MRP Creation

Forum,
If I have the following scenario:
1. Purchase Order on system for 10 widgets with a delivery date of 1st October
2. New Sales Order for 5 widgets entered with a Delivery date of 20th September
3. On running MRP wizard, it suggests we need to order 5 widgets to satisfy Sales Order as 10 on order will not be delivered on time.
Is it possible for MRP not to suggest the creation of the PO for 5 widgets?
Regards,
Juan

Hi,
Try to use the planning horizon in MRP to avoid the suggestion
JimM

Similar Messages

  • MRP Creation Indicator

    Hi Experts,
    Just want to seek help regarding the MRP Creation Indicator. What would be the effect if the Opening Period set is "0" or zero for the MRP item in SMK of Material Master but when we run MRP in the Selection Parameters we uses the parameter "2"- Purchase requisitions in Opening Period in the Create Purchase Requisition field.
    We have MRP items wherein MRP still generates Planned Orders (STPO) even if the Opening Period is Zero or "0". The MRP Planned Orders contains Planned Opening Date which is the same date when MRP run and yet MRP did not created PR for the item. Hope you can help enlighten us.
    Thanks,
    SD

    Hello ,
      The Opening period define at SMK is used to  calculate the "Opening date" of either planned order or Pur req. Opening date is calculated as below.
    Open date = Opening period - Order start date of Planned order  or Release date of Pur req.
    According to cont ind 2 ,  If Opening date  falls  before the "MRP Run date" system will create  Pur req directly.In your  case the Opening date and MRP date are same it will create Planned order Only. You have to  convert ot manually.
    Opening period  is nothing but a buffer period for MRP controller  t o convert the Planned order to  Pur req
    To check the same, increase your Opening Period at SMK and check with MRP
    Regards
    Pradeep
    Edited by: Pradeep Kumar on Jun 16, 2009 1:33 PM

  • PR and PO through MRP run

    hi,
    What are all settings to generate Purchase Requisitions through MRP run? Also, if, i wanna automate creation of Purchase order from Purchase Requisition (not manually). how to achieve this?
    thanks..

    Hi,
    1. Get PR trough MRP run
    1a, You have to have proper master data settings (e.g. material master: MRP type "PD", procurement type "F")
    1b, Proper MRP creation indicator shoudl be used in MD01 / MD02 / MD03.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
    1c, Your planning situation also influences whether you get PR or not. If there's no need to procure anything (e.g. you have sufficient stock level or you have no demand for the goods > MRP won't generate procurement proposal)
    2. Convert PR to PO
    It depends on your master data settings (material master, source list, QA, outline agreeemts, etc)
    If you have proper master data settings and during MRP run it is possible to determine the source of supply, you can use ME59 to get the POs from the PReqs (otherwise you have to use ME57, ME58 too).
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/4c/420d29470a11d1894a0000e8323352/frameset.htm
    But you can't get PO as the result of MRP run in standard system - you get PR (or PldOrd) and you have to convert the PR to PO (or PldOrd > PR > PO).
    Regards,
    Csaba

  • Automatic PR creation

    dear sap guru,
    How to create automatic PR with MRP?
    Regards,
    babu

    Hi,
    To get PR trough MRP run
    1. You have to have proper master data settings (e.g. material master: MRP type "PD", procurement type "F") and Maintain a soursce list if req.
    2. Proper MRP creation indicator shoudl be used in MD01 / MD02 / MD03 to create PR
    3. Your planning situation also influences whether you get PR or not. If there's no need to procure anything (e.g. you have sufficient stock level or you have no demand for the goods > MRP won't generate procurement proposal)
    Please refer below link for clarity of MRP. I hope this will resolve your issue. Thanking you.
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/30f4d6c1-0808-2d10-2ea5-f9b2863cfed8?quicklink=index&overridelayout=true

  • MRP document type

    Dear Expert
    I am creating PR from MRP run but the system is creating PR of different document type how can i tag the document type using mrp run
    Regards

    Hi
    Try using Different MRP groups. MRP groups are defined for a plant. See config
    Production ---> Material requirement planning ---> MRP groups -
    > carry out overall maintenance of MRP groups
    Here under external procurement type, you can assign ur required document type of Standard PR, subcontracting PR and stock transfer PR from MRP.
    Please not number ranges are not taken from Document type for MRP, it is maintained in plant settings.
    See the config path
    Production ---> Material requirement planning ---> Plant parameters
    Enter your plant,see the number range button... click on it. Click on Purchase requisition and enter number range object.
    Practically you can maintain two different number range for one document type. One for manual creation and another for MRP creation.
    Hope you understood.
    Regards
    Antony

  • Process instruction

    Hi
    Can any one give dtails of Configuration and Tcodes for PP-Pi
    regards

    Hi,
    Pls. find PP-PI Tcode list as below :
    PP-PI TCODES:
    CRC1 - Create Resource
    CR24 - Create Resource Network
    CR31 - Create Hierarchy
    C201 - Create Master Recipe
    C251 - Print Master Recipe
    C223 - Maintain Production Versions
    COIO - Order Info System for PP-PI
    COPD - Print Process Order
    COPI - Print Process Order ShopFloor Papers
    COR1 - Create Process Order
    COR5 - Collective Process Order Release
    COR6 - Single Process Order Confirmation
    COR6N - Single Screen Entry of Confirmations
    COR7 - Convert Planned Order to Proc. Order
    COR7_PC - Part.Conv.: Plnned Ord. to Proc.Ord.
    COR8 - Coll.Conv.: Plnned Ord. to Proc.Ord.
    CORK - Process Order Confirmations (Total)
    CORM - Mass Processing
    CORO - Create Process Order w/o Material
    CORR - Collective Entry of Confirmations
    CORS - Cancel Process Order Confirmation
    CORT - Display Process Order Confirmation
    CORZ - Process Order: Time Event Confirmat.
    COA6 - Process Order: Archiving
    COA7 - Process Order: Retrieval - Archive
    COA8 - Process Order: Archive Management
    CO56 - Display PI Sheet
    CO58 - Maintain PI Sheet
    CO59 - Delete PI Sheet
    CO60 - Find PI Sheet
    COPOC - Process Manufacturing Cockpit
    CO53 - Control Recipe Monitor
    O10C - Assig. Ctrl Rec. Dest./Proc. Instr.
    O12C - Assign Charact. / Proc. Instr. Cat.
    List of PP-PI Transport Request and their IMG Path :
    1) Define Distribution Keys
    IMG > Production Planning for Process Industries > Master Data > Material List > Item Data > Item Data from related areas > Define Distribution Keys
    2) Determine Person responsible for Resource u2013
    IMG > Production Planning for Process Industries > Master Data > Resource > General Data > Determine Person responsible
    3Define Planner Group-
    IMG > Production Planning for Process Industries > Master Data > Master Recipe > Define Capacity Planner
    4) Define Capacity Planner u2013
    IMG > Production Planning for Process Industries > Master Data > Resource > Capacity Requirement Planning > Determine Capacity Planner
    5) Determine Standard Value Parameter u2013
    IMG > Production Planning for Process Industries > Master Data > Resource > General Data > Standard Value > Define Parameter
    6) Define Setup Groups and Setup Group Categories
    Define set up groups and set up categories u2013
    IMG > Production Planning for Process Industries > Master Data > Master Recipe > Data for operations and phases > Define set up groups and set up group categories
    7) Define copy setting between plants-Process
    IMG > Production Planning for Process Industries > Process Management > Tools >  Define copy setting between plants
    8) Define Set Up Control Recipe destination u2013
    IMG > Production Planning for Process Industries > Process Management > Control Recipe/PI sheet > Set up control recipe destination
    9Define MRP controller u2013
    IMG > Material Management > Consumption based Planning > Master Data > Define MRP controller
    10) Special Procurement u2013
    IMG > Material Management > Consumption based Planning > Master Data > Define Special procurement types
    11) Define Floats (Scheduled Margin Key)-
    IMG > Material Management > Consumption based Planning > Planning > Define Floats (Scheduled Margin Key)
    12Define Splitting of Forecast requirements for MRP-
    IMG > Material Management > Consumption based Planning > Evaluation > Forecast > Define Splittng of forecast requirements of MRP
    13) Maintain Correction Factors for Forecast
    IMG > Material Management > Consumption based Planning > Planning > Procurement > Maintain Correction factors for forecast
    14 Carry Out Overall Maintenance of Plant Parameters
    Maintaining plant parameters in MRP u2013
    IMG > Material Management > Consumption based Planning > Plant Parameters > Carry out overall maintenance of plant parameters
    15) Define Planning Horizon
    Define Planning Horizon u2013
    IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Define Planning Horizon
    16) Activate Requirement Planning u2013
    IMG > Material Management > Consumption based Planning > Planning > Activate Requirement Planning
    17) Define Range of Coverage Profiles (Dynamic Safety Stock)
    Range of coverage profile u2013
    IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Define range of coverage profile (Dynamic Safety Stock)
    18) Define Stock in Transfer and Blocked Stock Availability
    IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Stocks > Define Stock in transfer and blocked stock
    19) Define MRP Areas
    IMG > Material Management > Consumption based Planning > Master Data > MRP areas > Define MRP areas
    20) Carry out maintenance of MRP groups
    IMG > Material Management > Consumption based Planning > MRP groups> Carry out maintenance of MRP groups
    21) Define Scope of total Planning - MRP
    IMG > Material Management > Consumption based Planning > Planning > Define Scope of total Planning
    22 Define Order Types
    Define Order Type-
    IMG > Production Planning for Process Industries > Process Order > Master Data > Order > Define Order Type
    23Define Order Type Dependent parameters u2013
    IMG > Production Planning for Process Industries > Process Order > Master Data > Order > Define Order Type Dependent parameters
    24) Define Production Scheduler u2013
    IMG > Production Planning for Process Industries > Process Order > Master Data > Bill of Material >  Define Production Scheduler
    25 Define Checking Control - Process Order
    Define Availability Check u2013 Define Checking Control u2013
    IMG > Production Planning for Process Industries > Process Order > Operations > Availabilty Check > Define Checking Control
    26) Define Checking Rule for backorder processing u2013
    IMG > Production Planning for Process Industries > Process Order > Operations > Availabilty Check > Define Checking rule for back order processing
    27Define Stock and batch determination for good movement u2013
    IMG > Production Planning for Process Industries > Process Order > Operations > Define Stock and batch determination for good movement
    28) Specify Scheduling Parameters
    Specify Scheduling Parameters u2013
    IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling > Specify Scheduling Parameters
    29) Define Reduction Strategies
    Define Reduction Strategy u2013
    IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling > Resource data > Define Reduction Strategy
    30) Define Confirmation Parameters
    Define Order Confirmation u2013
    IMG > Production Planning for Process Industries > Process Order > Operations >
    Confirmation > Define Confirmation Parameters
    31) Define Valuation of Goods Received
    Define valuation of goods receive u2013
    IMG > Production Planning for Process Industries > Process Order > Integration > Define Valuation of goods received
    32) MRP creation indicator u2013
    IMG > Material Management > Consumption based Planning > Planning > Define creation indicator
    33) Define safety stock u2013
    IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Stocks > Define Safety Stocks
    34) Define alternative determination of Production u2013
    IMG > Production Planning for Process Industries > Process Order > Operations > BOM selection > Define alternate determination of production
    35) Define no. ranges u2013
    IMG > Production Planning for Process Industries > Process Order > Master data > Order > Number Ranges > Define number ranges for orders
    HOpe this helps.
    Reward if useful.
    Regards,
    Tejas
    Edited by: Tejas  Pujara on Jul 24, 2008 9:22 AM

  • Creation of SDEB's for MRP type = VB materials.

    Hi Gurus,
    When we run plant wise MRP, SDEB's are created instead of Purchase requisitions for all Manual re-order point materials. We understand that SDEB's are created when the stock of tha material is above tha Re-order point, and this SDEB's indicate tha MRP controller whether he can create manually Purchase requisitions or not.
    But, we are getting these SDEB's for the materials that have stock below the Re-order point as well. Which is not correct i think.?
    For your information, when we run material wise MRP there are no SDEB's at all.
    Please explain what might be the Root cause and the solution to over come this..
    Thanks for your understanding..
    Naveen.A

    Dear colleague,
    without checking the issue it is difficult to know if there is an error.
    Please check if the following information can explain the behaviour of your system:
    A)When you do MD01 or MDBT the creaton indicators defines in the
    customising are used . whereas when you run MD02 or MD03 the creation
    indicator on the individual screen is used.
    Single-item planning and total planning follow a different logic
    concernng the creation indicators.This is also described in the
    documentation for Master Planning/Materials Planning (Chapter 4, Section
    2) and in the Implementation Guide.
    Single-item planning:
            The entered creation indicators are generally valid.
    Total planning:
           The entered creation indicators are used as default values.
           For materials from an MRP group, the values from the MRP group
           apply (if available).
           The creation indicator for delivery schedules can additionally be
           specified per plant. This is used if nothing was specified via
           the MRP group.
           Thus, the priority is as follows:
          1.  MRP group
          2.  Plant
          3.  Initial screen
    B)In MD02 system can de multilevel (For components of a header Materia)
    or/and Multiplant (Stock Transfre ) planning. In such cases for all the
    materials involved the creation indicator used in the screen is used.
    C)The creation indicator makes sense only for materials having
    procurement type external procurement (F) in material master. For the
    materilas which are produced in house (Procurement type E) system will
    always create planned orders.
        And Materials having procurement type X(Both procurement types ) is
    treated as Inhouse produced material by planning . Thus for such
    materials system will always create a planned order. Now this planned
    order can be converted into a production orer or into a purchase
    order(via purchase Requisition).
        When you run MRP with "Create Purchase Requisition " in the opening
    period , then the syetm uses in the opening period defined via  the
    scheduling margin Key. In material master , MRP 2 View we maintain
    scheduling margin key. And in Transaction OPP1->Planning->Scheduling and
    Capacity Parameters ->Define floats we maintain the opening periods per
    plant. I am attaching details of Opening period :
       opening period: Opening period is the time which the MRP controller
    needs to analyse.Thus he has this buffer with him to rectify any issues
    before converting the planned order into purchase requisition.
    The opening period is only used in backward scheduling.
    Suppose There is a requirement for a material on date =RD1
    Let the Goods receipt processing  time  is= T1
    Let the planned delivery time =L1
    Let the purchasing Processing time = X1
    Let the opening period for this material is P1
    Time line  for external procurement:
            Planned Del   Pur proc         GR Process
              Time            Time          Time
    ___|__________|_________|___________|___
                  L1            X1         T1
       SD                                         RD1
    Now accoring to Basic scheduling:
       Receipt/Requirements Date(RD1)
       Release/Start Date(SD) = RD1-T1-L1-X1
    Now let me explain to you when the planned order an purchase
    Requisitions are created:
    Let us say the date on which you do MRP be MR1
    OD = Opening Date
    From above diagram :
                                     Opening Per
                                     In Sch Mar Key
    __________________|______________|
      XX                          OD                 SD
                                                  Release/Start Date
    If your MRP date(generally Today) is lying between XX and OD (and
    excludind OD)then
    MRP creates planned order and if it lies between (and indclind OD)
    OD and SD then we create purchase req.
    when your MRP date comes between the period OD and SD then you do not
    have time left to analyse and therefore instead of you in such cases
    forgetting and delaying system automatically creates purchase req.
          In general if , if your order start date or release date is after
    the opening period from today then MRP will create planned order.
    Oterwise it creates Purchase req.
    Check also if you have the note 1063969 applied in your system.
    I hope it solves the issue. Otheriwse I think you should open an OSS message with connection to your system,
    best regards,
    maria

  • Automatic creation of Schedule line after MRP RUN

    Hi,
    Till now we are  using only PO for placing orders to vendor, now we want to use the functionality of scheduling agrement,  so that after MRP run,  we can get automatic schedule line creation,  for this ,  what are settings required, how system create the automatic schedule lines based on which criteria, second thing while creating on eschedule agrement i found that the conditon which i can add for a vednor in ME21N  that all condition are not coming while creating schedule agrement  even my vendor is same for PO and Schedule agrement,  so what are  the setting required for this.
      regards,
       zafar

    Hi
    1.In material master purchasing view data auto PO is to be flagged.If scheduling agreemet with release documentation.
    Then flag JIT indicator 1.
    2.maintain MRP views in material master
    3.In source list for fix vendor,source list usage 2 is to be maintained.
    4.Vendor master purchasing data auto PO indicator is to be flagged.
    5.Then when you run MRP automatically schedule lines are generated.
    For JIT and forecasting maintain creaton profile in OMUP transction.
    Assign the creation profile in scheduling agreement.

  • Creation of Purchase Requisition with MRP - MD02

    Hello,
    I have created a sales order using one material with MRP. When I run MRP-transaction MD02 for this material, a purchase requisition is created.
    What we want is to block the creation of the purchase requisition when the sales order has delivery block (code 02). I have been trying to use this enhancements; setting break-points in all function modules, but when running MD02 is does not stop there:
    MEREQ001      Customers' Own Data in Purchase Requisi
    LMDR2001      User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001      User exits in additional planning                         
    M61X0001      User exits PP-MRP materials planning                      
    M61X0002      User Exits PP-MRP Material Requirements Planning Evaluation
    Do you know a way to do this or also change data in the purchase requisition created with MD02?
    Thanks and regards.

    Dear ,
    Are you very particualr to process the Sales Order demand when there is a delivery block ?
    To restrict that  one you can do the following steps :
    1.Goto Sales Order -VA02-Select the line item -Double Click -Select the Schedule line  tab -Set Sechedule line item categoery as CN instead of CP.If it is CP then it will processed through MRP
    2.Change the pricining date and make credit block for sales Order and do not release though VKM3 so it will not be tearted through MRP run  to have PR geneartion
    Hope this is clear
    regards
    JH

  • Automatic creation of PR after MRP run

    Hi,
    can anyone please tell me what all fields are picked up in a Purchase Requisition(PR) in the scenario of automatic creation of PR after MRP run.
    If we are using more than 1 PR type in the system how is it determined during the MRP run that the PR will be created for which type.I understand that source list will have to be created and maintained but how is the PR type determined
    Thanks in advance

    In PR the system checks for the material and vendor. See the steps below.
    Step1:Auto PO tick in material master Purchasing view (mandatory)
    Step2:Auto PO tick in vendor master Purchasing view
    Step3:Maintain Source list for vendor and material (If u r not using source list for auto PO creation, the assign the Source of supply to a PR in ME56)
    Step4:Maintain Pur. Inforecord
    Step5:ME59n : execute for PR and Vendor In ME59n, you can also select the PR document type. If you want to select different document types, go for multiple entries and enter the doc types.
    When u execute, the system will give the appropriate PRs. Select the required and convert to PO.
    But through MRP you cannot create PO directly only Planned orders can be created.
    Reward if helpful..
    Thanks,
    Srib

  • Automatically creation of Purchase Order from MRP

    Material type = ROH (raw material)
    In MRP1 I have mentioned
    1. RP type =VB ( manual reorder point planning)
    2.Reorder point = 1000
    3.Lot size =FX (fixed order quantity)
    4. Fixed lot size = 300
    In purchasing I have checked the automatic P.O. option
    I have created a source list for the material and fixed the vendor for the material
    Quantiy of the material in stock = 0
    But Purchase Order is nor automatically generated during the MRP run ( MD03)
    IS there any step missing ? please suggest if any .
    Thanks in advance .

    Hi,
    As others suggested standrad SAP will not create PO as output of MRP.
    You need to check why you need AUTO FUNCTION.however you can use T code ME59n to create auto PO from Preqs.
    About AUTO PO
    One example is that while  taking delivery of the raw materials which are delivered by trucks and since it is not possible to capture the actual receipted quantity at the time of PO creation.
    To create AUTO PO
    Check in customizing whether you have maintained creation of automatic PO during good receipt.
    Menu path : MM -> Inventory Management -> Goods Receipt -> Create Purchase order Automatically -> Activate Auto PO creation for Mvt type and then activate Auto PO creation in vendor master.
    Hope this helps.
    SCMBEE

  • Creation of purchase order in MRP

    Hi All,
    Is it possible to create purchase order as an output of MRP? If yes, then how?
    regards,
    Mohit

    Hi Mohit,
    SAP has not provided such facility of directly creating the Purchase Order in MRP run, intentionally, so as to
    1. Provide an Authorization Level over the P.O. creation
    2. Provide a chance to change the Planned order or Purchase requizition before PO creation
    3. As this is a procurement proposal that is directly linked with the vendor, quantity and Price, it has to   be created very carefully.
    I hope you got it.
    with regards,
    gnk

  • PR values copy to PO (PR creation manual) PR is MRP then copy from Info

    Hello
    We have Two types of Purchase requisation in Business
    One is created from MRP run..... this PO is having the values in valution tab.
    While creation PO from PR...the values should copy from PR at first time. and system updates
    the Info record here for the material and vendor combination.
    while second time i have created the PR from manualy, and i have changed the PR value
    then system should go for release,
    while creation of PR to PO the system will copy the Price from Info record(last purchase order)
    then what is the need to release the PR.
    Bcz the Last PO price was having the 100Rs
    the new created the PR is having the 200Rs..... it should copy from the PR here in manulay
    created PR
    while in PR values copied to PO once while in fresh PR.(I,e MRP generated PR)..
    after that it should copy from Info record.
    sapmanman

    I don't get your questio clearly.....
    But as per my understaing of your que
    The PR generated from MRP or Manual creation-- when you convert the PR to PO system will pickup the price from inforecord and info record can not be created automaticaly by the system for psicing
    the inforecord will be cretaed first time when you create the PO from PR but it will not have pricing it is just updating the PO number in the info record
    so you have to create the info record.
    now suppose you want to copy the PR price to the PO than there is a funcitonlaity you have to activate
    tcode is OMET
    go here and check the adopt price check box than system will populate the button in the PR on valuation tab where you can select as gross price or net price than system will take this price in the Po.
    in you case if suppose system is copying the last PO price to new Po becuse in your system the setting for defualt value for buyers is active that;s the reason you see that system copy the last po price.
    if you dont want this than go to
    SPRO-MM-Purchasing-environment data-defien defualt value for buyer
    here on Price adoption tab you will see always copy
    now if you dont want than copy the 01 to blank value and remove the always copy
    Now use of PR release is not for the pricing but there is many other reqs for release procedure
    noramly the PO would have release process activated if you have concern for pricing.
    hope this will give you a clear picture

  • Creation of MRP Batch job

    Hello PP Sapperu2019s
    I need to create a MRP batchjob for one of my plant u2013 9030.I need to know the below highlighted details,
    Job name : MRP Plant 9030
    *Programname : *
    *Variant: *
    Frequency : Daily
    Timing : 01.00 (during the night)
    Step user :
    Please help me to proceed with creation of MRP batchjob.
    My requirement is to run MRP every night that reschedule the purchase order and create new purchase requestion in Total Horizon.
    Need any further input please let me know.
    PS:I also refer MDBT for the MRP jobs whihc already created for some other plants but seems to be different from the above requirement.
    Cheers,
    Kumar.S

    For the job which you refer to, go to the spool & study the section 'Runtime statistics'. It will let you know which section took how much time & based on that you would be able to infer what has caused the delay & thereby take suitable actions.
    Also note, there is no generic rules as such, each case has to be analyzed if there is a delay. But in general it is better to ensure your planning file entries are consistent, processing key - NETPL or NETCH & planning mode is 1.
    I guess this thread has gone way beyond the initial posting, so for any further analysis on this MRP job I would strongly suggest that you sit down with the MRP controller & analyze the same. I am quite sure it shouldn't be difficult in interpreting the results.
    Good luck.

  • Planned order creation via MRP depends, If we change Delivery date in STO

    Hi,
    Planned order  creation via MRP depends, If we change Delivery date in Stock transfer Order.
    I created STO with delivery date as 31.1.2012 and when i checked MD04, i can see Planned order created on 27.2.2012 with the same above STO quantity .
    Now when i changed the delivery date as 30.1.2012 and runned MD03, and then checkd MD04, planned order disappeared.
    Why Planned order got created when STO delivery date was 31.1.2012 and when I changed the delivery date in PO, planned order disappeared.
    MRP profile details :
    Plnd delivery time   1
    GR processing time   1
    Planning time fence  38
    Tot. repl. lead time 38
    Can you please let me know why system is beaving in this manner?
    Regards
    Utsav

    Hi,
    Normally , MRP runs based upon the requirements.If your STO is created for a date , system checks through the availabiloty check wheather there exists any stock for that date to get deliverred in the supply plant .If there exists for that date the stock , planned order will not be created.If no stock available then a planned order will be created in MRP.
    cHECK the availability check parameters assigned to material master in supply plant.
    Regards,

Maybe you are looking for

  • I can't get photoshop to finish downloading

    My photoshop downloads to 42% and then stops. I tried uninstalling it and trying again but it jumps right back to the 42% and stays there. How can I get this to complete the download?

  • Pass URL parameter for zip code

    In this fake url I want to pass the zip code value of the confirmed BP into "zipcode" https://acme.com/locator.jsp?zip=zipcode from the other post I have read the parameter name would be "zipcode" and thru the transaction launcher I am able to assign

  • Cs4 does not activate automatic on my new computer

    On my new Apple iMac 27" Retina quad i7, my CS4 suite does not activate. As for as I understand it should activate automatically, but I get a message "De licentieverleningsprocdure voor dit product werkt niet meer" (in english: the license activation

  • Can't copy Dynamic Scenario

    I have one dynamic calc scenario that uses some logic that if a stored date value is less than a certain other value, return the value in another Scenario otherwise nothing. The calc seems to work find when I retrieve in a spreadsheet, but it won't c

  • Black screen on ipad mini

    Please help!! My ipad mini screen is black and cannot charge even resetting the home and reset buttons. I have checked and the charger is in working condition.