Mrp md50

Hi
Iam having MTO scenario.
I have created sales order and run MRP. It creates planned order and purchase requisitions for procured items.
All procured items are individual.
When planned order of header material is converted into production orders.
When i make some  procured materials bulk in production order and run MRP md 50 then system does nor delete purchase requisition created by earlier MRP.
But when i do MD01 or MD02 then system deletes purchase requisition
Why system is not deleting with PR with MD50

Dear,
Yes right,
If you select individual requirement then system will not consider available stock and generate Proposals for every single requirements. Check in MRP4 view Individual / Collective.
Also you will find PR and Plan order with account assignment of Sales order (in case of MD50).
- If you select collective requirement then system will not generate planing proposals through MD50.In that case you have to go for individual MRP (MD02 / MD03)
This is standard SAP as MD50 for sales order specific requirement planning and MD02 is plant specific.
Please refer this link,
raw material stock to be consider against sales order in md50(i.e mrp run)
Regards,
R.Brahmankar

Similar Messages

  • Planned Order Creation after Sale Order MRP MD50

    In a BOM of FERT material, one HALB material is present at different BOM levels. When we run sale order MRP (MD50), system will create one planned order for complete quantity (total qty of HALB material at all  levels put together). Is there any way, so that system will create different planned orders for the same material present at different levels ?

    Hi,
    MD50 is T code for running MRP w.r.t sales sales, During MRP run system will explode the BOM and plan the requirements for all the levels( i.e, multiple levels)
    with regards,
    P.P.Anand

  • Difference of mrp  md50 & md02  whle doing mrp and production orders

    Dear Gurus,
    Please tell me the difference of mrp md50 and md02  also the production order difference from md04 and co01
    regards,
    muralidhar.t

    Hi Murlidahr,
    MD50 - Is Planing run for Sales Order.It can run MRP upto the last Level of BOM or in SAP terminology it is SINGLE ITEM MULTI LEVEL. Planing MD02 is also Single Item Multi level but there is one big difference and that is MD50 is concider those materials also which have MRP type M0, while MD02 is not useful in case of MRP type M0.
    MD02 - Single Item Multi Level.It is used for Planing for Single Item.But it will explode the all levels of BOM and generates the Planing Proposals for all level of BOM components.
    MD04  - Stock Requirement List.
    CO01 -  Create Production Order Manually.You will find Orders (upto Teco) in MD04 also.
    Regards,
    Dhaval

  • Bom explosion in sales order mrp(MD50)

    Hi Experts,
    In sales order MRP i.e. MD50 Getting the planned orders for header material(Finished goods) generated but for raw materials (BOM items) Purchase requisitions are not getting generated.
    Details:
    Header material A and raw materials B and C.
    In material B in MRP 4 coll/ind indicator is 2 And same indicator for C is blank.
    Now when we are running the MRP sales order based it will generate the purchase requisition for C only but not for B.
    In OPPQ we have done the setting for sales order BOM explosion.
    Can anyone please throw some light what is the setting missing in customization or in front end?
    Thanks in advance.
    Regards
    Vilas

    Dear,
    If you select individual requirement then system will not consider available stock and generate Proposals for every single requirments. Check in MRP4 view Individual / Collective .
    Also you will find PR and Plan order with account assignment of Sales order (in case of MD50).
    - If you select collective requirement then system will not generate planing proposals through MD50.In that case you have to go for individual MRP (MD02 / MD03)
    Please try and come back.
    Regards,
    R.Brahmankar

  • Viewing requirements generated after running MRP (MD50)

    Hi All,
    I would like to know if there is any way to check for all the requirements that have been raised subsequent to running MRP using MD50. We have an MTO scenario and want to cross-check if the requirements for raw materials are being accurately generated.
    This cross-checking requirement has risen due to the fact that there are many alternative BOMs for each material and there have been instances where due to errors in the material master, some raw materials are suspected to be missing out from the list of requirements generated.
    Thanks!
    Praveer

    Praveer,
    Check MDKP table for list of materials for which last MRP run date.
    Run MRP in MD01 for if in case MTO Raw materials has MTS relevancy this way you can include all materials for MRP.
    BR
    KK

  • Material Cost Not Shown in Production Order if planned with MD50

    Hi,
    We have run MRP MD50 for a sale order item ie FERT material which has BOM Items. All the stock of the BOM items is tranfered from Unrestricted Stock to Sales order stock. FERT ITEM planned order is converted to Production Order and all the BOM items sales order stock is issued against PO & Sales order no with Movement Type 261E.
    After confirmation and goods receipt stock of FERT is shown under sales order Stock of Fert Material.
    We can see the cost of operations but cost of materials consumed against the Production order is not displayed in Production order Cost analysis..How material cost can be displayed????
    If i create PO with out refering the sale order that is normal process i can see the cost of materials triggering in Production Order.
    Can we settle the varience when we are planning against sale order???
    Some one Pl help us.
    John

    Dear,
    Check your variant which showes the cost. See the following report
    KKAC - For Sales Order with Assigned Orders  or
    KKBC_KUN - For Sales Order or
    KOB1 - Actual Costs

  • Sale order stock de-assigning.

    Dear Gurus,
    Please address this scenario:
    Suppose I have a strategy which consumes from stock every time a sale order is raised. Imagine the situation that I have a stock of 50kg for a material and I receive a sale order for 30 kg, so automatically 30 kg stock is confirmed against this sale order. Couple of days later I receive another sale order for 30kg, now because there is a shortage of 10 kg. But I want this sale order to get the stock available and production to be triggered against the first sale order, which means I have to delink the stock assigned to 1st sale order and give it to second sale order. How do I handle this.
    Regards
    Sri.

    Hi!,
    Please elaborate on :
    1. Which planning strategy is being used.
    2.  Why you want to produce the balance quantity against the first sales order when that is completely delivered.
    If you are using MTS strategy e. g. 40 then you can handle this situation by proper setting in scope of availability check (OPJJ) (for the combination of Checking group and checking rule "A'). There if you uncheck " include sales requirement" and " include deliveries" then system will not reserve the warehouse stock for a previous sales order or delivery and you can easily use it as per your own priority.
    But if you are using MTO strategy then for the sales order of 30 system will never create an planned order of 50. Tthis is possible that against the sales order of 50 if you have only dispatched 30 and on the arrival of next order of 20 you want to utilize that stock. Then in that case you will have to make a stock transfer as suggested by the other guru. If you do so and you again run the sales order MRP (MD50) for first order then system will again trigger an planned order of 20 quantity with an separate stock segment in MD04 for first order.
    Regards,
    Uday

  • Order type settings for  convert planned order to production order

    Dear sir,
    I have 1 company code ,under 2 virtual plants are there.My scenario is plant 1(main plant)and plant 2 (virtual plant)
    both plant same FERT material.in plant 2 i am creating sale order and atual production will be done in plant 1.
    FERT material plant 2(strategy-40 sp.procurement-40 setting in spro ref plant (plant1) )and  plant 1 material (strategy 82)
    run the MRP MD50.panned orders are created but iam not getting production orders directly not getting the production orders
    .i have done settings in spro OPPE order type is given.in MD04 manual conversion planned order to production order system asking order type ,but i given order type in OPPE
    What are the settings for  production order directly from sale order at the time of RUNNING MD50
    Regards,
    Naresh.

    Hi,
    You will not get a production order out of MD50. That would have to be set up in the SD customizing for the sales order item, but I am not sure that would work with your two-plant setup.
    After MD50 you need to run CO41 for the collective conversion (and I also recommend the mentioned production scheduling profile customizing and then maintain this profile in the material master work scheduling view)
    BR

  • Sample Creation Process in Textile Industry

    Dear All,
    I had come across to a requirement that client wants to record different specifications of Products while creating a sales Order.Like Product Design, Thread Color & Design, Specifications of Threads, Customer name, Any Special Comment for Product or for Customer requirement.
    And where is am not using Variant Configuration.
    Waiting for your replies.
    Rajesh Kumar

    Hi Rajesh,
    Your requirement is clear in your first post itself. These type of requirements are addressed better through variant configurations. Defining two ways Go with the best.
    WithVC:
    Define one material KMAT and maintain the super BOM, Dependencies etc.
    Product Design,Thread Color & Design, Specifications of Threads, Customer name needs to be created as characteristics and accordingly values to be defined. Eg : Values for design - Design A, Design B etc.
    Any Special Comment for Product or for Customer requirement as production memo text
    In sales order creation as per customer wish list you can select and process the production cycle.
    Advantage is once you make this setup..production cycle will flow for 'n' number of customer requirements/trials
    Without VC:
    Create new material every time for sample production with strategy as 20. Assign material class 001 for maintaining the specifications in material master.
    As suggested earlier and also as suggested by expert, you need to maintain the related information in production memo as text for the production people to understand the requirement during manufacturing.
    Run MRP MD50 and comvert the planned to order and execute the production cycle.
    Every reply you have option to give helpful answer and correct answer. Mark helpful answer if something helped you and mark correct answer which you feel correct.
    Thanks & Regards,
    Ramagiri

  • Order BOM functionality suggestions required

    Hi Gurus
    I have a very immediate required question on a new functionality at my client place. My client had given a master data BOM and wanted to edit the BOM based on the customer requirement and selected BOM components should get transferred to MRP for the planning.
    So BOM is already maintained and based on the order , Order BOM should be maintained. So after fixing the order BOM components should get transferred for planning. Please Suggest this scenario with all the tcodes and configuration involved .

    Hi,
    Order BOMS are to be used in a MTO scenario if the components are to be transferred to planning.
    No additional customization are required for order bom, following steps are to be followed
    (1) Create a master bom - CS01
    (2) Create a sales order - VA01
    (3) Create Order BOM - CS61 (you can refer to the master bom & copy the relevant components)
    (4) Execute MRP - MD50/MD02
    (5) System shall generate the planned order & it shall have the components assigned in the order BOM
    I hope this addresses your query
    Warm regards,
    Umesh

  • Alternate BOM in Sales order?

    HI Dears,
    I am in a Pharma Company and i have one product with same raw material but in a diff. pack means i have a material said A with raw material AA & Packing Material BB and second one said A with raw material AA & Packing Material GG. {The product is same but in different pack (For Exam. : Paracetamol Tablet in 10x10 pack and 1000's pack)}
    By useing Alternate BOM i creat the both products. But When i creat sales order (VA01) their are no any indication for alternate BOM (BOM version).
    Please solve my problem as soon as .
    Thanks
    Sameer Kumar Pradhan

    Hi,
    You cannot create alternate BOMs if your working with Order BOM in MTO scenario.
    If you have created alternate BOMs in MTO scenario and wants to select this automatically from MRP then define prod version or selection criteria of BOMs in MRP4 view in Material master and please remember that 'Dont create any Order BOM from CS61".
    If there is no order BOM created then MRP (MD50) selects the available Material BOMs. If order BOM is created then this only will be exploded from MRP.
    regards
    Tajuddin

  • Sales order Release

    Hi,
    I have the below requirement from my client for make to order,
    System should allow to run MRP  MD50  only after the sales order is released from authorized person.
    Kindly suggest required confg.

    Hi
    First of all sales document dont have released procedure. But you can achieve it by following config.
    T-Code BS01
    Maintain here your required Status Profile (you can copy PM and changed the Status according to you by double clicking it)
    1. Not Released
    2. Released
    Then go to T-Code VOV8 and double click to your sales order type. In there in Transaction flow section "Status Profile"  is there assign your status profile there.
    Now with your authorized T-code VA02 system change the document status Released (with must be done by authorized person)
    Elese you can give t-code VA02 authority to authorized person (Take the help of Basis Guy)
    Now use BAPI or USEREXIT (with the help of PP consultant) and write the logic if sales order status is Released then system will allow to save Sales order planning (MD50)
    Hope it will solve your issue
    Regards
    Shambhu Sarkar

  • Using MD50 to run MRP for Sale Order

    Dear all,
    I have some problem when using MD50 with Mill Product Industry.
    When SAP system not activate Mill Product yet. I used transaction code MD50 to run MRP for Sale Order, the system have generated planned order for multilevel. But when SAP system have activated Mill Product, I used transaction code MD50 to run MRP for Sale Order, the system only generate planned order for single level. I think that we have to configure something based on Mill Product Industry. So can you help me for this
    Thanks, Regards

    Hi,
    Check with following links which may help you resolve your issue :
    http://www.sap.com/sme/whysap/industries/millproducts/index.epx
    http://help.sap.com/saphelp_di471/helpdata/en/4e/1796374b088e5ce10000009b38f8cf/frameset.htm
    http://help.sap.com/content/documentation/industry/docu_is_mill.htm
    Regards,
    Tejas

  • Raw material stock to be consider against sales order in md50(i.e mrp run)

    when i run MD50 against particular sales order, it is not considering stock of raw material. it is creating planned order for raw material which is already in stock. my problem is that when i run mrp it should consider my raw material stock.
    manish.

    Hi Manish,
    Correctly said by all our Experts (Mr.Brahmankar , Mr.Dharma)
    Now all you have to decide whether you want to go for this individual or Collective requirment type.Because on one hand
    - If you select individual requirement then system will not consider available stock and generate Proposals for every single requirments.
    Also you will find PR and Plan order with account assignment of Sales order (in case of MD50)
    - If you select collective requirement then system will not generate planing proposals through MD50.In that case you have to go for individual MRP (MD02 / MD03 / MD41 / MD42).
    Regards,
    Dhaval

  • MD50(MRP for sales order) doesn't work

    Hi all
    I ran MD50 for one sales order but it didn't create any planned order .Would you please tell what may cause this .
    Thanks
    Babak Bolourchi

    Hi, AJAY
    THanks for your reply,but If we run MD02 it generate planned order for other sales order as well eventhough I want to generate planned order only for specific sales order, Is there any setting for MD02 in this case prevent it generate planned order fo other sales orders.
    Thank
    Babak Bolourchi

Maybe you are looking for

  • How to change the Quantity in the Credit Memo using BAPI

    Hi All, I have a requirement in which i need to change the Quantity Value field available in the Credit Memo using BAPI. Can anyone help me out to get any available BAPI to perform this action or any Solution to change the Quantity in the Credit Memo

  • Forwarding to .mac

    I have email addresses at a company called Fusemail.com and forward those emails to my mac account. However, as of a few days ago, those forwarded emails have stopped coming. I checked with Fusemail and they're service is working fine. I then tried f

  • How to debug a smartform in WEBUI

    Hi, I need to make a change in the smartform being displayed in WEBUI. I found the smartform and the code where I need to make the chnage. However in order to see the values during run time, I need to debug it. Can I place a session breakpoint in a s

  • Need tips on my program

    Hi guys, I'm trying to create a program that prints a rectangle using the letter a and prints a space inside the shape but I can't seem to find the error. Here's my code: class Rectangle public static void printRect() char c; int positionOne = 1; int

  • Display all dates between a start and end date on an Apex Calendar

    Hi Guys, I am encountering an issue where Apex doesn't display the data from a valid query in a Calendar. I have a simple table used to capture events data with the following columns and data: event_id   start_date   end_date 1           20-APR-09