MRP & MPS PROBLEM

Dear ,
In my company we using MPS & MRP TWo planning mode.
Also we use two type of planning .one SO base & other one is on PIR.
I working with Process IND.
In our company only for packing Mat. we use SO,meansfor
FG we use MPS
SFG we use MPS.
ROH we use MRP.
Here we got problem.
Because by MB50 we got PLANNED ORDER for FG(A LEVEL ITEM).And SFG & ROH (B LEVEL item) we got Dep Req.And for ROH(C LEVEL ITEM)we not got any change.
So my problem is that for B level item i have to run MRP or MPS agin.
if it is single material then its ok but 10 or 12 material its become difficult for me that i have to run mps then again MRP.
So what i can do after A level MPS.
For B & c level material.......????????

Hi ,
Do this setting in your system , set up a back ground job for MPS materials and them set up the same for MRP materilas , this will solve your problem ., because MRP will run after the MPS run by which all your materilas will be planned accordingly .
Thanks and Regards,
Mallikahrjun.

Similar Messages

  • Mrp, mps questions.

    1.Is it possible to increase a companies output by increasing the MPS. if not, why?
    2.     How does the system coordinate the individual item records and provide back schedule information?
    3.     What are some of the reasons for wanting to process the records in and MRP system frequently? Provide examples and consequence of delaying the processing of the information.

    Deear,
    LTP is used for plnning the production for comming year and budget cost for comming year. i.e. std cost restimation is calualted.
    MRP/MPS are used to planning material/plant/multi plant level.
    After demand is put in DC's then if the special procurement key is maintained in DC's so that when run MRP in DC's the requirement will be passed to production plant in the form of sto planned order.
    Now we can run MRP/MPS sequencially in MD01- using scope of planning in which you can set the parameter such that which DC's MRP is run first, then which Manu plant MRP is run....
    In DRP, after running MRP you can run DRP to see that that push pull scenario is run so that load balance is done in such a way that DC's requirement can be met by another DC or a manu plant. If stock is not avaialbe in one manu plant it will go to other, if not available then systen will create a planned order in one of the manu plant.
    In APO we can optimise the whole cycle of push pull so that amany other constraint like cost also takne into account.
    pl come back if required.

  • How to Check MRP/MPS ASCP planning manager running or not

    Hi Team,
    How to Check MRP/MPS ASCP planning manager running or not.
    Could you please navigation for the same.
    Regards
    Jagadeesh

    Hi Jagadeesh,
    You can check whether the planning manager is running or not from the following navigation:
    Material Planner (R)  -> Setup -> Planning Manager
    You can get more information on planning manager from the below note:
    11.5 - Planning Manager Related Issues - A Complete Troubleshooting Guide (Doc ID 131051.1)
    Hope that helps!!
    Regards,
    Mohan Balaji
    NOTE: Please mark the post as Helpful or Answered if the update has really helped you. This would also bring the thread to logical conclusion and will be helpful for the viewers.

  • Mrp & mps

    hi friends,
    coud u plz solve my issue given below.
    we have seperate background jobs for running MRP(daily) and MPS(weakly once). can 1 material participate in both MRP & MPS.
    thanks in advance.
    regards,
    priya s

    Ideally it may not be feasible as the demarcation between MRP & MPS is based on MRP Types
    A material can have either MRP Type i.e. PD or P1 - P4 & if it is of MPS; it will have MRP Type M0 to M4
    How can a material have both types of MRP Types?
    Second thing; the MPS run is conducted without a BOM explosion whereas during MRP run system will not plan MPS parts again but only dependent assemblies and parts will be planned & clubbing both for a common material does not seem to be feasible
    However if u find some solution; do revert
    Rgds

  • MPS problem

    Dear experts,
           I am carrying out MPS(MD42) for a FG material for which there is a BOM, routing.
           I have maintained M3 as MRP type. But problem is that it is not planning for customer independent requirement in planning time fence. Client' reqirement is like that.
           plz guide me any setting are there for that.
    Regards,
    sameer

    Dear,
    Planning Time Fence is defined as number of days either at Plant Level or in MRP view of a Material.
    Planning time fence defined in mrp 1 view of material master.
    Run MD42 with processing key :- NETPL or planning horizon it can take from MD61 also.
    Regards,
    R.Brahmankar

  • MRP Tables problem

    HI All,
    I am facing problem in extracting datas from the table. In our Sandbox system, the table MDTB is not having datas. And the same table is having some datas in the Quality Server. i.e when I did MRP run, i got the No. MRP Table (DTNUM) from the table MDKP. By taking this No. MRP Table (DTNUM) as reference in the table MDTB, i checked the details. But I got the message "No table entries found for the specified key". But when I clicked on " Number of entries" tab, I saw there were lot of entries. But those are all old datas. It is same in the Production Server also. only old data's are present.
    Please someone let me know what may be the problem?
    Regards,
    Ram
    Edited by: Ram Kumar on Dec 31, 2008 11:07 AM
    Edited by: Ram Kumar on Dec 31, 2008 11:12 AM

    Hi Ram,
    Pls refer below link
    http://www.sap-img.com/pp001.htm
    http://www.saptechies.com/production-planning-extract-data-from-mrp-table/
    Regards,
    Sankaran

  • Mrp PO problem

    Hi Experts ,
                       In Order recommendation the quantity of finished item( production order) is not showing, while the purchase order quantity of the child item is showing . This problem is occuring against all the SO of a particular customer. I have checked the Instock of all the finished and child item. We are following the MRP process.
    Thanks and Regards
       Gyan Piyush

    Hi Rahul,
                  I have checked all the setting of item master which should be applicable for MRP of finished item and child item . when i run MRP it shows the recommendation of both finished and child item but after saving this recommendation at the time of order recommendation it is not showing the production order quantity and the quantity of some child item(purchase order quantity). i think you are understanding what i am getting the problem.
    Thanks and Regards
    Gyan Piyush

  • MRP run problem

    Hi experts,
    During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.
    MRP type = V1 (Reorder point planning)
    Lot size = HB
    planned delivery time = 0 days
    What could be the reason for it? Pls help me out.
    Thanks in advance,
    Rgds,
    jay

    When u keep your planning horizon 100 and in MD02 if ur using NETCH planning then system will consider the planning in between 100 days only If your open PO in out of planning horizon then it will not consider for the same.
    If u want to do the same u have to go for increase ur planning horizon time in OPPQ.
    whatever u required.
    Kind Regards,
    Nilesh

  • MRP run problem in TCode-MD01

    hi experts,
    There were some MRP controllers were assigned for User exit in SPRO for planning run (T code :- MD01 ). Now i have defined additional MRP controllers and also assigned them for user exit (in SPRO) for planning run.
    With old MRP controllers defined as user exits , Planning run is considering materials with only particular MRP controller.
    But for these newly defined MRP controllers , user exit is not restricting planning of materials with only particular MRP controller and materials planning is carried out for all materials with newly defined MRP controllers.
    please help me out
    thanks in advance
    rgds.
    jai

    The name of the extension where you can find the user exit is M61X0001
    You have to read the code to find out why it is not working for the new controllers.
    Probably the code is not that dynamic as you thought and the controllers are hardcoded ...

  • MRP Run Problem through MDBT

    Hi,
    We are running the MRP based on MRP controller through Transaction MDBT.
    As per SAP threads, We insert the User Exit Key as CB1 & User exit parameters as MRP Controller and click on start immediately.
    After result come, we see the output from SP02 transaction.
    There all the materials showing with 8 number exception (Terminations), means all the material's having the Deletion Indicator when i am seeing in MARC table against that MRP Controller - CB1.
    Please tell me how only deletion material's showing. How other material's will display, which display in MARC table except Deletion Indicator.
    Plz guide...

    Hi Kundan,
    STAD to trace combination of User and Tcode, but particular material its diffcult to trace in std sap.
    If you want to trace then you need do some enhancements, create customized table (mateial number, plant, date, time, etc) for when user run the mrp in MD02 then save all data's to your own table.
    I hope this will help to you
    Regards,
    Sankaran

  • MDBT : MRP RUN Problem

    I have one storeage locaion  for which i want to tun MRP run in backgruond .
    Now i have cerated MRP area (STORE) as stoarge location asssigne th erespective storge location there.
    Now i created  scop of planning & i assigne tthat MRP area as "STORE"to scope of planning.
    Now cerated varaint as "CONSUMPTION"and in scope of plalning i selcetd the scope of planing as my MRP area  and saved the variant .
    Now all material under this area are cinsumption baed material means everyone has MRP type as VB, reordre point and lot siza as HB, max lot qty  and STORE as MRP area in material master.
    NOw in MDBT i selcted the variant and click on start inmmediate i m getting mesage as "Request with variant CONSUMPTION Started"
    If i see MD04 til no requirenment is genrtaed with this Run ??
    1. Please tel ..where i ned to corect
    2. Is there any mesage after background MRP executed ;like in MD02 planning result screen .

    Dear,
    Please check whether planning file entry exists in MD21 also check MDAB & MDRE ?
    or run program RMMRP000.
    Please note With MRP type VB (Manual Reorder Point Planing) system will not consider Dependent requirement or any other reservation.
    It will take care about only Reorder point.
    If You have set reorder point of 100 Nos.
    And dependent requirement is of 35 Nos , and available stock is 90 Nos. then at the time of MRP run system will generate PR of 10 Nos only just to cover that less qty than the reorder point of 100 Nos.So there is nothing wrong in your case.
    If you want to concider Dependent requirement also during Planing run then you have to change MRP type VB to PD then check.
    Regards,
    R.brahmankar

  • MRP Run Problem With Shipment Notification

    Hi Experts,
    Issue
    In MD04 i have 1 shipment Notification,but after MRP Run it should get display in MD05 but in my case it is not happening.CAn anybody tell me the possible causes / reasons why this is happeinig.
    Awiitng for your quick response
    Need any furher inputs please revert back to me immediately.
    Cheers,
    Kumar.S

    Hi karthik,
    Thanks for your reply,even i know Md04 is Dynamic and MD05 is static,also i cant able to clearly understtood what u r telling,
    Kindly check whether shipment notification is updated during the 2nd run then it wont reflect in MD05
    but when i check the same scenario in Q shipment notification getiing updated but not in prdn.
    Pls clarify
    Cheers,
    Kumar.S

  • Mrp related problem

    Dear Gurus
    I am running mrp in md01 for consumption based planning.I have kept vb in mrp type hb in lot size and given the maximum stock limit  as well as reorder point.As I am running the mrp in md01 suppose a purchase requisition came for 100 for a particular material. Now I  converted partly say 50 to purchase order.If I run the mrp again in md01 the system is not creating the purchase requisition of remaining 50 . I have to  create planning file for that material in md20 then if  run mrp then only it is taking. Why automatically it is not getting updated.
    Regards
    Sandip Sarkar

    Hi Sandip,
    Your query is not clear. You are saying after MRP run a PR for qty 100 was generated. For that you can partially converted qty 50 to purchase order. Now the remaining 50qty is yet to be converted to purchase order. Now why you want that after MRP run again a PR or qty 50 is to be generated?
    Regards,
    Satyajit

  • Oracle 10G upgrade and MRP planning problems

    We just upgraded to Oracle 10G and are having users complaining about MRP not planning in correct low level code sequence. What has happened is that the MRP is planning component parts before the parent parts. We have never had this occur before and are on 4.6C hot pack 38. Help!!

    Hi,
    There are some Post-Upgrade Tasks like set compatible, db stats, check invalid objects, removing some database parameters, etc.  Make sure you perform these if you have not, please refer to your specific Oracle upgrade guide.
    Thanks,
    George

  • MRP running problem

    Hi gurus,
    When i try to run the total MRP in MD01, i can see that only certain material is being run, and most of it are not run.
    So, when i go to MD05 to view the MRP list, i can see that the material is still in old date MRP run date where the stock qty is wrong.
    I tried to go to MD02 to run that particular material, then that material is updated accordingly.
    Any one has any idea what had happen?
    Why when I run in Md01 some material is not picking to be run?
    Thanks!

    I've check in MR21, i found that planning file entry is there. But i can see some of the material that is not run do not have NETCH set.
    How do i make the material as NETCH set so that when i run the MRP in MD01 it can run it as well?
    Infact i try to create the planning file thru MD20 the entry is created but most of are not set as NETCH, why it can happen in such a way? (My processing key is NETCH when run MD01)
    Does it mean all the materials must have set as NETCH then only it can run the MRP?
    But i found some of the material do not have the NETCH set but when i try the total MRP run in MD01 it still can works?
    What is the reason behind?
    Please help, thanks!

Maybe you are looking for