For the FG used strategy 10 no special procurement key..MRP type:PD
For the RM  MRP type PD, MRP4 view Ind/collective indicator 2 maintained.
After running MRP for rawmaterials Purchase requisation are creating  with out consideraing the stock as "Direct procurement" MRP element.
I checked in OPPQ  maintained indicator as 3.
What are the possible reasons. we dont want to create PR  as per direct procuremet we want collective.
Regards,
srihari.M

Hi,
Check the BOM for the FG material if any SPK is maintained in BOM. IN MD04 put the cursor on PR generated and click on Pegged Requiremnt Button, this will give you the osurce from where the direct requirement has been generated and analyse further from that point.
Check and Revert,
Santosh Sarda

Similar Messages

  • MRP SPRO- Plant Parameters-Direct Procurement

    In the spro Plant Parameters-Direct Procurement
         Direct procurement only when creating production order
    1     Trigger direct procurement in requirements planning
    2     Direct procurement only when creating production order
    3     Trigger direct procurement in requirements planning
    Here 1,3 are seems to be same
    thanks
    K.Prabakaran

    hi
    it looks like even 'blank' & 2 are also same similar 1 & 3..
    but, options description clearly mentions the usage..
    Thanks
    JK

  • MRP elements

    Dear all,
    The MRP run creates different procurement proposals like purchase order or planned order. I am doing MRP run in plant A for a finished material with SPK 40 (procurement from plant B). The MRP run is giving me purchase requisitions in plant A. In plant B I am getting the MRP element PRqRel (Release order for a stock transfer requisition) and planned orders for the same quantity. Is the MRP element PRqRel correct? If I want the system to propose the MRP element as TrnReq (Transfer requirements WMS) instead of PRqRel what can I do?
    thanks and regards,
    Raghu

    Hi Raghu,
    Raghu Ram wrote:
    I understand that I am getting the correct requirement in terms of quantity. My question is about MRP elements. There are a lot of MRP elements available. Why the system is chosing only PRqRel as the MRP element. If I want the system to show another MRP element TrnReq in the place of PRqRel, what can I do?
    What is the use of so many MRP elements?
    TIA
    Raghu
    I have a similar query and requirment, I wants to understand the MRP Element TrnReq Functionality and when it comes means in which scenario?
    Did you got any solution then? Can you please share?
    Thanks
    Ashwani

  • MRP elements on MD04

    Hi Gurus,
    We see planned orders in MD04 for a material. Please explain me how and when the system will convert this planned order to PR. The material is externally procured. please exaplain me about the MRP elements and and their relationship in MD04. I 'm new to MD04
    Thanks
    Ansuha

    Dear Anusha,
    Once after running MRP either at the header material level or at the material level,the system creates planned order/purchase
    requisition depending upon the MRP control parameter given for create Purchase requisition at the time of MRP run.
    The planned order/purchase requisition is one of the MRP element that can be seen in MD04,which is one of the important
    screen for a production scheduler/purchase dept.
    Converting a purchase requisition into a purchase order or else a planned order into a purchase requisition depends on the
    business decision.Either you can convert the purchase req into purchase orders via MD04 or else using ME21N.
    Likewise MD14,MD15,MD16 can be used for converting a planned order into purchase req.
    Also a background job can be scheduled using T Code ME59N to convert the pur.req into purchase orders.
    Check and revert back.
    Regards
    Mangalraj.S

  • Closing of open MRP elements

    Hi All,
    I have a lot of open MRP elements in the system. They are since from 2000. The MRP elements are IndReq, DepReq, PchOrd, PurRqs, OrdRes, SubReq, Deliv, ConRel, PlOrd, Prdord, SchLne. So please tell how to close all the open MRP elements. All the materials will not be having all these MRP elements. Please tell me which MRP elements should be closed in decending order i.e. what should be the sequence.
    Regards,
    Ramesh

    Hi Ramesh,
    You need to analyze case by case basis as to which are linked & the impact of deleting them.
    But what you can do is, run MRP with Planning mode as 3, this will remove all procurement proposals (planned order / purchase rqn) which are not firmed. Now you can analyze the ones which are firmed, i.e. if it has been created manually or edited manually.
    The production orders, purchase orders, scheduling agreements needs to be analyzed & based on the confirmation from both operations & finance personnel in your firm, you may proceed to delete / close the same.
    It would be better if you analyze them thoroughly & if you face a specific issue then revert.
    If helpful award points
    Regards,
    Vivek

  • Planning Horizon & Direct procurement

    Hi, how touse the tabs planning horizon & direct procurement in oppr screen while running mrp?

    Hi Yadav
    The Settings of
    1) Planning Horizon in OPPR is meant for using Processing key - -NETPL (Net change for planning horizon) during MRP run : If u maintain the data say 100 days in this field that mean only those materials are planned in the planning run that have a change relevant to MRP within the period (in work days).The length of the planning horizon should at least include the following:
    period in which customer orders enter
    delivery times
    complete material processing time
    This setting is useful to restrict u r planning Horizon length to defined no of days say 100 days
    2) Direct Procurement : The setting controls whether direct procurement is initiated by the planning run or by the production order.Using this indicator, you can procure non-stock items directly for an order, bypassing the warehouse.Direct procurement for "parts to be provided" is not supported in subcontracting.
    U have to use Special Procurement key in Material master
    Regards
    Brahmaji

  • Direct Procurement  for BOM component

    Hi there,
                If we want to use direct  procurement for BOM component then where do we set the indicatior in BOM. I am not able to find the same in BOM.........??
    Please advice me ....
    Regards
    Kaushik

    Hi Kaushik,
    Maintain Direct Procurment is OPPQ-Plant paramaters. Here you specify whether the direct procurement is triggered by the Planning Run or the MRP.
    And also maintain a key for Special procurement Direct Procurement in OPPQ.
    Please assign Special Procurement Key as Direct procurement is MRP-2 view of material master.
    Thanks and regards
    Murugesan

  • Exclusion of Stock Transport specific MRP Elements from MRP Run

    Hi,
    How can we exclude specific MRP Elements from planning?
    I want to exclude the MRP elements like - Ord.DS, PRqRel, PlORel etc from MRP run.
    (After MRP run, they should only be displayed in MD04 and not planned)
    MRP run should treat all other MRP elements normally.
    Warm Regards,
    Madhavi.

    I think I understand what you want to do, and I think it is not possible without some major MODIFICATIONS, because it goes against the grain of what MRP is supposed to do: balance demand and supply.
    One thing you might consider as a possible work-around: create a "virtual plant" say 5000, that is a plant that isn't really used for anything. Then point your special procurement keys in plant 2000 to plant 5000. This is where you then get the purchase req releases etc, and they will not affect plant 1000.
    This doesn't require modifications... but it will also not display the elements in MD04 for plant 1000.
    Just an idea...

  • About the MRP element.

    hi,
    My problem is as follows.
    I have to find out what is next MRP element for the material/production version pair.
    In  my case  to consider the production finish date for planned order  date & scheduled end date for production  order as next MRP element for the material.
    If i got more than one production version for the same material,
    what criteria should i apply for calculating next MRP element.

    Hi,
    Planned order:-A request created in the planning run for a plant to trigger the procurement of a plant material for a certain quantity for a specific date.
    Customer order:- is nothing but sales order, A customer request to the company for delivery of goods or services at a certain time.
    The request is received by a sales area that is then responsible for fulfilling the contract.
    MRP elements are
    OrdRes Order reservation (production order)
    PurRqs Purchase requisition
    SubReq Subcontracting requirement
    SchLne Schedule line
    BtchSt Batch stock
    PrdOrd Production order
    Order Customer stock for make-to-order
    CusReq Customer reqmt (Reqmt element from demand management)
    ShipNt Shipping notification (committed order quantity)
    StLcSt Storage location stock (Storage location MRP)
    BStLoc Batch storage location
    SchAgr Scheduling agreement
    Reser. Reservation created manually
    NtwOrd Network order
    PlOrd. Planned order
    PrjStk Project stock
    IndReq Planned independent requirements
    ForReq Forecast requirements (forecast-based planning)
    QM lot QM inspection lot
    ComCnf Production order confirmation
    SimReq Simulative requirements
    SomOrd Simulative order
    DepReq Dependent requirements
    RelOrd Release order (Multi-plant planning: stock transfer)
    TrRes. Release order requisition (Werksübergr. Planung: Umlagerung)
    UnplRq Unplanned requirements (additional reqmts from forecast)
    StTRes Stock transfer reservation
    Transf Transfer reservation
    Inqury RFQ
    Quote Quotation
    Order Sales order
    SchAgr Scheduling agreement
    Contr. Contract
    Fr.del FOC delivery
    Deliv. Delivery
    CusReq Customer requirement
    GIssue Goods issue
    Stock Plant stock
    GRecpt Goods receipt
    Replsh Replenishment horizon

  • Pur req not generated for MRP element Planned order in stock reqmnts list

    Hi SAP Gurus,
    I have a problem where in MD04, pur req is not generated for the MRP element Planned order for a future date (about two months from now). Is there a specific reason? why is it not being generated? The MRP type is PD. The procurement type is F - external procurement. Can anybody please help me on this?
    Thanks
    Anusha

    Anusha,
    ??  Not sure I understand the question.  Are you saying MRP is creating planned orders instead of  purchase reqs?  Or, are you saying that no proposals at all are being created outside of two months?  Or, are you saying that the system is creating purchase reqs inside of two months, and planned orders outside of two months?
    Regardless, these problems are probably related to your MRP settings.  Try the following settings:
    NEUPL   Regenerative planning             
    1       Purchase requisitions             
    3       Schedule lines                    
    1       MRP list                          
    3       Delete and recreate planning data 
    2       Lead time scheduling and capacity planning
    on your MDBT screen.
    Regards,
    DB49

  • MRP element

    Hi Gurus,
    Please explain me what is meant by MRP element with an example
    Thanks and Regards,
    Prasad Yallapu

    <u>MRP Element</u> is Generic term for all objects which are displayed as items in the MRP list or in the stock/requirements list. The following are the various MRP elements in use with their abbreviations
    Dependent reservation     OrdRes
    Purchase requisition     PurRqs
    Subcontractor requirements of material provided     SubReq
    Order item schedule line     POitem
    Gross requirements planning     -
    >
    Process order     PrcOrd
    Batch stock     BtchSt
    Effective-out date     -
    >
    Subcontracting purchasing     SubCon
    Production order     PrdOrd
    End of planning time fence     -
    >
    Maintenance order     PMOrdr
    In plant (only relevant for IS Automotive)     InPlnt
    JIT call     JITCll
    Individual customer stock     CustSt
    Customer independent requirement (currently not used     CusReq
    Consignment stock for customer (availability check)     CCsgmt
    Shipping notification     ShpgNt
    Storage location stock     SLocSt
    Batch/storage location stock     BtSLoc
    SA schedule line     SchLne
    JIT delivery schedule     JIT-DS
    Stock with subcontractor     SubcSt
    Forecast delivery schedule     ForcDS
    Goods issue     StkIss
    Reservation     MtlRes
    Direct production     -
    >
    Network order     NtwOrd
    Planned order     PldOrd
    Project stock     ProjSt
    Planned independent requirement     IndReq
    Forecast requirement     ForReq
    Inspection lot for quality management     QM-lot
    Returns item     Return
    MRP requirement (only relevant for IS-Automotive)     RPMReq
    Confirmation     POConf
    Simulated requirement from availability check     SimReq
    Simulation order     PldOrd
    Dependent requirement     DepReq
    Safety requirement     SfyReq
    Safety stock     SafeSt
    Simulation requirement     SimReq
    Sim. dependent reqmts     SimReq
    Total requirements     TotReq
    Transfer requirements WMS     TrnReq
    Release order for a stock transfer order     Ord.DS
    Release order for a stock transfer requisition     PRqRel
    Transfer requirement for simulation order     PlORel
    Release order for stock transport scheduling agreeme     ScAgDS
    Unplanned requirement     UnplRq
    Reservation in another plant     StTRes
    Stock transfer reservation     TrnRes
    Request for quotation     RFQuot
    Quotation     Quottn
    Order     CusOrd
    SD scheduling agreement     SchAgr
    SD scheduling agreement; external service agent     SA-ESP
    Contract     Contrc
    Delivery Free of Charge     FOCDly
    Delivery     Delvry
    Planning     -
    >
    Returns (availability check)     RetDly
    External sales order     CusReq
    Unverified delivery     UncDel
    Goods issue     GIssue
    Plant stock     Stock
    Goods receipt     GdRcpt
    End replenishment period     -
    >
    Reward if cleared and close the thread.
    Keerthi

  • Sale Order # - MRP element missing in MD04

    Hi,
    I created an SO with a material, for which planning was not done in MRP view. Later I changed the schedule line category from CN to CP in VA02. Then MRP run is carried out for that particular plant (1001) . IN MD04, i could able to get the details of that particular SO except the MRP element Data . SO # is missing.
    Regards,

    Hi,
    Sale order no. is missing., say 3820. All the details of this SO is furnished properly in line, but the SO # column is blank. And to give you an extra detail, all other SO # for this particular material is displaying in its corresponding column.
        In my observation, if some changes (like changing the schedule line category, order reason), doing such changes effects in displaying the SO # in MD04.
        Pl do help me to display it and could anyone pl tell me what will be the reason for this blank column.
    Regards,

  • In MD05 system show message "The MRP element no longer exist".

    Hi Guru,
    Need some help .
    In MD04 transaction contain Purchase order, when I double click purchase order,It will get open .  But when I open same purchase order in MD05 system show message u201CThe MRP element no longer exist".
    Please help me , if any know the solution or any input. Open purchase order in system.
    Regards
    PNU

    PNU,
    I don't believe this is the same Purchase order.
    Review closely order number/item number/schedule number.  I believe you will see that the old entry (MD05) no longer exists, and has been replaced with a similar item.
    Best Regards,
    DB49

  • Change Mrp Element Data of Production Order in MD04

    Dear guru ,
    In the mrp element data of the stock/requirement list for the production order I see the
    Production order number , the order type , and the system add /RE if production order is released or
    /PD if production  order is partial delivered. No other information about others production order status.
    How can I change mrp element data using Customizing or ABAP in order to recognize in MD04 if production order is confirmed or partial confirmed ?
    Thanks.

    Dear Cris ,
    I am not sure if CNF/PCNF will show up in the MRP Element data in MD04.I have checked PO which are also CNF/PCNF and i looked the same order in md04.It is not showing .U may need some ABAP help .
    But if you really intersted to see the list PO status together , then go to COOIS and give plant , order type .It will give you all the order under that plant irrespective of material and also Status.U ave lot of option to filter the PO status under Status Profile or System status ok.
    Hope this will fullfill your requirement
    Reward point if useful
    Regars
    Jia

  • Intra company STO- MRP element reservations

    Dear All'
    I request your help to resolve following issue.
    I have created Intra company STOs based on different plant's requirements. say PO# 1, 2, 3...100.
    The system is reserving available qty based on POs in sequence. When I process PO# 56 for example, when doing PGI in VL02N, the system is throwing error saying deficit of qty in stock.
    But I can see stock as available in MMBE, but in mD04, mrp elements are created based on POs created earlier.
    But business needs can be, I can process any PO first for delivery and PGI based on urgency.
    Request you help in this regard.
    Best Regards
    Rahul

    Hi Maria,
    Thanks for your quick reply.
    I have checked ATP, that is not activated.
    Best Regards
    Rahul

Maybe you are looking for

  • Can't drag songs to new nano

    This is the second nano in the house. The first gets along great with the computer. We registered the second one and charged it. It synced all the songs from the library and we can play them on the ipod, but on Itunes the songs are not typed in black

  • My email is frozen.  what do i do?

    I tried to get my email and there is one open that I cannot delete or move at all.  The left side column of other emails is frozen as well.  what do i do?

  • Change location of APPLCSF log and out

    Hi , We are on oracle version 11.2.0.2 and Apps version 11.5.2.0 running on Solaris Sparc 64 Bit. We have a new mount point in the system and need to configure the APPLLOG and APPLOUT to that location. Previously it was confiugured to another mount p

  • How to learn ESS / MSS

    Hi I am a webdynpro (Java), I want to learn ESS / MSS, I have read the help.sap.com for ESS and MSS but I am not getting what exactly I will have to do as ESS MSS consultant from scratch. as it is already developed business pacakage. Thanks in advanc

  • Problem with iPhoto 9.2.1 update to a higher version.

    Hi, I have a problem with iPhoto 9.2.1 update to a higher version. I tried to install version 9.2.3 and version 9.2.2 and each time the installer returns the message that must have version 9.1.0. Both the update downloaded from Apple.