While accessing the MRP List (collective access MD06). There is a selection option for MRP Date. SAP Help tells that "Date: for example, all MRP lists that were created or processed within the last two weeks".
But I could not understand what this means. Please clarify this.
Regards
Mahesh

Hi
It means that, the MRP list will be displayed only for those materials that were created in that time frame. There might be materials for which MRP is not run and processed within that time frame. they will not be displayed. This is one of the parameters for filtering the list.
Hope this is clear and helpful. If so please reward
Chandra

Similar Messages

  • Report MRP data - Fixed Vendor

    Hi All,
    I am trying to build a report by query, to display MRP data and related fixed vendor (if available).
    I tried joining the tables MARC, MAKT, EORD and LFA1, but did not get the output as desired. The report shows only the material with a source list.
    Please, could you help me to display all the records (with or without fixed vendor)? How can i use a outer join?
    Thanks in andvance.
    Antonio
    Edited by: Antonio Bruno on Jun 22, 2011 10:40 AM

    Can use the inner join directly in the infoset by add a table.

  • Past MRP data

    Dear all,
    My client want   report with comparision of 2 MRP result  like ( no planned order , purchse order before and after MRP )
    For developing a Y report : Can you suggest me from where i get resutls of past MRP ? system should store data some where even if in frontend it is deleting and creating planned orders/ PR's again
    Please guide
    Ishwar
    Edited by: Ishwar on Jul 27, 2009 4:02 PM

    Ishwar,
    Although you think the system SHOULD store historical MRP lists, it doesn't.  You can get MRP to output the lists to a spoolfile, but this data format does not lend itself to data extraction (transaction MDLD)
    You will have to create your own storage methodology. 
    MRP lists are usually stored in a cluster, which are not directly readable.  Your storage will probably be easier if you change config for MRP such that it stores the MRP lists in Transparent tables.  IMG>Production>MRP>Check of performance settings>Check storage mode for MRP lists.  Select all checkboxes that are relevant.  THERE WILL BE A PERFORMANCE TRADEOFF.
    You could then easily copy data to your own Z tables, and manage and report these data anyway you want.
    Rgds,
    DB49

  • MRP Data in BW Has anyone did this before?

    Folks, I am trying to get the MRP data into BW and found that I could use the 2LIS_03_S194 extractor.....but here are a few things I am struggling with:
    1. It cannot support Delta...
    2. I am getting an error message when I extract the data or even do a RSA3 on the data source, the message reads "Faulty DataSource 2LIS_03_S194 or error in LIS environment for S194"
    Here is what I did
    1. Install data source from RSA5
    2. LBW0 (This gives an error "Generation not possible in SAP name Range" so I guess we do not need to generate the data source at all.
    3. If I look at the generation Log, it says this information strucutre cannot be used for SAP BW
    4. I used the program RMCBMRP2 and filled the S194 table and dsaw that it has data in it
    5. Next when I did a RSA3 it fails with the message I gave earlier "Faulty DataSource 2LIS_03_S194 or error in LIS environment for S194"
    also is it recommended to go for full loads everyday ? or can we just do a date based selective load every daya after the first full load?

    Ram,
    Try this:
    1. Delete the data in S194 table using transaction LBW2
    2. Fill the table S194 by running program RMBCMRP2 with transaction SE38
    3. Fill the following parameters for the initial load
    From Data: Some date in the past
    To Data: Current Date – 1
    4.After filling the table, log in to BW and run the full package which will load all the records into the cube.
    5.For delta, schedule the job in R/3 by setting up a variant for the program.
    a.Variant for the program should be set as specified below
    b.Do the same setting for ‘From’ and ‘To’ dates
    6.After saving the variant, schedule the job on R/3 side.
    7.Info Package configuration for daily loads on BW side.
    Use the package with above configuration in the process chain so as to get yesterdays data.
    Note: One important things to keep in mind is that R/3 job should be scheduled after 24:00 hours so it picks ‘yesterdays’ date and the same holds true for the BW package.
    For some reason if anytime you have to drop the data in the cube, then you will have to perform the setup from step 1 to get complete data.
    also check this thread:
    MRP list
    assign points if helpful
    kalyan

  • Delivaery Date in MRP PR

    Hi All,
    How the delivery date is calculated in MRP generated?
    Here is the scenario:
    We have planned del time in material master is 14 days, GR processing time is 2 days.
    PR has created on 23 Nov 2011, and it gave the delevery date 28.12.2011 how?
    FYI: There is a contract where the planned delivery time is 28 days, and also there is a reservation for same material for 261 movment and the requirement date is 11.01.2012.
    Could you please help to understand this calculation.
    Thanks in advance.

    A contract and reservation is no way related to each other in this context.
    A contract is long term agreement from vendor to buy something at an agreed price and condition.
    Reservation: Reserving Depenedent goods. (Ex. BOM Components are reserved when a planned order is converted into a Production order.)
    The role of MRP: it plans, the procurement cycle when certain materials falls below (re-order point VB(one of many ways)) because a reservation was created and subsequently the stock fell below re-order point.
    If the contract was maked as MRP relevant in source list then, MRP can create PR against the contract in MRP.
    Go thru this small presentation: [Material Requirement Planning|http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/30f4d6c1-0808-2d10-2ea5-f9b2863cfed8?QuickLink=index&overridelayout=true]

  • Schedule lines should not change 3 weeks time from MRP date

    Hi
    Is there any specific customisation required to get following results in case of schedule lines.
    1) MRP should not change/adjust the already send delivery schedule lines  which are lying within 3 weeks time from MRP date
    2) System should not allow to book the GRN unless the messages / print out has been generated from the system in case of scheduling agreement.
    Thanking you
    Shantakumar
    09944009752

    Hi,
    There are 2 possibilities:
         1. use MRP fixing using planning time fences, this is done by putting the relevant settings in the MRP1 view of the material master
         2. use the firming options of the scheduling agreement, these are set per material number that is entered in the scheduling agreement.
    The GR can only be posted for schedule lines that have been processed aka output generated.
    Regards,

  • Costing error while change mrp data in material master

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    i need to change the mrp data in mm02 and i donot want to do delete the pcc .
    any process to carryover
    thanks
    Edited by: raj on May 24, 2010 12:22 PM

    Hi,
    MRP is mainly configured for a material so that tere would not be any need for manual checking of the stock so as to create a PR. 
    The parameters which you have specified for a particular material like reorder point and lot size will help in planning for a particular material.
    If you need only Qty of two (Less) then  there s no need of configuring a MRP for that material
    And lot size is also decided basing on certain other factors like
    1) Lead time
    2) Transportation costs involved in procuring the material etc
    So ifyou want to generate PR for a qty of 100 then you need ot change the lot size
    I hope this gives you clarity
    Thanks & Regards
    Pavan

  • Costing error while change the mrp data

    Hi dears,
    This is Rem process. when i try to change the material master MRP data ex. ( mrp type M1 to M0)
    system not allow to change and show the error as
    Product cost collector 000000750122 is still active (assigned to PrCtr 50601-025)
    pls give some hints to clear
    Any program is there to change the MRP data for the material master in production server directly
    thanks

    Dear ,
    Did you try MASS or MM70 Transction ?
    If you do not want to go for Deletion flag of PCC  , you need to settle the REM qty  .You need to do product cost for semi finished product and finsihed product in KKF6N and after that you have to do mark and release in CK24N .For standard cat Estimate create std Cost estimation(CK11n)  and std cost Estimation Mark & release(CK24) .
    1.Backflush (confirmation) the Planned order - MFBF. Results planned order will Reduced and GR,GI, activity cost will be posted. U need not convert the planned order to production order, Confirmation for planned order only.
    2.To see Backflushed documents MF12
    3.Then Goto KKF6n to see the Manufaturing cost.
    4.Over head calculation - (Co42)
    5. Variance calculation (KKS6)
    6.Settlement(KK87)
    Try and revert back
    Regards
    JH

  • MRP Data Tables

    Dear Experts
    Pl tell about the MRP Data Table Where the Data Is stored .
    Like Requirement qty , Plant Stock,Open Purchase order, STO,subcontracting , Shortage qty.
    tables which will help me out to get the data from table .
    Rgds
    Pankaj Agarwal

    Dear use the following function module to get the details of what you are asking
    MD_STOCK_REQUIREMENTS_LIST_API
    Give plant and material number and execute...you will get all the data.

  • MRP Data from Live Cache

    Hi
    Please let me know the FM/BAPI which will get me the MRP data from Live cache.
    My requirement is to get the date and quantity for each element, MRP elements to be used are VC,VE,LF based on the plant and material
    Thanks in advance
    Amit

    Hello Sebastian,
    FM '/SAPAPO/OM_PEG_CAT_GET_ORDERS' seems to cover my requirements and I'm happy I found out about it here. Unfortunately I have some problems testing with SE37:
    Specifying only PEGID together with needed categories was not successful. Searching for calling programs of this FM I found FM '/SAPAPO/ATP_DISP_LC_SINGLE' which additionally sets parameter IS_GEN_PARAMS-SIMVERSION to '000' and receives the correct values.
    Now I have the problem that with setting the same input values I still receive exception 'LC_APPL_ERROR' and don't know why. Since I'm new to APO it could be some basic setting, still I'm wondering why this could be. Hopefully you can provide some helpful information, otherwise I think I'm lost
    Thanks in advance,
    eddy

  • Table of WBS MRP Date Data

    I want to know all MRP Run Dates for a WBS Elements i.e all the dates in which MRP is carried out for that particular wbs. Please Reply ASAP.
    Thanks

    Dear,
    Yor question is not clear. Are you looking for the PS driven MRP data?
    You will get the data in MD4c...enter the Project or WBS..you will get the required data
    This data is not comming from one table
    Try using FM-  MD_STOCK_REQUIREMENTS_LIST_API

  • Extracting MRP Data by GR date instead of AV date

    For reporting purposes I  have a requirement to extract the MRP data by GR date, not the default AV date. I have looked at all the FM's and the BAPI's I could find and cannot seem to get the data as required.  I see that in MD04 you can change your user setting to default to GR date, so I assumed that there is a similar configuration or FM parameter that can do the same.  So far I have not found a solutoin. Short of writing a custom ABAP that mimics the MD04 GR button for every plant/material I'm  hoping someone has a better suggestion.

    For reporting purposes I  have a requirement to extract the MRP data by GR date, not the default AV date. I have looked at all the FM's and the BAPI's I could find and cannot seem to get the data as required.  I see that in MD04 you can change your user setting to default to GR date, so I assumed that there is a similar configuration or FM parameter that can do the same.  So far I have not found a solutoin. Short of writing a custom ABAP that mimics the MD04 GR button for every plant/material I'm  hoping someone has a better suggestion.

  • RIMODINI for CIF Object: [MRP Area Matl, MRP Areas]

    Hi Experts,
    We have Material maintained at MRP areas in R/3. Integration model is maintained with CIF object : [MRP Area Matl, MRP Areas] to bring the new material master at MRP Area changes through Delta mode(CFM3), but the changes to existing material in Integration model at MRP Area does not come over immediately to APO and not through DELTA mode.
    We have to execute Report: RIMODINI to bring the changes of existing material master changes at MRP Area level to APO. Since its a performance intensive it takes too long  to execute to bring changes over to APO.
    Is there alternative method of bringing the existing material master changes at MRP area level for CIF object : [MRP Area Matl, MRP Areas] to APO without executing RIMODINI.
    Additional Information: R/3: SAP_APPL     470     0030     SAPKH47030
                                     R/3: PI                2004_1_470     0015     SAPKIPZI5F
                                    APO:SCM                    500     0012     SAPKY50012
    Thanks,
    K Sendil Kumar
    Thanks,
    K sendil Kumar

    Hi Sendil,
    Are you getting this error only for Material or other master data also?
    Please can you quickly check below mentioned checks:-
    https://www.sdn.sap.com/irj/scn/wiki?path=/display/scm/cif
    Regards
    Samir

  • MRP Areas and MRP

    Hi I've created MRP areas, and expect to run MRP by MRP area, however, when I click on the drop down list beside the field MRP area in MD01 I do not get a list to select an individual MRP area.  Is this right?
    Thanks

    Hi,
    we can use Total planning(MD01) for a single plant or use scope of planning to control whether total planning is to be carried out for single plant/sevaral plant/ for one MRP Area/sevaral MRP areas/ combination of plant and MRP Areas.
    Steps :
    1.Group together the plants which are to be planned in spro in --->Define scope of planning.(OM0E)
    2. Define the scope of planning as 999 for ex and give description.
    2. Now select that and Specify the sequence in which Plants and MRP Areas are to be planned,
    3.Goto new entries and enter the plant as 1000/MRP Area as 1000 with counter 1 and plant as 1100 with counter 2 and save.
    4.Execute the total planning either as online job or as background job.
    5.The planning run has to be always started with paralle processing.
    In SPRO in define parallel processing in MRP enter the destination for parallel processing for ex your server name and enter the no .of sessions as 1 and save.
    6.Tcode MD01 enter the scope of planning group and selet the parallel processing and enter. Hope the above points taken care and resolve the issue. Thanking you.

  • How to auto populate data from one list in SharePoint 2007 into another list based on a key value?

    Hi,
    As a part of new requirement in my project I am supposd to work on SharePoint 2007. I have one List (BCExtract - Main list) with all data related to an Application (like ID, name, app manager RTO etc).
    I have created another list which has form to be filled by a user (with details about his/her applications). My requirement is that when the user enters AIT ID then the page should refresh (probably after hitting enter) and other details like Application
    name, RTO etc which is present in another list gets auto populated depending on the AIT ID (unique column) entered so reduce the burden on the user.
    Please suggest me how this can be done. I do not have permission for obtaining SharePoint Designer and I do not know JQuery. Infopath is ok but if this can be done through SharePoint 2007 alone then it would be great.
    Thanks....

    Hello,
    You can either use jquery/jaavscript or infopath form to achieve this. There is no default way to do this.
    I would suggest jquery because you can put script in newform/editfor.aspx page using content editor webpart. Refer this link for jquery:
    To get value from list:
    http://social.technet.microsoft.com/Forums/en-US/ac47fe2a-ccb6-4f5b-b274-703aecc6cb0a/get-list-items-in-sharepoint-2010-by-using-jquery
    http://www.robertkuzma.com/2010/08/read-list-items-using-sharepoint-web-services-and-jquery/
    To set value in column:
    http://paulgalvinsoldblog.wordpress.com/2009/06/13/quick-and-easy-use-jquery-to-set-a-text-field%E2%80%99s-value-on-a-sharepoint-form/
    http://spservices.codeplex.com/discussions/468729
    If you use infopath form, then you need to create two data connection to get data from both lists. Later you can set value in fields based on selection using rule. This can be possible without code.
    Hope it could help
    Hemendra:Yesterday is just a memory,Tomorrow we may never see
    Please remember to mark the replies as answers if they help and unmark them if they provide no help

Maybe you are looking for