MRP dependent requirements indicator

Hi,
Can anybody please let me know use of MRP dependent requirements indicator in MRP4 view?
Regards,
Samir Wadajkar

Dear,
You only use this indicator in connection with planning strategies for make-to-stock production, assembly planning. Note that the indicator Dependent requirements not relevant to MRP should only be used when, for  example, planned independent requirements exist for an assembly.
EX... If you manufacture the chemical product say named ABC and you use water as component to manufacture it , and you dont want to plan the WATER quantity as it is used in bulk . So you can exclude the material water from the MRP run and only the Chemical product is planned and not the WATER.
Edited by: Girishprasad Subhash Pawar on Jun 24, 2010 9:13 AM

Similar Messages

  • MRP Dependent requirements - How to define

    Hello.
    If I set "1" in MRP Dependent requirements field the Depended Requirements are excluded, but also the Order reservations.
    Can i somewhere set so that only depended requirements are excluded and not the rest?
    Thanks in advance.
    /Gherry Svantesson

    Dear,
    In the MRP dep.requirements field, you set the indicator to 1 so that dependent requirements (reservations) are not planned.
    You do not set an indicator in the Cross-project field for the availability check. This means that only the individual segment (segment of the production lot) is checked during the availability check.
    Thanks,

  • MRP Planned order generation for Order reservation excluding Dependent Requirements

    In our Project we have a requirement like for FG stage & SFG1 stage are M.T.O So after sales order are punched through  MD50 we have created Planned orders against sales orders,But dependent stages like SFG2 & SFG3 which are pure M.T.S so only Dependent requirements will get generated.Suppose for SFG1 i have partially converted planned order to Production order then for component SFG2 we get Partial Quantity as order reservation.Now requirement is if i run MRP for SFG2 system need to generate demand only for order reservation excluding Dependent requirements.Is there any possibility where we can generate demand only for order reservation.As system will create Planned order for SFG2=Dependent requirement + Order reservation

    Hi Uli,
    Suppose i have Sales order--100 kgs for FG
    B.O.M levels
    1.FG-----M.T.O
    2.SFG1---M.T.O
    3.SFG2---M.T.S
    4.SFG3---M.T.S
    5.ROH
    So if i run MRP via MD50 system would generate planned orders for FG & SFG1 level as they are M.T.O specific
    Now my requirement list would be
    FG-100kg planned order
    SFG1-100kg planned order
    SFG2-100kg dependent requirement.
    Now suppose i have partially converted SFG1 planned order to production order
    SFG1--100kg planned order to 30 kg production order
    Now my requirement list would be
    FG-100kg planned order
    SFG1-70kg planned order & 30 kg production order
    SFG2-70kg dependent requirement & 30kg order reservation.
    Here my requirement is if i run MRP for SFG2 in MD02 as these stage is M.T.S system should provide 30 kg planned order & if we see down the line it would be like
    Now my requirement list would be
    FG-100kg planned order
    SFG1-70kg planned order & 30 kg production order
    SFG2-30kg planned order & 70kg dependent requirement.
    SFG3-30kg planned order
    ROH-30kg Purchase req
    Client requirement is like these..

  • MRP: how to segregate the planned orders by dependent requirements

    Hello SAP Guru's,
    I would like to know if this is possible to make the MRP work is this way:
    - generate global planned orders (by date) for several dependent requirements, for inhouse production;
    - AND generate individual planned orders for each dependent requirement, for external procurement;
    For the moment, it is grouping the quantities of all the dependent requirements to generate a unique planned order by date.
    But we would like to get separate planned orders for each dependent requirements that are externally procured.
    Do you think it is possible to do so? and if yes, how?
    Thanks in advance for your help on this subject.
    Regards,
    Rudy

    In MD04 the demand n supply that is seen is considered as plant segment. In some cases when you plan demand n supply for a given storage location separately it is called as SLoc segment, also if you're working with MRP areas then its called mrp area segment, likewise for project & sales order.
    In short it is just a way MRP would do its planning. In normal cases, the demand n supply is in plant segment, so in this segment the least resolution that you can work with is a day, so all demand on a given day is clubbed together and a supply proposal is made (depending on the lot size).
    If you want further split on a given day, then MRP needs some way to identify the difference & this is provided by the special stock segment such as project segment. To see how it works, if you're working with PS module, ask your PS colleague to create a demand for the material from different projects for a given day. Then in MD04 you will see each project demand show up in different segment & when you run MRP, you will see the results.
    I guess more than me writing quite a lot out here, a simple test at your end should help clarify... good luck

  • Dont want dependent requirement after MRP

    hi all
    I dont want dependent requirement after MRP?
    means A is a header material and B.C are the component
    after MRP run system should be created requirement of component item.
    so wht r setting  required?
    plz guide me

    Hi,
    First you ask how can you carry out settings not to get DepReq for your components than you say system should create requirements for your components.
    Please give a clearer picture of your situation and make your question more clearer.
    How do you procure your goods (if you do not use MRP)?
    If you do not want DepReq for your goods you can:
    - remove them from the BOM (use them as text item, use design BOM - I do not know your situatio)
    - you can set the MRP type in material master as 'ND' (not planned) (MM02 > MRP1)
    Please give more information.
    Thanks,
    Csaba

  • Rounding of Decimal for dependent requirement During MRP Run

    Hello Experts,
    I have the following scenario:
    We are currently enabling Characteristic Based Planning in our system.
    Our one component is selected when two characteristic values are met through object dependencies.
    Ex: Component A = Char A= '002' and Char B ='002'
    Now we have given the following Usage Probability for the two characteristic:
    Char A = 20%
    Char B = 15%
    And the total PIR quantity is 25 Pcs for Configurable Header.
    With the above usage probability and PIR Qty, We have a dependent requirement of 0.75 Ea
    ((20% X 15%) of 25 Pcs) = 3% of 25 Pcs = 0.75 Ea of the component
    Now during MRP Run I want to round the dependent Requiremnet to 1 Ea instead of 0.75 Ea.
    Any suggestion towards the solution will be appreciated.
    Regards,
    Vinod

    Hi Vivek,
    As mentioned we are using Characteristic Based Planning.
    The component is selected based on a Selection comdition which is as follows:
    Component 721290201000 = $PARENT.BCS_RL_LINE_LOADER = '002' and $PARENT.BCS_RL_WAFER_VENDOR ='002'
    When the above two conditions are met the component is selected.
    In Characteristic Based Planning we give percentages (Usage Probabality) to the characteristic values like:
    $PARENT.BCS_RL_LINE_LOADER/'002' =20%
    $PARENT.BCS_RL_WAFER_VENDOR/'002'= 30%
    For the Parent which is a KMAT Material we maintain the PIR say 40 Qty.
    Now the component qty is calculated as follows:
    721290201000 =(20% X 30%) of 40 Qty of parent
    721290201000 =(6%) of 40 Qty of parent
    721290201000 = 2.4 Qty of component is the dependent req.
    Now my requirent is to round the dependent requirenment to 3 during MRP Run. Please note that the purchase requisition got from the above dependent requirement is rounded to 3 qty.
    Now I want to round the dependent requirement.
    Regards,
    Vinod

  • Dependent requirements for Top level materials planned in MRP

    Hey Gurus,
    A top level material 20350 has a component 30397 and both of these materials are planned in APO.  We have another top level material 30399 (but this material is planned in MRP) and the component 30397 (is planned in APO) will the dependent requirements from material 30399 be populated in APO for material 30397?
    Sincerely,
    Kris

    Kris
    As Datta has mentioned the dependent demand will not reflect for the component material in APO. We had the same scenario as yours and this is what we did
    We modified the Planned order integration model filter criteria by adding custom logic in the BAdI CIF_INT_MODEL. The logic was to query the BOM tables in R/3 and find out all parents that have SNP relevant materials as components and include these parents in the list of materials for which planned orders are to be CIF'ed from R/3 . The BAdI will be invoked when you run the IM generation .
    You also have to CIF the BOM to APO . Once the PDS and planned orders are available in APO , the dependent demand will be created automatically. ( If you do not want to modify the BAdI then you can write a query and identify the parents and add them to the integration model manually)
    Thanks
    Saradha

  • MRP planning - dependent requirements

    Hi all
    I have an assembly A1 which has a component C1. The assembly can be procured from a vendor or can be produced using component C1. C1 is always procured. I am entering independent demand at A1 and C1. I do not want the dependent requirement from A1 to appear on C1. Is there a way I can stop the dependent requirements on C1.
    thanks a lot

    Hi John,
    Create a BOM Explosion Type in Customization, in which you flag the check box
    "Plng Off".
    Now you assign this Explosion Type in the Item Details screen of the component C1 in the BOM of A1.
    It will fulfill your requirement.
    Regards
    Krishna

  • Dependent Requirements Planning

    Hey Gurus,
    I have a situation in which I have two materials that are planned with Independent requirements but also have dependent requirements against them.  these two materials are 6001116 and 6001771.  I have set the MIXED MRP indicator to "1", planning strategy "40" and MRP Dep. requirements as "1".
    6001116 is not planning the dependent requirements and is only being planned by the independent requirements.  6001771 is planing both the dependent requiremnets and the independent requirements even though I have set the MRP Dep. requirements to "1".  The only difference between these two materials is that 6001116, is a made in house product and the 6001771 is a purchased product. 
    I can't think if anything else that would control this to put me in this situation.  Do you guys have any ideas for me or things that I should check to make sure that this is working correctly?  I thought it was only the Dep requirements indicator that controlled the planning of independent reqs.

    Dear,
    You donot want dependent requirements
    to be created" for your components when MRP is run
    There are three Options:
    First Option:
    For the all respective components in MRP 4 view Input "1" for MRP Dep.Reqts
    Second Option:
    In the Basic Data 1 view maintain the X-Plant Matl Status maintain "01"(Blocked for Procurement/Whse)
    Third option,
    You can set the MRP type in material master as 'ND' (not planned) (MM02 > MRP1)
    Then Planned orders/Purchase requistions will not be created for the components
    Regards,
    R.Brahmankar

  • Setting nedded for creation of Planned Order for Dependent Requirement.

    Hi PP Gurus,
    I have a one material for which I m running MRP which have three Components.
    I m using strategy 10 for FG and SFG also.
    When I m running MRP for FG the system is creation planned order for FG, but not for SFG even though no stock available for them.
    I m using lot size EX for all SFG.
    Please Help.
    Thanks in Advance.

    Dear ,
    You should maintain proper MRP related parameters for both FG and SFG.Check all the MMR parameters :
    1.MRP Type -PD for FG/SFG
    2.Procurement Type -E  for FG/SFG
    3.Planning Startegy -10  in FG
    4.BOM/Routing Explosion -Keep it Blank
    5.Indiviaul/Collective Indicator -not applicable as it is MTS  so keep it blank
    6.Validity of BOM /Routing should be corrcet before MRP run in MD02-NETCH , 2,1,3,3,2
    7.What is the Lot Sizing Set up-EX in OMI4-Scheduling Tab -Requirement date =Delievery Date and BOM Validity Date  .
    Ref .Re: MRP not plalned for dependent components
    8.Check in MRP4 -MRP Dept Requirement Parametre should be balnk for plalling the SFG  in MMR of FG -MM02
    I hope this issue may be with BOM explosion as per the validity and lot size -schedueling set up .
    Hope this will be useful
    Regards
    JH

  • BOM Explosion/dependant requirements

    Dear All,
    I have a concern regarding the "MRP 4" view in MM.
    BOM/Explosion
    Individual / Collective requirements
    "MRP 3" view
    Availability Check
    Availability Check (Daily / Individual)
    I would like to know the effect of these settings clearly with an example please.
    Thank you in advance

    Hi,
    1. The Individual Collective indicator 1/2 indicates how to club the dependent requirements either Individula Processing or Collective Processing.
    This is generally used in MTO Scenario.
    Here, For eg., you have 2 FERT Materials, in that 1 component say xyz is same.
    If you want to club the requiremnts for for xyz for both the sales orders then you need to select 2.
    By defult system will create PurReq for xyz as Sales Order/Customer Specific.
    2. Now the Availability check:
    Specifies whether and how the system checks availability and generates requirements for materials planning.
    The availability check can be carried out in MRP for the depedendent requirements. This means that the availability check can directly check whether sufficient material is available for the production of the assembly. The availability check is initiated from planned order processing. It is not carried out automatically in the planning run for each requirement of an assembly.
    Checking Group and Checking Rule clubbed together forms the Checking control..
    Hope this helps..
    Regards,
    Siva

  • Function module to find out dependent requirements

    Hello Experts,
    Any function module to determine the dependent requirements for process order...
    Pls let me know.
    Regards.

    use the following FM
    MD_STOCK_REQUIREMENTS_LIST_API
    give material no and  plant and following\
    DISPLAY_LIST_MDPSX = X
    DISPLAY_LIST_MDEZX =  X
    DISPLAY_LIST_MDSUX =  x
    o/p
    MDPSX filter for the values of here DELKZ(MRP element indicator) = AR
    you will get all depnedent reservation from process order.

  • System considers dependant requirements lying outside planning horizon

    Hello Experts,
    Iam running the MRP for procurement. I have defined a planning horizon so that system will consider the requirements of that period. Iam using NETPL as my planning method in MRP. I wanted to create only purchase requisitions during this period so I selected 1 as my creation indicator as well.
    But the issue Iam facing is, system is not skipping the dependant requirements which is outside planning horizon. System skips only PIRs.
    For all the dependant requirements outside planning horizon, system creates planned orders and for those within plannning horizon system creates purchase requisition. Is there any settings to skip system considering dependant requirements outside planning horizon.??
    Thanks
    Prathib

    Hello
    I believe that there is a misunderstanding about what exactly is the planning horizon. Using a planning horizon does not means that the requirements outside the horizon will not be planned.
    The planning horizon represents a part of the planning area, where a planning file entry is made for the MRP processing key net change planning in the planning horizon (NETPL).
    In this kind of net change planning, only those materials that have undergone a change that is relevant to MRP within the planning horizon are included in the planning run. Such materials receive a net change planning indicator in the planning file.
    That means, if an MRP relevant change is made for a material within the planning horizon, the planning file entry NEPLT is set for this material.
    You can check in the SAP Help how the planning horizon works, see below:
    "You can also use a planning horizon to further limit the scope of the planning run. In "net change planning in the planning horizon", the system only plans materials that have undergone a change that is relevant to the planning run within the period which you defined as the planning horizon. The system sets the net change planning horizon indicator automatically for these materials."
    http://help.sap.com/erp2005_ehp_06/helpdata/EN/f4/7d274f44af11d182b40000
    e829fbfe/frameset.htm
    So, the planning horizon only define is the planning file will be marked as "net change planning".
    BR
    Caetano

  • Individual/Collective Requirement indicator in MTS

    Hi Gurus,
    Can you please let me know what is the relevence of individual/Colelctive Requirement indicator from MRP4 view of material..
    for Finished product as well as its sub assembliees in case of make to Stock planing strategies.
    i know how it works in MTO and how depednent requirements can be grouped together or sepated based on this indicator.
    When i tested the same in case of MTS, i found for dfinished product as well as sub assemblies behaviour is always like collective irrespective of MRP4 indicator.
    any thougts lets me know.

    Dear Santhosh,
    MRP-4 as 1 : In individual planning, this indicator is used to display the dependent requirements of a component separately.
    MRP-4 as 2 : In collective requirements, this indicator is used to display the dependent requirements of a component grouped together.
    This Indicator is useful to control the planning of dependent requirements if the main product is being planned with strategy 20 ie; MTO Process.
    Ramagiri

  • Conversion of Planned order to PR and Dependent Requirements

    Hello Everyone,
    I had two issues to be dealt with..
    1. When i run my MRP run for a specific plant i do not want the system to automatically convert planned orders to Purchase requisitions for specific material in specific plant. How do i Configure the same?
    2. I use planning strategy 40 for the header material. During MRP run dependent requirements are automatically  raised for lower level components. But how does the user know which planned order is generated for which higher level order?
    Moreover, since the same raw material is used in multiple  finished  materials, a single planned order is raised for the same raw material. This makes it all the more complex.
    I think Individual/ Collective requirement does not help in this case because i am using stategy group 40 which is a MTS strategy.
    Any help in both these cases would be greatly appreciated..
    Sincerely,
    Aji
    Edited by: Aji Kurian Mani on Nov 28, 2009 2:51 PM
    Edited by: Aji Kurian Mani on Nov 28, 2009 2:51 PM

    1) Select the indicator "3"- Planned Orders in the MRP Screen or in a Variant you use to schedule the MRP
    2) Under a make to stock scenario, requirements are summarized in a planned order (or many, according to the lot size key). But in general as the stock is generic and not customer-specific, there is no assignment of planned order to a given customer.
    Regards

Maybe you are looking for