MRP creating multiple delivery schedule lines in PR

Hi,
We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
Material Requirement for a month is say 1,25,000 units
Closing Stock say 25,000 units
PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
How can it be achieved ?
Regards,
Nirav Kinkhabwala

Dear
Are you dealing with Single vendor  where you want Multiple Schedule Line item through single PR  which should be generated through MRP run ??
What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.
Or you can use Qouta arrabgement in that case for different vendor .Please refer : Multiple Requisition  line itme for Quota arrangement
Just check and revert
regards
JH
Edited by: Jiaul Haque on Dec 25, 2010 1:52 PM

Similar Messages

  • Why GR performed on MRP generated delivery schedule line (unconfirmed)?

    Hi Gurus,
    Need some advice from you all, I have a scenario here which MRP generated the delivery schedule lines for material A on 10.08.2011 - 124 KG.
    User review the MRP result and didnt confirm the line, but she added in manual line on 11.08.2011 - 124KG.
    On 11.08.2011, warehouse performed GR on the delivery schedule lines. It's found that GR was actually updated into the delivery schedule line generated by MRP (10.08.2011) and not the manual line confirmed by user. (11.08.2011).
    User is questioning now why the GR able to be performed on MRP generated line which had not been confirmed? Any guru can share with me the fact and good note regarding this on MRP? Thanks!
    Michelle

    Hi,
    Since we are talking here about schedule lines, these are open for GR when the delivery schedule is send to the vendor.
    In your case you had a quantity open for 10/08/2011 generated by MRP, then the user added manually another line on 11/08/2011. After this the user will have transmitted the delivery schedule which makes that both the items where marked as transmitted and thus open for GR.
    Now when the goods come in the system will post against the first open schedule line that is found until this is fulfilled and then switch to the next open line at the moment of GR. So this is why the GR was put against the MRP generated schedule line as this one was the one with the earlier date.
    Regards,
    Peter

  • Scheduling agreement, unnecessary delivery schedule lines

    Hello
    We use Scheduling agreements for purchasing spare parts. The MRP run checks the warehouse requirements and creates delivery schedule line to scheduling agreement.
    Now the MRP run creates unnecessary delivery schedule lines to scheduling agreement if the earlier created delivery schedule line's delivery date has been changed manually.
    For example,
    Today the MRP run finds requirement for one article  and creates the delivery schedule line, where delivery date is 2.9.2008 (determined from articles basic data).
    The Vendor confirms the delivery date as 3.10.2008 and the purchaser changes manually  (transaction ME38) the delivery date to delivery schedule line accordingly and prints the created message.
    The next MRP run creates new delivery schedule line, where delivery date is again 2.9.2008.
    now there are two open delivery schedule lines for this article with delivery dates 3.10.2008 and 2.9.2008.
    Why the MRP run does not notice the existing delivery schedule line with the new delivery date 3.10.2008?
    we have changed delivery dates manually several years and this has never happened before.
    could you please help me to resolve this.
    Thanks in advance,
    Srikanth

    In addition to the above post,
    as you changed the date manually from 2nd to 3rd....
    so there are was no report for 2nd generated ulitmately...and if generated it was changed...right...
    so when you again run the mrp...the system will generate one more pr for the same article....
    this ultimately happens because of the set del dates in the MMR as i told above..
    Hope it helps..
    Regards
    Priyanka.P

  • The delivery schedule lines don't get created automatically on MRP run.

    Hi All,
    The delivery schedule lines don't get created automatically on MRP run for subcontracting material.  I have maintained source list as follow eg.
    Valid from | Valid to | Vendor | Porg | PPI | Agreement | Item | Fix | MRP | MRP area
    02.11.2009 | 31.12.2999| XYZ | XY01|     |AA0000XYZE |10 | X |2 | ABC
    Could you please help me about this issue
    Thanks in advance.

    Hi Amit,
    Please ensure the value of Special procurement key in the MRP2 view for the material. It should be maintained as 30 - subcontracting.
    Thanks and Regards,

  • Order of delivery schedule line counter at schedule agreements from MRP run

    Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
    Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
    Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
    Thank you
    Daniel Guillen
    IT
    Skyworks Inc.

    Hi,
    Pls put this query in SD fourms  and get immly help because this is technical fourms.
    Anil

  • Forecast delivery schedule lines consumption

    Hi,
    I cannot fully understand what is the logic behind the consumption of the forecast delivery schedule lines. This is how the problem can be exactly defined:
    - scheduling agreement with delivery orders (LZM)
    - JIT delivery schedules are not used and no delivery schedule is maintained... just a forecast delivery schedule
    - the whole process is manual, there is no EDI implied
    - the cumulative received quantity is updated by an ABAP development that is triggered at delivery goods issue
    The rest, happens normal - forecast schedule lines are updated weekly, the customer send pick-up sheets, a TAM delivery order is created, then delivery, GI...
    The problem: not always the MRP requirements generated by the forecast delivery schedule lines are consumed by the delivery order/GI. If the delivery orders / deliveries are made on the exact quantity of the schedule lines everything works fine. It is also ok when there are two successive delivery orders with a cumulative quantity that matches exactly the forecast line. As soon as a over-delivery is made, everything turns upside-down: older delivered schedule lines appear again in planning as if nothing was delivered until now...
    I suspect that the problem is related to the fact that the whole process is manual and updating the cumulative received quantity is not the only parameter that is counting... is it so? Or the forecast delivery schedule has to be respected 100% in terms of quantities and timing?
    I would really appreciate your help.
    Regards,
    H.

    Also please clarify whether delivery schedule lines in ME38 (even it is created automatically), in Planning time fence, will get affected by MRP run.

  • Delivery schedule lines

    Hi Experts,
    Please clarify whether delivery schedule lines if creatd manaully in ME38 will get affected/changed by MRP run.
    Edited by: Shravan A on Apr 15, 2008 7:04 PM

    Also please clarify whether delivery schedule lines in ME38 (even it is created automatically), in Planning time fence, will get affected by MRP run.

  • Multiple MM schedule lines for the same date

    Hello All Gurus,
    I am facing a problem where the MM schedule lines are divided into various quantites for the same date. For example on 02/11/2010 the total quantity is 120, it is appearing in the below form in ME38:
    02/11/2010 - 40
    02/11/2010 - 40
    02/11/2010 - 40
    Although this is not an error, but my client is not happy with this. Can someone tell me why I am getting this error? Is it because of the rounding value that we maintain in MRP 1 view of material master record? Or is there any other setting that I am missing?
    Please let me  know. I would be very much thankful to you.
    Thanks and Regards,
    Umakanth

    Hi,
    Before changing the setup, note that sometimes it is beneficial to split one demand into multiple delivery schedules. Especially if the demand is bigger than equipment type (container/truck etc.). If you want to manage inbound transportation for such delivery schedules, it is much simpler to do this when each delivery schedule is not bigger than one equipment.
    Regards,
    Dominik Modrzejewski

  • Purchase Requisitions created instead of Schedule lines

    Hi Experts,
    When I run MRP for materials with mrp type as PD, MRP creates Purchase Requisitions instead of Schedule lines
    I have Scheduling agreement in place.
    Kindly let me know what could be the possible reasons for this
    Thanks & regards,
    Shashidhar

    Hi
    While running the MRP, Check the input parametrs.
    Check the MRP control Parametrs
    Delivery schedules - ensure that Schedule lines has been created.
    Check it out.
    Raman

  • Scheduling Agreement - Delivery schedule line number

    Hi,
       I am developing a report to show the Goods receipt postings for each delivery schedules of Schedule agreements.
    I am not able to find Delivery Schedules line(EKET-ETENR) in Material document table(MSEG).
    How do we exactly link the GR quantity to Scheduling agreement Delivery schedules.
    We have line item number but not delivery schedules.
    GR quantity may be posted to different delivery scheules and for some SAs when the MRP Runs it is positng randomly.
    Is there function to find the link,
    Searched EKBE, EKET, MSEG  and other tables also.
    Appreciate your help <offer removed by moderator>.
    Satya
    Edited by: Thomas Zloch on Jan 18, 2011 2:44 PM

    Hi Shravan,
        Thanks for answering, I checked those two tables EKEH, EKEK are release tables. We have some SAs without release documentation. I have to find the delivery schedules using the GR document to which delivery schedules the qty it is delivering.
    It is not posting the qty from top of schedules, for some SAs it posted randomly.
    Any other ideas or any function modules,
    In BW it is possible using extractor but we need in R/3
    Thanks,
    Satya

  • SCHEDULE AGREEMENT-DELIVERY SCHEDULE LINE ITEM PRINTING

    Scheduling agreement is created in ECC.
    Delivery schedule line items are generated using APO and CIFed over to ECC.
    Upon displaying in ME38 in ECC, the delivery schedule line items are appearing as required. The problem is that no output type is displayed for condition type LPET even though the settings are done & condition records are maintained.
    Can someone throw some light on this?

    Hi Anil ,
    Goto Transaction NACE , Select Application EL and then Click on O/p Types.
    Select your o/p and click on Processing routines.
    Make a copy of medium 1 and change it to 5. The program , Form , Form routine would remain the same.
    Maintain condition records with medium 5 in MN10.
    Ensure that email address exists in Vendor Master.
    Check with ur Basis to make sure that the setting are done in Transaction SCOT for sending document via PDF.
    Create a new Agreement and test it.
    Regards
    Ramesh Ch

  • Delivery schedule line number in make to order

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated and delivery date is not picking correctly in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    regards
    piyush

    Hi
    When you do the MRP Run at MD02, maintain the Delivery Schedules as 3 (schedule lines), so when ever you do the MRP Run, it will run along with the delievry date.
    reward if it helps
    Regards
    Prasanna R

  • Delivery schedule line number in sales order is not populated in production

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Will reward points.
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil

  • Delivery schedule line number in sales order is not populated  in productio

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil

  • Delivery Schedule line no in Make to Order

    Hi all,
            i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated and delivery date is not picking correctly in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    regards
    piyush

    hi
          thanks,
    i have checked MD04 peg requirement list with order route.
    every thing is ok.,schedule number is also coming but only for finished good . if three production order is there for semifinished then there is no any relation that how i can judge that this semifinished is for which FG material.means :
    FG 1             FG 2            FG 3
    SF 1              SF 2            SF 3
    SF 11            SF 22           SF 33
    How this SF 11 is linked with FG1.and schedule delivery number is there but only for FG material. planning segment is same for all the FG material.MRP element data having all the link but only for FG material.
    what is the link of SF 11 to schedule delivery line number with FG material.
    Regards

Maybe you are looking for