Mrp for phantom assembly

Dear Gurus
My main item is a phantom assembly the sales order comes for the phantom assembly only.I have got a multilevel bom for this phantom assembly .The bom of the phantom assembly contains the semifinished item. And the bom of the semifinished item contain raw materials.Now while running MRP I dont want any planned orders to be generated for phantom assembly the system should create planned order for semifinished item and purchase requisition for raw material.How can it be done.
Regards
Sandip Sarkar

Hi,
Check the Planning Stratgy: [Planning with Planning MAterial without MTO|http://help.sap.com/saphelp_erp60_sp/helpdata/en/a2/4e799a927d11d1800f00c04fadcb73/content.htm]..
It seems relevant to you Business..
Phantom will carry altogether different meening..
How will you handle the Stocks??
Regards,
Siva

Similar Messages

  • Unable to View low level items for Phantom Assembly - Order created in APO

    Hi All,
    I am unable to view the sub items when I create planned orders in APO and production orders in ECC. But when the order for the same material is created in ECC, I can see all the sub items. I see that this issue is only for Phantom Assemblies.
    And I cannot say that all the items in the Phantom do not appear, actually some of them do appear in BOM explosion.
    For example:
    Pld Ord is created for A in APO
    Prd Ord for A is created in ECC
    A has B, C and F as requirements
    and  B is phantom
    B has D and F as requirements
    Then my BOM explosion shows
    ..1 B
    ..2 D
    ..1 C
    ..2 D
    ..2 E
    ..1 F (This only gives the quantity required to make A)
    But it should also list how much of F (..2 F) is required to make B.
    Where as it comes up in ECC.
    Do I need to change the material settings for Phantom or is it just the UOM that is creating an issue?

    Hi All,
    I am unable to view the sub items when I create planned orders in APO and production orders in ECC. But when the order for the same material is created in ECC, I can see all the sub items. I see that this issue is only for Phantom Assemblies.
    And I cannot say that all the items in the Phantom do not appear, actually some of them do appear in BOM explosion.
    For example:
    Pld Ord is created for A in APO
    Prd Ord for A is created in ECC
    A has B, C and F as requirements
    and  B is phantom
    B has D and F as requirements
    Then my BOM explosion shows
    ..1 B
    ..2 D
    ..1 C
    ..2 D
    ..2 E
    ..1 F (This only gives the quantity required to make A)
    But it should also list how much of F (..2 F) is required to make B.
    Where as it comes up in ECC.
    Do I need to change the material settings for Phantom or is it just the UOM that is creating an issue?

  • BOMMAT Idoc for Phantom assembly

    I have to send BOM to SAP-ME using BOMMAT Idoc. I would like to know how the Idoc behaves for Phantom assembly.
    For header material A, I have 2 components say B & C. C is a phantom (MRP2-Spl Proc Key=50). And C has a BOM with components D & E.
    Now  I want to generate Idoc for BOM for A. Will the item level segment in Idoc for A will have B &C only or B, D and E. i .e will it skip Phantom component?
    Regards
    Shiju

    Hi,
    Your requirement is not very clear.
    Assuming that you want to create an Idoc say for BOM(phantom assembly), the following are the steps:
    1. Goto WE02 (list of Idocs)
    2. Give FINSTA in Logical Message field then, execute.
    3. Take the reference of any Idoc with status 53 (Green).
    4. Goto WE19 (to create new Idoc with reference)
    5. Give the Existing Idoc no. as selected in Point 3, execute.
    6. Give all the parameters as per your new House Bank.
    7. Click Standard Inbound button and note the Idoc No.
    8. Goto WE02, give the Idoc No. as per Point 7, execute
    9. The status has to be 53, else look for the error log.
    10. Goto BD87 to make corrections in Idoc and execute.
    The above steps are at a high level to kick start the creation of Idocs.
    Cheers
    Chandra

  • Reservations for phantom assembly

    Hi All,
             I have a phantom assembly in a process order, on creation of the process order. Reservations are created for the all the material. Is there a possibility to clear the reservations for a 'phantom assembly' before 'TECO' ?
    Regards,
    PSS

    Yes, reservations gets clear at confirmation when 'clear reservation' is ticked. I have case where reservations for phantom assembly exist even after confirmation with 'clear reservation'.

  • Interchageability for phantom assemblies

    Dear Experts,
    We have finished product A and have generated PPDS PDS for it.
    For PDS of A, one of the several components is Phantom 1, which is a phantom assembly and has components X and Y.
    We want to use interchageability of BOM for Phantom1 with Phantom2. Phantom 2 has components X1 and Y1.
    That means for producing A, either X and Y together can be used or X1 and Y1 together should be picked(if stock is not available for X and Y while for X1 and Y1 stock is available)
    Is there any way we can maintain interchageability / substitution for XY with X1Y1 as a group? Or it is posible to maintain Interchangeability for assemblies Phantom1 and Phantom2 so that BOM will be entirely interchangeable.
    Thanks & Regards,
    Vaibhav

    Mayuresh,
    Generally when a production order is created and if the order has Phantom assemblies, it is suppose to explode the BOM of the phantom assembly and create reservation for its components. Is this not happening?
    Can you please mention how you have defined that material as "Phantom assembly". Hope you have not used any special procurement key at the BOM Item level details to switch off bom explosion.
    Regards,
    Prasobh

  • Phantom Assemblies with component for PDS - SNP.

    Hello,
    Does anyone  have planned a components under phantom assembly?  How can we  explode the BOM in PDS-SNP.
    Is it possible to used PDS for  Phantom Assemblies, what have to check and modify?
    Thanks in advance.
    Dgee

    Dear Dgee,
    please read followings on sap help about phantom assemly and PDS: http://help.sap.com/saphelp_scm50/helpdata/en/40/57454070eb2571e10000000a155106/frameset.htm
    and
    http://help.sap.com/saphelp_scm50/helpdata/en/92/b84d40eae76f13e10000000a1550b0/frameset.htm
    and
    http://help.sap.com/saphelp_scm50/helpdata/en/dc/28c13dd9279710e10000000a114084/frameset.htm
    and
    http://help.sap.com/saphelp_scm50/helpdata/en/4d/01be3d1abbe913e10000000a114084/frameset.htm
    and
    http://help.sap.com/saphelp_scm50/helpdata/en/71/513b407b686913e10000000a1550b0/frameset.htm
    I hope this helps.
    Regards,
    Tibor

  • Phantom assembly quantity change in production order

    Hello experts,
    We are producing 1 type of goods, but for 2 different customers. each of them has their own specification for packaging. as per system it was decided to not create another finished goods partnumber with additional BOM, but instead we created 2 phantom assemblies in 1 BOM. 1 of them is the main (for customer 1), another one is alternative (for customer 2).
    Now the idea was that whenever Purchasing is maintaining materials in production orders they were supposed to switch quantity from main phantom assembly to alternative phantom assembly whenever goods were required for customer 2.
    We quickly tested the possibility of quantity change on our test server, but not entirely. the thing is, that for some reason you can change phantom assembly required quantity only if it's already has required quantity higher than 0. otherwise the item is greyed out and you can't perform any changes in it.Same happens if you simply reduce required quantity of phantom assembly item to 0. once you do so - the item becomes greyed out as well.
    So, the question is - is it some kind of settings in BOM\MMD that prevents user from changing quantities for phantom assemblies (and if it is - where exactly you can change it), or it's something else (like i dunno, maybe user authorization issue or something).
    Any help will be appreciated.
    P.S. - i know that you can still simply remove entire item from production order and put it back with quantities and etc., but that way of work has higher risk of making a mistake.
    BR
    VE

    Dear ,
    Couple of points on this issue which may help you understand the problem  : Bom Explosion With Phantom Assemblies will happen based on the following set up .
    1. You need to maintain the special procurement key-50 for the phantom Assembly
    in the MRP 2 View of the material master
    2. We can override the Phantom Assembly Setting by defining in SPRO --->
    Define Explosion Types so that MRP Creates Procurement Propasals for the
    Phantom Assembly itself.ie We can Swith off the Phantom Assembly Settings.
    This settting need to be defined in the BOM Item details screen in the Basic
    Data Tab Page under MRP Area.
    So check in your Bom whether switch off phantom assembly is defined.Make the Explosion Type-Blank
    3.Run MRP Single Item - Multi level - Transaction MD02 with Planning Mode 2 : 'Re-explode BOM and Routing'. The Phantom Item will now get exploded correctly in the Planned Order.
    4.Check the Validity of the BOM  and planning date
    5.Check the MRP4 set up in FG where you have kept the BOM/Routing selection
    6.Check wether dependent requirement  material master -MRP4 view -MRP  for Depent Requ should be blank .
    Check the above points and come back
    Regards
    JH
    Edited by: Jiaul Haque on Jun 14, 2010 2:15 PM
    Edited by: Jiaul Haque on Jun 14, 2010 2:18 PM

  • Phantom Assembly Reporting Point Backflush - Not able to backflush

    We are unable to generate a backflush of the assembly components of a phantom assembly.  The backflush indicator in the operation have been activated and the components involved are production relevant.
    In the material master, i believe the REM Profile has been set correctly to allow for backflushing of the asseblies.
    Am I overlooking something to have this work properly? 
    Any thoughts are much appreciated!
    Thanks All!

    Dear suntevea,
    Generally Production confirmation is not made for phantom assemblies either in Discrete or REM scenario.
    So once when you do the confirmation for the upper level assembly where this phantom assembly is used
    as a component,then at this point the good's issue(backflush) will be happening for the component's of the
    phantom assembly.
    Eg : Material A is a phantom assembly which is made up of components say B & C.
    Again material A is a component for making another assembly say X,so when you do the backflushing in
    MFBF for material X,you can see the components B & C are getting issued,which means Good's issue will
    be happening for B & C,261 movement.
    I hope you will be clear with the concept.
    Revert back if you need any further assistance.
    Regards
    Mangalraj.S

  • PP - Phantom Assembly Alt Item in BOM not loaded in Planned Order

    Hi all,
    I have a scenario where in my finished product, I have several components organized in Alternate Group, and for each group, I define a component as Prime (100% usage) and others as Alternate (0% utilization). Among these there are some components that are configured as Phantom (Special Procurement 50), and these Phantom items, when they are Alternate in the BOM, ie, 0% Probability of Use in Alternate Item Group, it is not loaded in the list of components in Planned Order. Only the Phantom that is as Prime in BOM is showed in the Planned Order, together with their subcomponents.
    The other components that are not phantom, usually appear within the Planned Order, those that have 100% utilization, and those who have 0% utilization set in the BOM. Obviously, all requirement is pointed in the Prime Item, but I can change according to availability of material in MDVP or manually in CO02.
    When the Production Order is created directly by CO01, without conversion of planned order, the list of components typically brings all the Phantoms, independently of the Probability Use %.
    Someone tell me if there is some kind of configuration to allow the Phantoms Optional also be uploaded to the component list of planned orders without having to change the percentage of use in BOM.
    Thanks in advance.

    Hello MCantos,
    When you have maintained the usage probability as 0% for a alternative component, that means you do not want that partular material to be planned further. In short this is just an Engineering Relevant Material (is not required in Production activity).
    When this alternate material with usage probability 0% is phantom material, you want its components to be proposed. But you yourself have answered that this phantom material has usage probability 0% and this means it is not required in Production and thus its components as well are not required. Thus system is not exploding the BOM and proposing the material at the time of Production activity.
    Hope I answered your query. Please check your usage probability for phantom assembly part and if required correct the same so that you can achive what you want.
    Thanks,
    Rahul.

  • Phantom Assembly Planned Order in APO

    Sub : Incorrect quantity and Bucket for component in scenario of Phantom Assembly
    Hi Gents,
    I am using the Optimizer planning run for a scenario with Phantom assembly.
    The master data has been used below
    Material u2013 862700 (Finished goods)
                    1091895 (Phantom assembly maintained for above FG)
    Location - 8501
    Planning Book - ZAL_SNP_PB_BG
    Data View - ZAL_SNP_DV_BGF
    Optimizer profile - ZAL_OPT_01
    I have entered a demand for above FG on 22.02.2012 and running a optimizer by selecting both FG and Phantom assembly. As a result the optimizer has created the planned order for FG from 18th to 22nd Dec. 2012. The advancement of the planned order is due to production capacity constraint.  When i analysed System has created  planned order for phantom assembly in last two buckets of the planning book and heneceforth  the component requirement it is appearing only on last 2 buckets of the planning book. The date for this dependent demand is 28th and 29th Feb.2012 and the quantity is also wrong for the components as per the BOM.
    The result I am expecting as system should create the planned order and dependent demand for the component maintain below phantom assembly should be same FG planed order date and quantity of component should also give the right requirement as per the BOM.     
    Thanks in advance,
    Regards,
    Rajesh patil

    HI Ipsita,
    Did you try running it form SE38.
    SE38 because in SE37 it is not necessary to give all the parameters..
    But in SE38 you need to pass all the values required & Check form there.
    Also you can check the details in PLAF-Table.
    Thanks & regards,
    Dileep .C

  • Planning at Phantom Assembly Level 59- Mixed MRP

    Dear Gurus/Friends
    For strategy 59 Planning at Phantom Assembly Level
    What Mixed MRP selection we have to make
    1 or 2 or 3
    Prabakaran K

    thanks iam closing the thread
    Prabakaran K

  • Planned order is not creating for a phantom assembly

    Dear experts
    My fert having two semi finished components
    first semifinished is assigned with a raw material
    And second semifinished is assigned with two different raw material
    in material master of second semifinished mrp2 view Special procurement=50
    and after running mrp, second semifinished is not getting any planned order or dep requirement all the raw material under this getting planned order
    But in my understanding of phantom second semifinished in should not get any planned order?
    Am  i correct?
    Pls advise me where i need to check
    Abu Fathiam

    Hi,
    Phantom assembly will generate planned order for its component when you will maintain:
    Procurement type: E
    Special procurement type: 50
    Also in SPRO: OPPQ BOM explosion
    Also check in BOM In basic data tab
    In MRP Data screen, check explosion type- are you maintained phantom assembly off? Check it if you want planned order.
    If you don't want system generated planned order for your phantom assembly component you should not maintain this indicator.
    Regards,
    Alok Tiwari
    Edited by: Alok Kumar Tiwari on Feb 29, 2012 11:38 AM
    Edited by: Alok Kumar Tiwari on Feb 29, 2012 11:39 AM

  • Pull list for the component of the phantom assembly

    Hi
    I am in rem process. while doing the pull list for the fianl product using Entry with bom explosion.
    i did not get the components (level 3)for 1 assembly(level 2 ) which is phantom one under the final product (level 1) BOM.
    i also maintained the production stor loc for the components and the phantom assmy.
    i check the stock in the production storage location . no stock is there in the location.
    what is the problem . how to get the component of the phantom in the pull list.

    Dear Raj,
    If your FERT contains a HALB and inturn this HALB contains say HALB1 which is a phantom assembly
    and and another 2 raw materials means,when you execute MF60 For HALB,you will get the 2 raw
    materials along with the component's of phantom assembly.
    Check and revert back.
    Regards
    Mangalraj.S

  • MRP for Assemblies

    Hi,
    Can any one say what is MRP for Assemblies.

    Hi
    It;s working fine.Take exp.
    If in material master Rounding value is 10 , MRP type VB , Reorder level 100.12,stock 0 then it create PR for 110 nos
    Same is for % scarp .You have to mention deceminal points then it is rounding

  • Phantom assembly

    I want to understand phantom assembly concept..
    I have gone through sdn and find this answer to be understandable..
    Phantom Assembly:
    A logical grouping of materials.
    A phantom assembly is created in engineering to describe a number of components and manage them
    as a whole. The components in a phantom assembly are immediately placed in the superior assembly.
    Components in an assembly are first assembled to produce the header material. Then header material
    is placed in the superior assembly.
    Example
    The phantom assembly "set of wheels" contains the components "front wheel" and "rear wheel." The front and rear wheels are immediately placed in the "bicycle" assembly. The "light" assembly contains the materials "bulb" and "reflector." The light components are first assembled and then the light is attached to the bicycle.
    Settings to be done:
    For configurations settings goto OPPQ for maintaining the values of special.key
    Special procurement key value 50 must be set in the MRP2 view of the material master.
    For the materials for which sp.procurement value 50 is set the system creates the planned orders and
    purchase requisitions for the components of the phantom assembly.
    Regards
    Mangalraj.S
    But can anybody tell me, In the above where should we maintain the sp prc key 50.. In the fron wheel or in the rear wheel...
    Pls explain me..

    Hi,
    "In the above where should we maintain the sp prc key 50.. In the fron wheel or in the rear wheel..."
    For this you need to create an logican assy new mat no in MMR.ex: xxxxx for which components are rear wheel  - Rxxx, front wheel  - Fxxx ..
    Assign 50 in mrp 2 view of assy xxxxx material .
    now this xxxxx material is phantom assy.
    when you run MRP for FG this phantom assy will get explode and dependent req will be created for Rxxx and Fxxx directly with out creating planned order for xxxxx mat..
    come back futher if you have any doubt.
    regards
    vinoth

Maybe you are looking for

  • Image in template background do not appear in browser

    Hello all I run a site ( http://ntp.neuroscience.wisc.edu/ ) that uses templates for backgrounds/spry menus for its pages. We currently use three templates to display backgrounds across the site and up until a few days ago everything displayed fine,

  • How can I send many invoice documents to one customer in SAP B1?

    Hi Now I can send e-mail through sap b1 to customer by using outlook_integration add-on. But I want send many invoices to a customer in one email. Can I do it in sap b1? Thank u Theerawat

  • Looking for form filling app that can do this

    I am looking for an iPad app that can do this. I know it would need some type of cloud/web based backend to setup and manage but I'm looking for the following: We are a fire and security company. Many jobs require multiple documents to be created suc

  • Active Directory replication and login errors (Plz HELP !!)

    Hi All, We have one forest domain (XXXX.LOCAL)and lots of child domains (XXX.XXXX.LOCAL). We are facing issue that child domains are not able to login with forest administrator account and there are also lots of replication errors. Exchange OWA gives

  • Serial number reconcilation

    Dear Gurus, This is a scenario of material issued to contractor. The client receives gas cylinders from the vendor. This is in turn issued to the contractors. At the month end there is reconcilation of the issue/receipts. To map this into SAP, i have