    Experts,
    is there a way to set forecast per storage location, e.g. for material  10000 i like to forecast 100 pieces per month in Sloc A and 100 pieces per month in Sloc B.
    We have no MRP areas in place.
    Thanks in advance
    Jörg

    In my opinion MRP area is the only option for you.

  • How to run MRP on different storage location level ?

    Dear Experts,
    Need your valuable guidance to solve the below requirement form the client-
    1) My client want to enter a "safety stock level" for one spare part/ Material on the basis of individual storage locations.
               For sake of example: in SL01 he wants the safety stock for particular material set to 5
                                  In FS18 he wants the safety stock set to 2
                                  In FS15 he wants the safety stock set to 1
    Kindly tell me whether it is possible? & guide me how to do it.
    2) Also tell me how to run MRP on a storage location level?
               This is because after maintaining different safety stocks for one material in different storage locations,  is it possible to appear each storage location with their differing safety stock levels?
    I checked the MRP type maintained & its-1 (plant) & not as- 2 (storage location).
    Kindly guide me for the above issue
    Thanks in advance for your support.
    Regards,
    Mehul

    Hi Umashanker,
    Thanks for your suggession . Accordingly I have resolved the issue.
    Regards,
    Mehul

  • Change MRP type at storage location level

    Morning,
    i am having trouble with PD and ND reporting. Your you are aware ND should only have balances of 0 and PD should only have balances of >0. When i run a reportto show all PD stock and exclude the positive balances, i am getting MM numbers appearing that are 0 in 1 sLoc but have a positive stock balance in another sLoc. This becomes a problem when i change the PD to ND because it changes at plant level. i only want this to be changed at the sLoc with the 0 stock balance.
    I have tried MM06 to flag the MM for deletion at sLoc level however, when running the report again, the sLoc with 0 stock balance still shows.
    Also, i have about 800+ that need changing so a solution to do this in a batch would also be appreciated.
    Please help.
    Paul

    Hi,
         Go to IMG settings 'Materials Management + Consumption-Based Planning + Planning + Define Storage Location MRP per Plant' Enter your Plant, It will show list of storage location in that Plant, then select 2 in 'MRP Indicator' field for storage location for which u want to plan seperately.
    Hope It will clear Your Problem
    Regards
    Sunil Kumar

  • Can PIR created at wbs element and MRP area of storage location level

    Hi,
    I tried to create an planned independent requirement at MRP area and WBS element level, but failed. The MRP area is not plant level, but storage location level.
    *When trying to create account assignment category Q for it, then there is an error message saying:*
    **only stock requirements are allowed when planning at MRP area level.**
    Does it mean it is not possible to create planned independent requirement for this case?
    Thanks!

    Select the "Issue storage location" as '2' here:
    spro -> production -> material requirement planning -> mrp groups -> overall maintenance of mrp groups -> overview -> mrp control parameters at material level -> (field) Issue storage location selection
    & make sure:
    1. In the BOM  issue storage location is blank for the components
    2. For the FG products , in mrp area prod.storage loc is maintained
    3. Components are extended to the mrp area.
    Pl. revert with the results

  • LTP excludes materials with MRP indicator of storage location

    Hi All,
    SAP Note 208017 explains the reason for LTP not taking into account the MRP
    indicator of a storage location for a material. Has anyone tried a work around for this issue?
    <b>We basically are looking for a snapshot of operative MRP a week back from current date</b> and I thought LTP can be used, but it plans at the plant stock level. Since we have service inventory managed at storage location level and its exculded in operative MRP, we cant have consistent results with LTP being used for my purpose.
    Any inputs appreciated
    Thanks

    Hi,
    1. I dont think we should use the LTP Forthe purpose of your requriement
    2. Since i think you will be runing the MRP at certain frequency say daily,weekly etc
    3. LTP is a strong functionality for the forward planning , which means for a medium or long term in the forward direction
    4. For the purpose of snap shot we shouldnot use this ...
    may be pp gurus in the forum will be giving  us some reply which you are looking for
    reg
    dskumar

  • MRP Areas on storage location Basis

    Hi,
    I created some MRP areas for different storage locations, and assigned those MRP Areas to material(MRP 1 View). Every thing looks fine as of now.
    1)Now when I have seen some forums, I seen Convert planning file entries (SE38 program RMDBVM00), I never done conversion of planning files, can any one tell me what is the importance of it? I didn't done conversion of planning files, will that have any impact on MRP Run.
    Thanks
    Aplha

    Alpha,
    Can I convert planning files now, In D,Q and P, will that effect MRP Run?
    As expert Caetano has said repeatedly, of course it will affect the MRP run.
    The whole purpose of having Development, Quality, and Production systems is to ensure that any changes made in software do not disrupt your business.  In any sane environment, you first perform your changes (such as converting your planning file entries) in dev, and perform unit testing.  Once you have convinced yourself that the change is worthy of testing, you then move the changes to Qual, where typically your company performs Integration and User Acceptance testing.  Only after the business community and the IT community have tested and are satisfied with the results, should you then perform the changed process in Production.
    In short, you shouldn't be asking us in SCN when it is OK to perform the activity in the Productive system, you should be following your company's 'change management' processes, which usually involve, at a minimum, asking your company's user community if the change is acceptable to them.
    Best Regards,
    DB49

  • MRP run at storage location

    Dear All
    We have around 10 storage location and out of the 5 storage location i dont want to include in the MRP run.
    What should I do ?  can you please guide me.
    Regards,
    AMOL WAGH

    Dear ,
    In my understanding it's only possible to make stock in transfer,blocked stock and restricted use stock as available/not available
    for planning.So in my understanding it's not possible to exclude a particular storage location's quality stock to be excluded from
    MRP.
    kindly check this thread which gives a clear explanation regarding your requirement.
    Exclude QI stocks from MRP
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • MRP to ecxlude storage location stock and read only requirement

    Hi All,
    Below is the requirement for raw material,
    Have two storage locations A and B.
    For storage location A, MRP should exclude stock but has to consider demand's at A (dependent requirements, order reservations) and create MRP elements (purchase requisitions, scheduling agreements etc.).
    SLOC B has to consider as normal for MRP (should read demand and stock as well).
    Please suggest if it is doable, if yes; how to set the storage location A, so that it just read the demands but exclude stock.
    Setting up only "SLOC Indicator" 1 in MRP 4 view is not the option I believe.
    Thank you.

    Can someone please suggest on below requirement,
    How to make the settings at material level so that for a storage location 'A', MRP will just read/consider the demand but exclude the stock.
    Is it feasible?
    Regards,
    Deepak Girme

  • MRP for plant/storage location

    Dear all,
    I have a question regarding MRP extension for plants and materials.
    There is one plant (8000). Company has recently got two locations u201Cxu201D and u201Cyu201D in different states. MRP has to be run for u201Dxu201D  for sales orders and PRu2019s generated should be directed to the main plant 8000 which then triggers a TO for u201Cxu201D.
    My question is since u201Cxu201D and u201Cyu201D are not yet maintained in SAP, Please advise whether to maintain them as plants or as storage locations and also the main steps to be followed for this process. Also, Please advise is there any config to be done so that PRu2019s are directed to plant 8000 and automatic TO/STO are triggered to u201Cxu201D
    Suraj

    Hi
    you have to create  both X&Y as plants.
    Then the procedure to be followed in multi plant planning.
    The following link can be followed.
    http://help.sap.com/saphelp_erp60/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
    Regards
    YMREDDY

  • Fixed "Default" Storage Bin per Storage Location

    Hi all,
    I have a Storage Location (1234) with only one Storage type (FIX) and one Storage Bin (FLOOR).
    What I want is all materials should go (when receiving) to this Storage Bin.
    I have configured the Putaway strategy for the Storage Type "F - Fixed bins"
    But it's not working. The system is always considers the Next empty bin strategy.
    I don't want to make the storage bin fixed per Movement type or per material...The same material can be maintained in different storage locations.
    Thank you
    Best regards,
    Kifah Yacoub

    Hi,
    a storage location never has a storage type.
    If you have a storage type and this has one one bin, why don't you use the strategy "Open storage". Then only that one bin is used. of course you need to allow "addition to stock" and "mixed storage" with all consequences.
    If you used "fixed bins", you also have to assign the bin to all the materials.
    Brgds
    Juergen

  • Storage location reference per Storage location

    Hello Experts,
    We have a storage location X000 and it has assign storage loc ref 00( GR to VZ1 ) therefore during the GR the storage loc S000 go through VZ1, before Schedule agreement is created with x000.
    I require that in the same process the system go through EWJ and ETP for some materials and not go to VZ1. But the issue is that I cannot create several Storage location reference (00, 05,03) for the same storage location (X000)
    I do not want create a storage location for each storage type.
    My currently configuration is:
    Storage location: x000
    Storage location ref: 00 ( GR to VZ1)
    Storage type: VZ1
    Strategy source: VZ1 with ref 00
    Material: WH 1 view VZ1
    I require similar configuration for my news storage types EWJ, ETP but I require use the same storage location X000 it is possible? Or could you please recommend a idea..
    reagards,

    Hi,
    If I understand correctly....you want three different material should putaway into three different storage type using same storage location reference...
    It is possible. No need to create another storage location reference for the St.Locn: X000.
    Assuming material A & B should go to storage type EWJ & ETP respectively.
    1) Maintain storage type indicator for putaway in WM view1: Mat. A=EWJ, B=ETP
    2) Maintain st. typ search strategy  W/H no.,E,EWJ, st loc. Ref.=00,.st.typ=EWJ .Similarly for st.typ indicator ETP, 00,ETP.
    When there will be stock putaway for Material A,B & C system will find the st.typ indicator for putaway from WM view and get storage location reference 00 (set for st locn:X000) and will search the appropriate storage type in storage type search strategy and putaway material into st. typ EWJ, ETP and VZ1.