Hi experts,
We run MRP everyday, How it will create plan order or PR?  We hope it could create Plan order first,
but I run MPR md02 and choose parameter as 3 (plan order) , it still come out PR.
what's the scenerios for PR or plan order creation?
Thanks
Alice

hi,
Check your Material master record...
there check for the field "Procurement type" it shd be set for the both ie. external as well as internal....
Here you would have asked for internal one....that's why system is generating PR directly instead of Planned order....
Check n let me know anything else...
Regards
Priyanka.P

Similar Messages

  • Changing MRP controller for planned order

    Hello experts,
    Is there any way the planner could change the MRP controller of a planned order within MD12 ? We are using ver 4.7 and this field is not enabled. Currently the planners are creating prod orders much in advance and are looking to move to a process where they firm planned order. We are using project stock planning structure so more that one planner may create orders for the same material. So when one planner review the material planning for one project he would firm the planned order and assign it to him for leater conversion.
    Note: I the config I didn't saw any field selection control for planned orders.
    Thank you in advance for sharing your wisdom.
    Francois Paquet BPA
    aeronautive industrie

    Francois,
    Very interesting question. However I never had to change those fields in either planned or prodcution orders.
    Both orders master data fileds are disabled.
    However since your are working with project orders ( or netwrok orders ) system would be giving you specific planner order hard tied to the project order ( similar to Made to order scenario).
    Planner could use MD51 ( project planning ) & MD4C ( option for Netwrok or WBS element ) for monitoring progress of his /her order.
    This way planners do not have to go by MRP controller data.
    Hope this provides some new thoughts.
    Thanks,
    Ram

  • Pur req not generated for MRP element Planned order in stock reqmnts list

    Hi SAP Gurus,
    I have a problem where in MD04, pur req is not generated for the MRP element Planned order for a future date (about two months from now). Is there a specific reason? why is it not being generated? The MRP type is PD. The procurement type is F - external procurement. Can anybody please help me on this?
    Thanks
    Anusha

    Anusha,
    ??  Not sure I understand the question.  Are you saying MRP is creating planned orders instead of  purchase reqs?  Or, are you saying that no proposals at all are being created outside of two months?  Or, are you saying that the system is creating purchase reqs inside of two months, and planned orders outside of two months?
    Regardless, these problems are probably related to your MRP settings.  Try the following settings:
    NEUPL   Regenerative planning             
    1       Purchase requisitions             
    3       Schedule lines                    
    1       MRP list                          
    3       Delete and recreate planning data 
    2       Lead time scheduling and capacity planning
    on your MDBT screen.
    Regards,
    DB49

  • User exit/ badi needed for planned order create/change,collective ATP check

    Dear All,
    I'm looking for a user exit/ badi which can be used for planned orders at the stage of
    mass collective availability check (COMAC tcode) update; or at some other relevant stages of mass update of planned orders.
    I need after collective availability check to perform the following:
    1) to copy date from "total comitment" field on header tab of planned order and paste it (replace old date) to order finish date on header screen
    then
    2) to start a scheduling.
    Very appreciate your help.
    Best Regards,
    Andrey
    Edited by: Andrey Kruglov on Apr 15, 2010 3:06 PM
    Edited by: Andrey Kruglov on Apr 15, 2010 3:07 PM

    Dear,
    Use the BAPI : BAPI_PLANNEDORDER_CHANGE
    Or use the function module MD_SET_ACTION_PLAF for Schedule planned order.
    and the transaction MDAC Execute action for planned order
    This function module includes the following actions:
    Explode BOM
    Explode BOM, check availability
    Check availability, only explode BOM in the case of a requirement
    Check availability, do not explode BOM
    Reset availability
    Change planned order data
    Schedule planned order
    Delete planned order
    Assign the key for the respective action control to the materials in the material master (MRP 4 view).
    Please refer this thread,
    Re: MDVP for collective orders
    Regards,
    R.Brahmankar

  • Creation of Reservation for planned order

    Hi Team,
    Is it possible to create reservation for planned orders after MRP run?
    My opinion was the reservation can only be created with reference to production order after MRP. The reservation can not be created with reference to planne dorders after MRP run because planned orders are intermident document which will not exist in the system always. The planned order details will not be available in the system once it get converted into production order.
    How the reservation will be processed which was created with reference to planned order after converting the planned order to production order?
    Kindly need ur guidance.
    Thanks
    psk

    Dear PSK,
    In a typical discrete manufacturing setup production orders are the promised receipt for which reservations gets generated as
    soon a production order is created.But only if the order is released goods movements can be posted against the reservation
    details through MIGO/MB1A for 261 movement.
    It's not required to create any reservation at the planned order level or which may not help you in any means to your business.
    But however in a REM scenario MF60 is used to create stock transfer reservations for 311 movement where planned orders
    are used for production backflush.To explain in detail even without any planned orders you can do a stock transfer reservation
    for a production quantity.
    Check and revert back.
    Regards
    Mangalraj.S

  • Sufficient stock but MRP create planned order and purchase requisition .

    Hi Expert,
    After MRP run planned order and purchase requisition created . but the problem is for child material sufficient is there but still PR and plnd order is created .
    MRP type PD, LOT size EX,Strategy group 10, for testing purpose I made safety stock 0, min lot size 0 , max lot size 0.
    I cant find the cause why MRP create PR and Pland order for the material which has sufficient stock. Please help.

    Dear Anirban
    could you check the following master data value:
    Lot size -> MB Monthly ( only for test)
    Rounding value -> null
    Strategy 40 MTS.
    You can try with this setting in order to figure out what is the problem.
    You can check also orizzon planning and re-scheduling (set to 999).
    Let me know if i have been useful for you
    Daniele

  • Using MD50 to run MRP for Sale Order

    Dear all,
    I have some problem when using MD50 with Mill Product Industry.
    When SAP system not activate Mill Product yet. I used transaction code MD50 to run MRP for Sale Order, the system have generated planned order for multilevel. But when SAP system have activated Mill Product, I used transaction code MD50 to run MRP for Sale Order, the system only generate planned order for single level. I think that we have to configure something based on Mill Product Industry. So can you help me for this
    Thanks, Regards

    Hi,
    Check with following links which may help you resolve your issue :
    http://www.sap.com/sme/whysap/industries/millproducts/index.epx
    http://help.sap.com/saphelp_di471/helpdata/en/4e/1796374b088e5ce10000009b38f8cf/frameset.htm
    http://help.sap.com/content/documentation/industry/docu_is_mill.htm
    Regards,
    Tejas

  • Multiple number range for planned order

    Hi,
    I want maintain different number range for MRP related planned order and manual creation planned orders. I have checked OPPQ and OMI2 transaction but i could not get any clue to create different number range for same plant. Let me know is how we can create.
    Regards / US

    Hi Uma,
    number range is dependent on plant alone and I don't think there is an user exit or badi to change number range at planned order creation.
    I guess the alternative is an enhancement or using some other field to determine what planned orders are manual.
    regards,
    Edgar

  • Run MRP for production order/maintenance order has been release

    Hi all,
    please tell me how to configure for running mrp for production order/maintenance order has been release. as you know, i want production order has not release will not appear in MD04. I think that is the way for running mrp will not take care about this production order has not release
    Thanks all

    Hi Hoai,
    It is impossible to exclude production order from net requirement calculation in MRP run. You may take a look at the online documentation under the PP-MRP area.
    Material Requirements Planning (PP-MRP)
       Planning Process
         Net Requirements Calculation
           Net Requirements Calculation for MRP
    But there is a way to temporarily exclude production order from MRP. That is you can set the 'delivery completed' indicator in 'Goods receipt' Tab in in production order. Please note that this order will not appear in MD04. Actually to some degree, this order could be considered as completed because ticking the indicator could set status 'DLV' for the order. But you still can execute confirmation, goods issue and goods receipt activities. This way is just a workaround. You may
    consider it.
    Or maybe you can consider the useage of BADI: MD_CHANGE_MRP_DATA to change the MRP run data to see if this could fulfill your requirement.
    Regards,
    Rachel

  • Table For Planned Order Details From PP Module

    In our organisation we are taking Plan Vs Acheivement from Production. So, intialy we taken Plan details from "PLAF" Table and Acheivement details from "S225" Table. But After running MRP at month end. Previous month plan get deleted and new order create.
    how to get history data for Planned order.
    Please help us.
    Regards
    Naga

    I don't think that there is any history in regard to planned orders.  PLAF will get rebuilt according to your MRP parameters and I don't believe that the data is stored.
    Regards,
    Rich Heilman

  • Costing affect with MRP at planned order level and after production order

    Dear all,
    How the costing affect with MRP at planned order level and after production order completion?
    Edited by: Maulik on Jun 24, 2009 1:59 PM

    Dear Maulik,
    check Mr. Vinod's inputs abt costing
    1. Maintain following master data:
    MM01 Material Master with Costing and accounting view. Make sure all the cost Std, Moving avg etc is maintained along with valuation class in Accounting view 1. In costing tab pls make sure "with qty structure" and "Material Origin" are ticked.
    CS01 BOM with components marked with costing relevance in Status/Long Text Tab. Also check all the qty are correct.
    CR01 Work Center in Basic data tab maintain standard value key sau SAP1 and in costing tab maintain the workcenter, activity type and formulas (Usually standard formulas like for Machine Hours SAP006, Labour SAP007, Setup Activity SAP005 is used).
    KL01 Cretae activity types, in basic data tab maintain ATyp Category AS "1" and cost element (as provided by your FI Guy).
    KP26 Activity pricing, here with the combination of Activity type and the cost center you assign price to the activity.
    2. SPRO Activity
    Maintain Costing sheet IMGControllingProd cost controllingProd Cost PlanningBasic settingoverheadsdefine costing sheet.
    OKKN Define costing variant, you define costing type (In the costing type, you define the purpose of a material cost estimate by specifying, for example, which field in the material master record the costing results can be transferred to like std price, moving avg etc), Valuation Variant (defines how the prices are prioratized), date control and transfer structure.
    3. Costing Process Flow:
    1. CK11N CREATE COSTING RUN
    2. CK24 CREATE PRICE UPDATE (You Mark and release the prce to be updated)
    4. COSTING VARIANT WRT PP
    1. OPL1 DEFINE COSTING VARIANT WRT PP
    2. OKK4 or OPN2 DEFINE VALUATION VARIANT
    3. OKK1 or OPM1 DEFINE COSTING TYPE
    4. OPL8 ORDERTYPE DEPENDENT PARAMETER (assign the above creted costing type for both planned and actual)
    Hope this will throw some light on product costing.
    Regards
    kumar

  • Release status for planned order

    Hi All
          I am running MRP weekly,system is generating the Planned order  once MRP is completed.Here my requirement is i want release status for planned order, at the same time once planned order is released i dont want user to change any data in planned order.
           Somebody explain me about the settings of action control of planned order.
    Regards
    Srinivasan.P

    Hi,
    Sorry to say but there is nothing like system status for Planned orders.
    Check below thread,
    [Release of Plan orders|Planned Order Release]
    Regards,
    Dhaval

  • Scheduling for planned order

    When I choose leadtime scheduling in MRP RUN then system does forward scheduling always.
    Then in planned order change mode when i do manually do scheduling then it does backward scheduling as  per settings in OPU5.
    How to get backward scheduling in MRP.??

    Dear,
    MRP do the backwordscheduling but The system always determines the basic dates for planned orders using backward scheduling.
    The system automatically switches to forward scheduling if the determined start date lies in the past.For this you have to maintain 2 settings.
    1)In OPPQ - Plant parameters maintain the indicator for start date in the past allow. 2) In OPU3 for your plant & order type , maintain the no. of days for start date in the past.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • ATP Rule for Planned Orders

    Hi Experts,
    I have configured the ATP rule for Planned Orders. So I only want to check the component stock and Production Orders when running ATP check for the Parent Material.
    In OPJJ, I only selected the following options.
    Include Safety Stock : Ticked
    Check without RLT : Ticked
    Incl.production orders : X (Take all production Orders into account)
    No other options or boxes have been selected
    Also I have included the relevant Checking group in MRP 3 for the Parent Material (Checking Rule has been assigned to that Checking Group in Config) and also maintain the Plant Parameters for MRP (assign the checking rule to the plant)
    So, For an example :
    Parent : A
    Components : B and C
    Parent Material A has only 5 Planned Orders starting on same day 20.05.2014 each qty 5
    Components B got stock 300
    Components C got stock 1
    When I ran ATP Check for the Parent material A using COHV, qty 1 has been allocated to all the planned orders as committed. Why is this happening ?
    I also checked in CO09 for the Component Material C, and it says ATP Qty is only 1. I expected the system would allocate that stock 1 to one of the Orders but it seems to be not working as I expect.
    Any explanations will be much appreciated and will not hesitate to avoid the points.
    Kind regards,
    Ishara

    Hi DB49,
    Appreciate your reply. Please see the following comments.
    Right now I have been assuming that you have performed an availability check manually for one of the planned orders, and you got the same results (overconfirmation).  Please confirm.
    Yeah I have performed for one order and it gave me the same result.  Also, when I perform for the 2nd Order, it allocates the quantity.
    OK, basic things you should already have checked:
    You have maintained the checking rule for planned orders (OPPQ or OPPR)
    You have maintained the ATP group for the materials (OVZ2)
    You have assigned the ATP group to the Material Master of the components (MM02)
    You have maintained the scope of check according to the rules you mentioned earlier (OPPJ).
    You have no planning strategy in the component material that would have invoked a special ATP.
    I checked everything apart from point 2 (OVZ2). I have maintained that via MRP Group and that MRP Group has been linked to Master Data (MRP 3)
    Really appreciate your support in this.
    Kind regards,
    Ishara

  • Where we enter raw material reservation qnty for planned order in monthwise

    sir,
    as per client requirement in every month raw material reservation quantity fixed for planned order in monthwise.
    in sap Where we entere raw material reservation   for planned order in month wise nov, dec, jan and whre its show.
    is it possible after mrp run.can we check that raw material reserve stock in mmbe for planned order.
    pl guide me step by step

    Dear Prakash,
    1) in MMBE, you cannot see Reserved qty against plan order ( it is not a confirmed receipt )
    2) the reserved qty which is shown in MMBE is against production order
    3) only after converting plan order to production order ( Header material )
    4) dependent requirements will convert into reservations
    Regards
    kumar

Maybe you are looking for

  • Safari 1.3.2 plus OSX10.3.9 plus Norton Firewall 3.0, does it work?

    Safari 1.3.2 + OSX 10.3.9 + Norton Firewall 3.0 = no Safari, no IE. Help! I am connected to internet with AOL on Verizon DSL with Norton Firewall enabled. I can browse with AOL only. Problem: cannot use Safari browser, get the following error msg: Sa

  • Calculation in COPA

    Hi Friends, Is there a way I can do a calculation based on a formula in COPA? I know we can use key figure for this purpose but my scenario is we have a sales discount posted to one customer and it needs to be distributed to the customers based on th

  • Phish in Adobe acrobat's name?

    Received this email but my acrobat is up to date.  Is this a phish? Action Required : Upgrade New Adobe Acrobat Reader 2011 For Windows And Mac From: Adobe <[email protected]> Add to Contacts To: @@hidden@@ ADOBE PDF READER SOFTWARE UPGRADE NOTIFICAT

  • Itunes wont detect iphone 4s

    just bought iphone 4s, itunes wont detect it preventing sync

  • Creating Workspace administrator from apllication

    Hi There, I can currently create new end users from a page in my application. This works successfully, although I would like them to be created as workspace administrators and I do not know how to do it. Is there anyone who can help me here? The code