Mrp list

When i run mrp MD01 and select option display list. Then inside list iam getting selection groups beside material number.
This groups are numbered 1,2,3,4,5,6,7,8
What is meaning of this numbers ?

Mayuresh,
These are basically MRP- Exception messages grouped together in 8 groups. You can check the details of this in SPRO->Production Planning->MRP-Evaluations-> Define and Group Exception messages(To know how they are grouped) or Check exception group texts(To know the details below).
1     New; opening date in the past
2     New; start date in the past
3     New; finish date in the past
4     General messages
5     Exception during BOM explosion
6     Exception during availability check
7     Exception during rescheduling
8     Terminations
Hope this helps...
Regards,
Prasobh

Similar Messages

  • Time stamp in MRP list after MRP Run

    Hi Gurus
    After running a MD01-MRP at scope of planning level, with processing key as NETCH, materials which had no planning file entry also were updated with the latest executed MRP run time stamp in MRP List MD05.
    Is it the standard behaviour? As per my understanding, the materials with no planning file relevant change is not included in the MRP run with processing key NETCH/NETPL. Then how does the time stamp be relevant for the latest MRP run while the material was never included in the mrp itself?
    Regards
    Deepak Prasanna S

    Dear Deepak,
    If my understanding is correct only if a mterial is included in the last MRP run(MD01/MDBT) then the time stamp gets included in the
    MRP list which can be checked and confirmed through MD05 and also the output of last MRP run.
    Once after the MRP run is completed the system deletes the corresponding planning file entries in the system.
    On completion of the planning run, the appropriate indicator is automatically deleted in the planning file:
    The system deletes the net change planning indicator and the net change planning horizon indicator for a regenerative planning
    run and a net change planning run.
    The system only deletes the net change planning horizon indicator for a net change planning run in the planning horizon.
    Check and revert back.
    Regards
    Mangalraj.S

  • Report for MRP list(MD05/MD06)

    Hello,
    I am looking for a Report that can give me the details of the MRP list(MD05 or MD06).
    Basically I need the report to give me the following details.
    Material Number
    Material Description
    Date
    Opening Date
    Rec/Reqd qty
    MRP element
    If you see all these fields are coming from the MRP list(MD06)
    Is there a standard report or table that can give me this information.
    Let me know
    Thanks
    SAP Fans....

    Hi,
    Please check this link for the desired tables / structures:
    Re: Tables in MD04 list
    Regards,
    Csaba
    PS
    http://www.sap-topjobs.com/SAPTABLEREF%5B1%5D.doc
    Edited by: Csaba Szommer on Nov 17, 2008 5:07 PM

  • Report on MRP List

    Kindly suggest me if any standard report is available in which I can get the requirement of MRP ( Plant / Porg wise ) without considering the Open PO and stocks

    hi
    U can use MD04 or MD06  for reports on MRP list
    Vishal..

  • Report RMMD07EX for collective MRP list

    Hi all
    I want to use the collective MRP list MD04 but by defining a range of plants and multiple MRP controllers at a time. SAP recommends using a report similar to RMMD07EX. This mimics MD07. Has anybody created a report for collective MRP list using MD04
    thanks

    How do you plan to switch from collective display to individual ? DO you plan to agregate some figures like stock for differents materials?
    Have you tried the LIS, with transactions like MCBZ? This is collective Stock/ Reqmts List !

  • MRP list issue

    Hello,
    I am having issues when I run MD05 MRP list for a material. It gives me the below error.
    "No MRP list exists"
    This is a material just extended to a new plant with no stock. Is this issue because there is no stock for it and/or because its a newly extended material?
    Same material in a different plant does give me the MRP list view when I run MD05.
    let me know how it works.
    Thanks
    SAP Fans...

    Have you had an MRP run after the creation of this material?
    If not, then it is obvious that an old MRP run does not know anything about a material created after this event.

  • MRP List issue(MD05)

    Hello,
    I am having issues when I run MD05 MRP list for a material. It gives me the below error.
    "No MRP list exists"
    This is a material just extended to a new plant with no stock. Is this issue because there is no stock for it and/or because its a newly extended material?
    Same material in a different plant does give me the MRP list view when I run MD05.
    let me know how it works.
    Thanks
    SAP Fans...

    Dhaval and All,
    Thanks for the Response. I want to confirm one thing.
    "MD05 is for displaying MRP Result.Once you run MRP for that material then only you will find the result in it unless you will find that " NO MRP list exists" message."
    The above statement you made (no MRP list exists) is true only in the case of a newly created/extended material for which MRP was never run.
    For material which already exists it would still show data in the MRP list from the last MRP run. Isnt it?
    Let me know
    Thanks
    SAP Fans....

  • MRP Date in MRP List

    Hello All,
    While accessing the MRP List (collective access MD06). There is a selection option for MRP Date. SAP Help tells that "Date: for example, all MRP lists that were created or processed within the last two weeks".
    But I could not understand what this means. Please clarify this.
    Regards
    Mahesh

    Hi
    It means that, the MRP list will be displayed only for those materials that were created in that time frame. There might be materials for which MRP is not run and processed within that time frame. they will not be displayed. This is one of the parameters for filtering the list.
    Hope this is clear and helpful. If so please reward
    Chandra

  • Resolve error msg 26 In the Mrp list

    Dear Gm,
    How to resolve the below Error in the MRP list
    26 Excess in Individual segment
    Regards
    Arun kumar K

    hi
    always post the error message number to provide solution for the errors in quick manner

  • Different Exception messages in MRP list & Stock Requirement List

    Hello Experts,
    When I run MRP and then look at the stock Requirement List & MRP list for the same material, I see different exception messages in these list.
    I noticed that any of the exception messages in Exception group "7 - Exception during rescheduling" (ie, 10-reschedule in; 15-Reschedule Out; 20-cancel process; 30-plan process according to schedule) is not appearing in the stock requirement list even though they appear in the MRP list.
    Does any configuration affect what message group can appear in Stock Requirement List & MRP list?
    Please advice.
    Regards
    Tom

    Hi Tom,
    For exception message - 62, just do the below checks -
    Some of the reasons as to why you may find this exception message is because the backward scheduling can drive the start date in the past so far that:
    - there is no valid BOM as of that date
    - one or more of the work centers are not valid on that date
    - there is no valid factory calendar on that date
    Check the scheduling formulas in your work centers that are set up, and/or to specify for the material master a fixed lot or a max lot size so that planned orders result with realistic lot sizes.
    Also you can set up MRP to only run on basic dates for your overall run, and to follow up with an MRP run which generates capacity planning only within the planning horizon, such as NETPL.  You would need to configure the planning horizon so that it specifies a time frame over which capacity planning is to be done.
    Also check the note : 88505 - Planned order upload generates exception message 62
    In short, do a thorough check of the parameters maintained to ensure there is no inconsistency in the master data.
    Check & revert.
    Regards,
    Vivek

  • MD05- MRP LIst

    Dear All,
    I am facing a unique problem in Trx MD05. Actually I run MRP through MDBT Trx on 01.07.09 but in MRP list (MD05) It is showing MRP list as of 03.07.09. How this can be possible?
    Please share your views on this
    Thanks & Regards
    Kundan Kumar

    Hi Kundan,
    STAD to trace combination of User and Tcode, but particular material its diffcult to trace in std sap.
    If you want to trace then you need do some enhancements, create customized table (mateial number, plant, date, time, etc) for when user run the mrp in MD02 then save all data's to your own table.
    I hope this will help to you
    Regards,
    Sankaran

  • Tables in MRP list??

    Hi Experts,
    I need help to identify the tables from which the data is fetched when we run the MRP list transaction (MD05).
    I need the tables from which the 'Request/Scheduled Qty' and 'Request scheduled date' are fetched.
    My assumption is that the other datas like the MRP date is from the table 'MDKP-DSDAT' correct me if i am wrong.
    Thanks,
    Manju

    Hi Manju,
    please check the below tables.
    MDFD                           MRP firming date
    MDFDDB                         Firming Data of MRP - MRP Area
    MDHS                           Cluster Table BOMs Explosion (Shared Buffe
    MDIP                           Material: MRP Profiles (Field Contents)
    MDK_INVENTORY                  MDK Inventory Example - Data Table
    MDKP                           Header Data for MRP Document
    MDKPDB                         Header Data for MRP Document
    MDLG                           Customizing: MRP Area Storage Location
    MDLL                           Customizing: MRP Area Subcontractor
    MDLV                           Customizing MRP Area
    MDLW                           Customizing: MRP Area Plants
    Award points if useful.

  • MRP List dispalys Old closed sales order

    All,
             After run MRP,stock and requirment list and  MRP list displaying completed.closed sales order also.Please give suggestion how to rectify this issue.

    hi pl check wether the sales order stock has deliverd or not.
    i mean wheter it has done PGI for SO
    -ashok

  • MRP list - Exception 30

    Hello All,
    In MRP List a schedule line is created with exception message 30. what does it mean?
    (MRP type is P1 for the material).
    There are requirements (for ex in 03.04.2008), but it is planned only on 05.05.2008 with rescheduling date 31.03.20008
    ( where as  planning time fence ends on 08.02.2008 itself.)
    what does the rescheduling date means?
    thanks in advance.
    ranjit

    Hi,
    when Mrp type is P1 then it is mps run ,and it will take the planning time fence that you  have mentioned in material master record ,in that period whatever requirements are there those it will plan by considering the dates and it will make them as firm with the firming indicatodr as *
    for those planned order only mrp controller is allowed to chage the planning values and no one can change those ,system automatically not going to change those firming indicator planned orders.
    reward points if useful.

  • MRP list: collective requirements (MD06) in the background mode

    Hi Friends,
    We have requirement to run MRP list: collective requirements (MD06) in the background mode per MRP controller. Is there any way we can run MD06 in the background?
    Appreciate your response.
    Thanks,
    Srinivas

    Dear Srinivas
    if you need to run planning as a background job please try t-code MDBT;
    as far as i know you can't run MD06 as a backgroun job.
    you could ask your abaper to create a custom program based on functional module MD_MRP_LIST_OVERVIEW
    after that you will set up this custom code as a background job.
    good luck!

  • MRP list MD05 not displyaing results where as MD04 displays results

    Dear Experts,
    We have a peculiar problem in SAP, MRP list MD05 not displyaing results where as MD04 displays results.
    Please suggest me how to find out the error and what could be the reasons.

    Dear Kannaiyan.
    MD05 displays the results of the last MRP run,where in you will be able to see the stock,requirements and receipts that was
    available during the output of MRP.It's a static one and changes after every MRP run.
    MD04 - stock/requirements list displays the newly created requirements,stock on that time.It's dynamic one.
    Regards
    S Mangalraj

Maybe you are looking for

  • BW Web reporting failed

    Hi, I have a one huge BW report and it can be accessed in BEX .However, when i try to execute the same report in Web, there is error message 'An error has occured.Restart'. i have checked in ST22 and notice there is abap dump. Abap Dump : Unable to f

  • How do I print images from Aperture to the Canon MG6150?

    I have recently installed (i think correctly) a Canon MG6150 printer on my iMac but am having difficulty making it work correctly when photo printing (the wireless connection seems OK).  When printing from Aperture I can cause a print to be made but

  • App Store does not acknowledge installed software

    Hi, I was wondering if someone could explain something to me. When the Mac App store first launched, I was able to see if updates were available for software already installed on my MacBook Pro (iLife, iWork, Delicious Library 2, etc.).  Even though

  • Business logic in a Java Class

    Hi, In case of RPC web services why it is necessary to have a stateless session bean ? can i have a simple java class instead ? thanks and regards Vedant