MRP Forecasting Run

Hi Gurus,
Need your expert advice on one of our issues.
We have a requirement that AMC should be taken for the past 6 months regardless if there is any usage or not. Standard behaviour is that during MRP Forecasting run, zero values in the earlier historical values are not taken into account.
For instance forecast period is set to '6' however, only last period has a value of 19.17 and others are zero in the historical data.
When we execute the forecast run system actually considers as 1 month even if we defined 6 month.
If standard SAP doesn't  cater for the above,  is there a  way to twig the system to achieve the above objective? If yes, how can this address the zero usage and can it be restricted for a specific group of users?
Thanks.
J&J

Dear Poster
You have created a thread in the SRM (Supplier Relationship Management) area, is this correct? The issue reported seems like it should belong to an ERP or similar forum? Let us know of this issue refers at all to SMR_SERVER and we can proceed with assistance otherwise I will move your thread to a  more suitable forum if SRM is not your issue!
Regards,
Jason

Similar Messages

  • Interested in bringing Past Due forecast from MRP Forecast Sets to ASCP

    We are on 12.1.3 (EBS and ASCP) and are interested in bringing a week of past due forecast from MRP Forecast set into ASCP. We are running EDD plan.
    Following have been enabled but no luck yet, open to suggestions or explanations.
    1. Include Past Due Forecast = 5
    2. Spread Forecast Evenly = checked (as we are in weekly buckets)
    3. Demand Time Fence control = checked on plan options
    4. Item are enabled for Demand Time Fence days = 0
    5. Complete Collections and Plan have been ran.
    Observation - Since the week start date is on Monday, when the plan ran from Tuesday, it brings the forecast for current week from Tuesday of that week onwards breaking into days. But it doesn't bring in forecast for Monday or prior week days.
    Per ASCP guide, Include Past Due Forecast is useful only in case of Oracle Demand Planning.
    Any help in this regards is appreciated.
    Thanks in advance.

    Hi,  
    This is the Advanced Collections Financial community.  I believe you are looking for a Manufacturing community.  
    Thank you
    Christine Williams
    Oracle Support,  Global Advanced Collections SME
    -----If my response assisted you on this matter, please feel free to click on the Correct Answer button, or Like the response.

  • MD21 and MRP forecasting

    Hello,
    I am running MRP(forecast based) and found that system does make changes in planning file(MD21),
    if there are changes made in GR/GI, scrap, Materials master and PO  etc.
    But does not make change, if these changes are in Sales order, new sales order, creation delivery and picked by TO/WM etc...
    My understanding is that if new sales  order created/deliveries changed, if should add made the entry in MD21 as all these changes and run with MRP as these are recorded in MD04.
    Other thing is: Processing Indicator, after making PGI, it did not reset the indicator. I have checked fully may be qty was smal l!!
    Please suggest.
    Regards,
    JPS

    Hello
    Please try to provide more details when opening a thread, so that people can understand exactly what is your problem.
    I have searched for a functionality called "Interactive Graphics" and the only reference that I found was on Sales and Operations Planning (PP-SOP):
    Sales & Operations Planning (LO-LIS-PLN) - SAP Library
    Are these the same interactive graphics refered on your thread? If this is the case, there is no such functionality on MRP.
    BR
    Caetano

  • MRP run details(date and time when MRP was run)

    Hello,
    I need time stamps of all MRP/MPS run for a particular material. Please let me know relevant T.code/FM/BADI.

    Dear
    One more way to find this is using Transection Code AUT10.
    Here you can find not only Last MRP date but some other useful data also like user, date ,time and so many.
    Try it by using T.Code like MD01, MD02, MD40 etc.
    Or goto se16-SAP Table MDKP-Here you will get MRP run details
    Hope this helps
    Regards
    JH

  • Forecast run MP30 be to disabled for future

    One of the user has by mistake made a forecast run at a plant level (T code : MP30)leading to forecast view added to the materials in the plant. This leads to Unplanned Requirements appearing in the Stock requirement List.
    How do we reverse these changes. Can we switch off Forecast related requirement for the plant via. some T code? If we delete the forecast from MM, these quantity disappear from MD04 but it seems this is not sufficient.
    Also, how can we figure out who made this run ? These changes are not recorded in the MM and there is no trace of who did it ?

    Ravi,
    I believe that you have misread the events.  I don't believe MP30 can be run until the forecast view in the MM has first been maintained.
    If you wish to know who created the forecasting view of the MM, you can look in MM history for an MM01 entry.  I don't believe that MP30 can create this view.
    Forecasts by themselves do not normally create unplanned issues, they must be released to demand planning, where they create PIRs.  I suspect you may have some automatic jobs that are performing this task behind the scenes.
    If you wish to deactivate the forecast, go to MM02, forecast tab.  Select forecast model zero, save.  existing forecasts and relevant data will be deleted.  Then, delete any PIRs that you don't want. 
    Rgds,
    DB49

  • Bacground Forecast Run - Error - data that is currently locked

    Dear All,
                  I am scheduling the Forecasting Job in Background on daily basis , sometime in logs i get the below ERROR...
    " Selection accesses data is currently locked"
    Can any body help me...
    what are the possible reasons? i mean except the User is working in the planning book?
    Suppose if the only reason  (User is in the planning book)  then how can we avoid this error??
    Is there any way  , if the user is in the planning book .then also we can avoid this error!
    Plz help
    Regards,
    Rajesh

    Hi Rajesh,
    Check the lock using transaction sm12
    You can control the users by locking/unlocking during forecast run
    using transaction su10
    Regards
    R. Senthil Mareeswaran.

  • MRP Forecast Interface

    Hi all,
    I am doing MRP forecast interface. I got  MRP_FORECAST_INTERFACE_PK API  for MRP forecast interface.
    but i do't no this is correct or not.
    Please tell me how to use this API .
    if u have any previous code provide me.

    Please refer MOS note:
    MRCRLF - The Planning Manager is not Loading Rows From MRP_FORECAST_INTERFACE [ID 183304.1]
    MRCRLF - Does Not Pick Up Records in MRP_FORECAST_INTERFACE [ID 180138.1]
    regards,

  • MRP not running with MD01

    Hi Gurus,
    My client has a problem, MRP is running OK with MD02 and MD03 tansactions but no materials are planned when MRP is run through MD01at plant level.
    Can anybody throw some light what could be the problem?
    There is no error message either.
    Thanks in advance
    Shailesh

    Dear PP and QM
    I think there is a misunderstanding
    The reason why the materials are getting planned via MD02/MD03 is because here you are forcefully running the MRP for the material,System wont look for the planning file entry where as when run through MD01 system will check for planning file entry
    Just though to explain the reason behind such behavious, there is no intention to prove you wrong
    Shailesh
    Proceed as suggested by other expert,Even i feel that planning entry might be missing
    I'm not sure how the materials were uploaded in the system,if it is via BDC then you normally one setting is there(update planning file) if it is not done then planning file entry will not get created ,we have to create it manually
    Hope this helps !!
    Thanks
    SVP

  • MRP is running in MD03 and not in MD03

    Hi all
    The MRP is running well in our MD03 T code, but same time we cant do the same in MD01. Let me have the reason.
    Basically we have the user exit parameters is implemented, this is running well in our other plant. There is no authorisation message about this. Totally we are searching for scrap

    Thenna,
    MDAB will indeed create new Planning file entries en masse.
    In addition, it is always a good idea to periodically run MDRE to repair any inconsistancies in the planning file.
    Some companies run these two programs in batch regularly, say every week or so.
    Rgds,
    DB49

  • MRP is running daily but not in MDBT

    Dear Guru,
    In my system, MRP is running daily but I am not able to find out in MDBT. Is there any othe way for automatic mrp run? Please reply.
    Thanks in advance.....
    Regards,
    Raj.

    Hi,
    2 things you can do:
    1. Ask your system admin or basis consultant
    2. Go to SM37, specify
    for Job name & user name. Set the job status as finished, specify the date interval say today until a week ago & in the Abap program specify RMMRP000 & execute. The output will list all MRP jobs defined & this should clarify.
    Regards,
    Vivek

  • Generate Delivery Schedules via MRP Planning run

    The company wants to create Scheduling Agreements and generate the Delivery Schedules from the MRP Planning run - MRP 2 view via JIT.
    Can you generate Delivery Schedules from Schedule Agreements if the company does not have an EDI server or APO set up?
    Thanks,

    Shirley Globe,
    You seem to be putting the experts to the test.
    As it was told you, you can generate schedule lines via MRP run. MRP run can be done (e.g.) trough MD01 /MD02 / MD03. Of course, you have to use the proper selection parameters to achieve your goal.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
    As for how to use SA with MRP please check SAP online help:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/3b/66596eda7b11d1b6330000e8a738dc/frameset.htm
    Regards,
    Csaba
    Edited by: Csaba Szommer on Apr 9, 2009 7:40 PM

  • MRP- Forecast

    Hi All Expert,
    I am using SAP 2007 B PL04 my question is :
    When we are ruunning MRP we are considering following document:
    1)  Purchase Order
    2)  Production Order
    3)  Sales Order
    4)  Forecast
    On the Second Run if we left some Purchase order/ Production Order from the order recommadation report
    The MRP wizard will not pick up the data from the order recommadation report. Is  there any way to consider Last forecast or the Purchase order/Production Order in the  fresh MRP Run.
    Ashish Gupte

    Hi Marcella
    When we Run MRP thru some forecast we will get result and we save the Order Rec. Report. From the order rec. Report we can generate the purchase order and the production order. But the scenario is suppose if we cannot generate the Purchase order and the production order from the order recom. report. It lies in that report.
    Second time when we Run the MRP i want to consider that pending purchase order and the production order which lies in the earlier order recm. report.
    Is this possible thru some development or other way. Pls suggest.
    Ashish Gupte

  • MRP/Forecast Profiles - Program RMMM0001

    Hi,
    anyone out there knows how to turn off the program RMMM0001? It will run whenever a MRP or Forecast Profile is changed or Deleted.
    In addition, can this auto-schedule be configured? That is, only run whenever change is done (even default value change) and no run if profile is deleted.
    Regards,
    Norman

    ??

  • MRP planning run

    Hi experts,
                 During MRP run for  a material ,  open PO quantity is not considered   If  delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.  
                 What could be the reason for it? Pls help me out.
    Thanks in advance,
    Rgds,
    jay

    The Planning Horizon entry for your plant must be 110 or more. Check it out in OMI8. Click on the 'Maintain' button after entering ur plant, click on 'Planning Horizon' to see the entry.
    For open PO qty to be considered, try running MRP run with processing key as 'NETCH' in MD02 or whichever t-code u use this doesn't take planning horizon into account.
    Amit G

  • To generate Schedule lines for scheduling Agreement when MRP is run.

    Hi,
    Please help advise on my following requirement:
    When I run the MRP for 'Single Item - Multi level' (MD02) for a material, I want MRP to generate delivery schedule lines for that material in Scheduling agreement.
    Please advise as to how i can go about with this.
    Regards,
    Manju

    Hi Manju,
    For this you need to set creation indoactor for planning run in SPRO.
    The path is spro-MM-CBP-Carry out overall maintenance of plant parameters-Click on maintain-give your plant-click on external procurement under planning run-here you can give your option for the schedule line creation.
    Traction code is omi8. Hope this will help you.
    Cheers
    Ravi