MRP data MD04 Data Extractor (not MD05)

Hello,
Is there a SAP-delivered extractor for MD04 data? All the previous threads on this topic equate S194 extractor to MD04. The S194 based extractor delivers MD05 data not MD04.  MD05 will generally equal MD04 if you do a fresh MRP run.

Hi,
2LIS_02_SCL does not deliver MD04 data. 2LIS_03_S194 is the closest with the limitation that it is only as good as the last MRP run.

Similar Messages

  • MD04 MRP Data Element for Production Order add Order Status

    Hi,
    Currently in MD04 when you create a production order it gives the status in MRP Element Data as 000001138145/YP01/ and once I release this is shows the following status 000001138145/YP01/Re
    I want to bring another status in how can you do this?
    Thanks
    Adeel Sarwar

    Dear,
    It is not possible in standard SAP to display the Lock production order as status 'Locked' are taking into consideration with regard to availability relevance in the MRP. MD04 display only those MRP element which are relevent for MRP calculation.
    So better check this order in COOIS with LCK (Locked Status).
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Schedule lines should not change 3 weeks time from MRP date

    Hi
    Is there any specific customisation required to get following results in case of schedule lines.
    1) MRP should not change/adjust the already send delivery schedule lines  which are lying within 3 weeks time from MRP date
    2) System should not allow to book the GRN unless the messages / print out has been generated from the system in case of scheduling agreement.
    Thanking you
    Shantakumar
    09944009752

    Hi,
    There are 2 possibilities:
         1. use MRP fixing using planning time fences, this is done by putting the relevant settings in the MRP1 view of the material master
         2. use the firming options of the scheduling agreement, these are set per material number that is entered in the scheduling agreement.
    The GR can only be posted for schedule lines that have been processed aka output generated.
    Regards,

  • Stock transport order requiremnet date does not match in tranRRP3) &MD04

    STO delivery date does not match in transaction MD04 (ECC 6.0) and RRP3 (SCM5.1). This situation occurs when delivery date in STO is past due.  During Shipment Scheduling & avaibilty check, materail staging/availability date(EKET-MBDAT) get updated with current date. This EKET -MBDAT date is reflecting in the stock requirement list as a requirement date which is correct. Still APO product view screen dispalys the past due date as a requiremnet date instead of date in MBDAT.
    Please let me know in case of any more clarification on this.

    Dear Sanjay,
    STO Delivery Date is receipt date at destination location. This minus Transportation Lead time is STO requirement date at source.
    When you conduct ATP check for this PO/STO, your committed date is updated at source and delivery date will be updated as committed date plus TL lead time.
    Do check your GR/GI times in Product Master as primary date mismatch issue.
    If you are using any Customized program for updating EKET-MBDAT, it wont automatically trigger the change date in APO.
    In such cases you need to run CCR in APO and reconcile.
    The better way is to periodically schedule IM initialization (RIMODINI). This maps all R3/ECC data in your IM for PO/STOs and you would see the consistency in APO and ECC.
    Regards,
    Bipin

  • Extractor not picking delta data

    Hi All ,
    I have a very peculiar problem with extractor 2LIS_02_SCN .
    The Delta data's are not getting captured in BW as well as in the RSA3 .This is happening for few  PO's .
    I checked the extractor debugger as well (in RSA3) , but it shows only 1 record which is already there in BW , but the new delta data is not available in RSA3 as well .Deltas are running fine everyday .  I also checked in the underlying table EKES for the Vendor Confirmations , I can see 2 records ie the previous as well as the changed records . Now my Problem is why the extractor is not pulling the new changed record . We have Update Mode in R/3 as Direct  Delta
    Note : There were no filling of  set tables done since long time. set up tables are working fine .
    Could anybody help me in this issue .
    Thanks & Regards
    Zeenath Syeda

    Hi sidhartha,
    SAP says :
    <i>To improve performance, this DataSource contains no information about scheduling agreements. This also applies to returns items, service items, and limit items.</i>
    So check whether your records(which are not extracted) are belongs to any one of above types.
    With rgds,
    Anil Kumar Sharma .P
    Message was edited by: Anil Kumar Sharma

  • MD04 Stock requirement changed date is not updated.

    Hi Experts,
         Please can any one give me solution for the date in Md04.
    Co02 if I change the PR date that date is not showing up in MD04, the previous date is showing up that to 1 day extra.
    Reward poins will be given

    Hi Jay,
        My requirement is : In CO01 we create production order with BASIC FINISH and START DATE.  exp  FINISH DASTE  12/01/2007
                                        START DATE     11/30/2007
    In MD04  : i can see this start date  as 11/30/2007 for all the stock requirements
    If I change the date in CO02 as  FINISH DASTE  12/20/2007
                                                   START DATE     12/01/2007
    in MD04 should show 12/01/2007 for all stock requirements, but it is showing 11/30/2007.
    Please help me in this issue, Good reward will be given

  • ICal Week view, Date is not aligned with the Time(schedule) of each date

    Well, just like it says over there (`` ). I've recently been to China for a business trip, and I suppose the different time zone may have had something to do with the problem. Now I'm back home, changed the time zone back to normal, still the iCal shows in the weekly view that the Date on the above is not aligning with the Time and schedule. Any suggetions would be grateful!!!

    Hi,
    i omit the scheduling maergin key in material master,
    the result of MRP is
    BASIC DATES
    Finish 15.10.2009
    Start 14.10.2009
    PRODUCTION DATES
    15.02.2010 14:33:25
    14.10.2009 07:00:00
    scheduling type i planned order is still "backwards"
    so in MD04 it is say that the goods is available at 15.10.2009 same with requirement dates.
    this seem not right.
    it seems that order finish date is not adjusted by lead time scheduling on "today scheduling".
    Is there a way so order finish date is adjusted by lead time scheduling on "today scheduling" ????
    Best regards,
    Freddy Ha
    Edited by: Freddy Halim on Oct 14, 2009 10:01 AM

  • Basic date is not same with schedule dates

    Hi,
    I have a problem in MD04 stock requirement list.
    Planned order basic date and schedule date is not the same.
    The schedule date finish at year 2010 but basic date still end ad 2009
    in MD04, the date display is basic date.
    Why the basic date is not adjusted?
    in configuration i had choosen adjust basic date in scheduling planned order.
    In material master in house production time is not updated because we use lead time scheduling
    Please kindly help
    Best regards,
    Freddy Ha

    Hi,
    i omit the scheduling maergin key in material master,
    the result of MRP is
    BASIC DATES
    Finish 15.10.2009
    Start 14.10.2009
    PRODUCTION DATES
    15.02.2010 14:33:25
    14.10.2009 07:00:00
    scheduling type i planned order is still "backwards"
    so in MD04 it is say that the goods is available at 15.10.2009 same with requirement dates.
    this seem not right.
    it seems that order finish date is not adjusted by lead time scheduling on "today scheduling".
    Is there a way so order finish date is adjusted by lead time scheduling on "today scheduling" ????
    Best regards,
    Freddy Ha
    Edited by: Freddy Halim on Oct 14, 2009 10:01 AM

  • Why the basic finish date is not adjusted in planned orders

    Hi, all.
    Can anybody help me to understand:
    "Why the basic finish date is not adjusted in planned orders during
    forward scheduling, but in production order basic finish date is adjusted?
    It is look like non-coordination between groups of developers.
    And lead to situation, when planner don't see in MD04 when he can really wait material receipt. He must go to planed order and check production data there, it's unusable."
    Am I right, or SAP have it's own logic.

    Hi,
    Production orders are different story. Since production order is a constant element, they are not created in the course of MRP, basic dates can be adjusted. In production order basic finish date is adjusted, but you won't see for the upper level materials', basic dates of the planned orders adjusted according to the prodcution order you create. Production order is consistent within itself in terms of date and is not dependent to other elements of MRP, but planned orders are not like that.
    MRP creates planned orders whose basic finish dates are calculated by subtracting goods receipt time from production start date of the source of requirement. MRP works backwards without changing directions. Meanwhile if any production finish date is calculated different than the basic finish date due to forward scheduling, in order not to violate the alignment between the basic finish date and source of requirement's start date, basic finish date is not adjusted. If it was, dates of all the planned orders calculated so far at the upper levels of the BOMs had to be recalculated, otherwise all the consistency of all the dates is violated. This cannot be done because changes in any level affects all lower levels.

  • MRP Data in BW Has anyone did this before?

    Folks, I am trying to get the MRP data into BW and found that I could use the 2LIS_03_S194 extractor.....but here are a few things I am struggling with:
    1. It cannot support Delta...
    2. I am getting an error message when I extract the data or even do a RSA3 on the data source, the message reads "Faulty DataSource 2LIS_03_S194 or error in LIS environment for S194"
    Here is what I did
    1. Install data source from RSA5
    2. LBW0 (This gives an error "Generation not possible in SAP name Range" so I guess we do not need to generate the data source at all.
    3. If I look at the generation Log, it says this information strucutre cannot be used for SAP BW
    4. I used the program RMCBMRP2 and filled the S194 table and dsaw that it has data in it
    5. Next when I did a RSA3 it fails with the message I gave earlier "Faulty DataSource 2LIS_03_S194 or error in LIS environment for S194"
    also is it recommended to go for full loads everyday ? or can we just do a date based selective load every daya after the first full load?

    Ram,
    Try this:
    1. Delete the data in S194 table using transaction LBW2
    2. Fill the table S194 by running program RMBCMRP2 with transaction SE38
    3. Fill the following parameters for the initial load
    From Data: Some date in the past
    To Data: Current Date – 1
    4.After filling the table, log in to BW and run the full package which will load all the records into the cube.
    5.For delta, schedule the job in R/3 by setting up a variant for the program.
    a.Variant for the program should be set as specified below
    b.Do the same setting for ‘From’ and ‘To’ dates
    6.After saving the variant, schedule the job on R/3 side.
    7.Info Package configuration for daily loads on BW side.
    Use the package with above configuration in the process chain so as to get yesterdays data.
    Note: One important things to keep in mind is that R/3 job should be scheduled after 24:00 hours so it picks ‘yesterdays’ date and the same holds true for the BW package.
    For some reason if anytime you have to drop the data in the cube, then you will have to perform the setup from step 1 to get complete data.
    also check this thread:
    MRP list
    assign points if helpful
    kalyan

  • Extracting MRP Data by GR date instead of AV date

    For reporting purposes I  have a requirement to extract the MRP data by GR date, not the default AV date. I have looked at all the FM's and the BAPI's I could find and cannot seem to get the data as required.  I see that in MD04 you can change your user setting to default to GR date, so I assumed that there is a similar configuration or FM parameter that can do the same.  So far I have not found a solutoin. Short of writing a custom ABAP that mimics the MD04 GR button for every plant/material I'm  hoping someone has a better suggestion.

    For reporting purposes I  have a requirement to extract the MRP data by GR date, not the default AV date. I have looked at all the FM's and the BAPI's I could find and cannot seem to get the data as required.  I see that in MD04 you can change your user setting to default to GR date, so I assumed that there is a similar configuration or FM parameter that can do the same.  So far I have not found a solutoin. Short of writing a custom ABAP that mimics the MD04 GR button for every plant/material I'm  hoping someone has a better suggestion.

  • Costing error while change mrp data in material master

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    i need to change the mrp data in mm02 and i donot want to do delete the pcc .
    any process to carryover
    thanks
    Edited by: raj on May 24, 2010 12:22 PM

    Hi,
    MRP is mainly configured for a material so that tere would not be any need for manual checking of the stock so as to create a PR. 
    The parameters which you have specified for a particular material like reorder point and lot size will help in planning for a particular material.
    If you need only Qty of two (Less) then  there s no need of configuring a MRP for that material
    And lot size is also decided basing on certain other factors like
    1) Lead time
    2) Transportation costs involved in procuring the material etc
    So ifyou want to generate PR for a qty of 100 then you need ot change the lot size
    I hope this gives you clarity
    Thanks & Regards
    Pavan

  • Costing error while change the mrp data

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    pls give some hints to clear
    Any program is there to change the MRP data for the material master in production server directly
    thanks

    Dear ,
    Did you try MASS or MM70 Transction ?
    If you do not want to go for Deletion flag of PCC  , you need to settle the REM qty  .You need to do product cost for semi finished product and finsihed product in KKF6N and after that you have to do mark and release in CK24N .For standard cat Estimate create std Cost estimation(CK11n)  and std cost Estimation Mark & release(CK24) .
    1.Backflush (confirmation) the Planned order - MFBF. Results planned order will Reduced and GR,GI, activity cost will be posted. U need not convert the planned order to production order, Confirmation for planned order only.
    2.To see Backflushed documents MF12
    3.Then Goto KKF6n to see the Manufaturing cost.
    4.Over head calculation - (Co42)
    5. Variance calculation (KKS6)
    6.Settlement(KK87)
    Try and revert back
    Regards
    JH

  • Planned order creation with PDS valid on only order start date and not finish date

    Hi All,
    We have requirement to allow creation of planned order manually if production version is valid on order start date and not finish date.  This is because lead time of order is longer. I refered OSS notes 385602. I could find out solution for this is implementation of OSS note 694140 to change validity mode at activity level to consider start date of first produce activity  in validity interval. Problem is even If I create order in APO by implementiong this note planned order is not transfered to ECC and it gets stuck with error production version not valid.
    Is there any way in ECC to control this? Any config or customization?
    Regards,
    Santosh

    Nilesh,
    I think there is a simple procedural skip happening in your business process. You are right when a planned order is created after MRP it would default assign it to the first available production version. 2options available for us,
    1. First use transaction MF50 and do the line loading and assign the quantites to the production versions/Production lines, so that the actual capacity planning is getting completed. This way you can have planned orders with both the production versions and matching to your actual line capacity.
    2. Use Quota arrangement concept, to automatically split the Planned orders during MRP for a percentage based on individual production versions.
    Now when backflush is performed S225 table is updated and Planned order qty also gets reduced.
    Hope this helps....
    Regards,
    Prasobh

  • Report MRP data - Fixed Vendor

    Hi All,
    I am trying to build a report by query, to display MRP data and related fixed vendor (if available).
    I tried joining the tables MARC, MAKT, EORD and LFA1, but did not get the output as desired. The report shows only the material with a source list.
    Please, could you help me to display all the records (with or without fixed vendor)? How can i use a outer join?
    Thanks in andvance.
    Antonio
    Edited by: Antonio Bruno on Jun 22, 2011 10:40 AM

    Can use the inner join directly in the infoset by add a table.

Maybe you are looking for