MRP Net Requirements Calculation

Hi Guys:
I defined a Planning Horizon of 40 days, for Example if  today is the start date Since Planning horizon is 40 days (01/30/2012).
Vendor Lead time = 2months
Purchase order to vendor with Delivery Date (12/20/2011)  : 5000 Pc
Purchase order to vendor with Delivery date ( 03/04/2012): 6000Pc
Onhand Inventory = Zero
So i have Sales order for 10000 with Delivery Date ( 12/28/12) with in the Planning horizon.So when I run MRP using MD02 ,
Does the system consider Purchase orders with delivery dates  that are outside planning horizon into the net requirements calculation?
thanks for the help.
Kodali

dear friend,
as far as i know the available stock is calculated as follows:
plant stock
safety stock
+
receipts (pur.orders, prod. ordersfirmed proc. proposals)
requirements quantity (say, PIRs, mat. reservations,...)
=
available stock
shortage occurs if available stock is negative, that is, the requirement quantities are greater than expected receipts and stock quantity.
so, system specifies the date of the issue (for example, customer requirement, planned independent requirement, reservation, forecast requirement) as the requirements date.
regards,

Similar Messages

  • MRP Net Requirements calculation in External procurement Vs STO

    Hi gurus,
    Lets say I have a FG 1234 which has raw component 9999.
    Case1:
    Setting for 9999 is externally procured.
    I have a stock of 50 pc for 9999.
    I got order for 60 pc for FG 1234.
    so system will only create purchase reks for 10 pc of 9999 as it already sees 50 pc in stock.
    Case 2:
    Setting for 9999 is externally procured but from one of our own plant (Using SPK 40)
    I have a stock of 50 pc for 9999.
    I got order for 60 pc for FG 1234.
    will system create STR for 10 pc of 9999 as it already sees 50 pc in stock? or will it create STR for 60 pc without checking stock in the ordering plant?

    >
    dorian661 wrote:
    SPK 70 will not create an STR. Stock of 9999 will be checked in supplying plant. In case there is a shortage, a procurement proposal will be created against the dependent requirement here. Stock is not checked in ordering plant. You will notice that dependent requirements for 9999 will be seen in the supplying plant.
    Dorian,
    Thanks for the reply. so are you saying that in SPK70
    In ordering plant - MRP will not look at the stock situation for that material
    In supplying plant - system will check stock requirement and create dependent requirement for the shortage amount
    and in spk70 case, against what element is the delivery done to the ordering plant? in spk40 delivery is done against STO.
    Thx

  • Net requirement calculation in MRP

    Hi Gurus,
    Is there any way we can exclude Created Purchase order ( Not yet released ) in MRP run for the Net req calcualtion . ( pl suggest other than exit )
    Regards,
    Prasanna

    Hi prasana
    Net requirement calculation in MPR will include firmed receipts. ( P.O.). You can only block what are all given in plant parameter.
    We can exclude in Availability Check, in scope of Availability check setting.
    Regards
    J. Saravan

  • Net requirement calculation for Sales Order

    Dear Experts,
    I have configured a strategy comprising both( KE,040) and (LSF and 100), say the strategy is Z0.But the system is not doing net requirement calculation for the dependent requirement(always proposing Pr Req though there is stock).Checking group and checking rule, I have created like the standard PP order.Will anybody Pl. guide me regarding this?
    Regards
    Reshmi

    Hi,
    1. The MRP group or the strategy group in the MRP view of the material master record determines what requirements type is used.
    If you have not specified this information, the requirements type will be selected through the item category of the sales order item and the MRP type in the MRP view of the material master record.
    If you have maintained both an MRP group and a strategy group, the system uses the strategy group (precedence to strategy group).
    You can enter the strategy group directly in the MRP view. If you have specified a strategy group, you do not need to enter an MRP group.
    The configured Strategy group need to be copied from a standard Strategy and even if you group many Strategies(Max 7) you ned to check the req Type assigned to it .
    2. The item category is derived from the item category group in the Sales view of the material master record and from the order type of the sales document. Together with the MRP type in the MRP view of the material master record, the item category determines what requirements type is selected. The MRP group in the material master record is irrelevant here.
    The advantage of this method is that the selection of the requirements type depends on the business process (such as quotation, sales order, or repair).
    All the above Points need to checked in your case
    Pavan

  • Rescheduling horizon impact on net requirement calculation

    Dear MRP experts ,
    What is the impact of Recrudescing horizon on net requirement calculation .
    Regards
    Sasikanth

    Dear Sashikant,
    The rescheduling check is used to change the dates of already existing firmed receipts not planned on the same day as the requirement to suit the requirement date.
    If you look at MD04, the rescheduling date is based on the Stocks Requirement date. 
    In the net requirements calculation, the system checks whether warehouse stock or firmed receipts are available to cover requirements. If a material shortage exists, the system usually creates a new procurement proposal.
    Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
    hope it helps. please revert back.
    Regards,
    Alok Tiwari

  • Net requirement calculation

    Dear Gurus
    In Net requirements calculation, Safety Stock, Recipts (Purchase Orders, Production Orders, Firmed Procurement Proposals), Requirement qty(Pir, Customer requirements, Material reservations) are considerd
    In My Situvation, I want to exclude considering Safety stock while doing net requirements calculation
    Kindly tell me the setting i have to do
    regards
    palaniappan

    Dear Planiappan,
      In IMG Production + Material Requirements Planning + Planning + MRP Calculation + Stocks + Define Safety Stock Availability maintain 100% in AvSafetySt field. So in planning your 100 % safety stock will be considered.
    Regards
    Sunil Kumar

  • Exclude Stock Transfer from MRP Net Requirements

    Hi,
    Is it possible to exclude the Stock Transfer Orders from the Net Requirements generated by MRP? I want to base the requirements only from historical consumption. In my Stock/requirements list (MD04) for example, the Requisition generated by MRP increases in quantity since there are open Stock Transfers which are to be served by that plant to other plants.
    Regards,
    Lee

    Nazrin,
    Availability check configuration (OVZ9) has no impact on MRP.  MRP relies on its internal rules when it is performing its net requirements calculation.  You have very little control over which elements are included/excluded.
    You can exclude selected storage locations from MRP planning.  Stock and reservations against these storage locations will therefore also be excluded. 
    You can exclude a material from planning, change the material master MRP type to ND.
    Your best bet, though, would be to set your PM planning process up such that these materials never create the reservation in the first place.
    Regards,
    DB49

  • Excluding Stock From Net Requirement Calculation in PPDS

    Dear All,
    We can exclude stock on hand from Net Reuirement Calculation in ECC MRP by selecting Strategy 11 ( Gross requirement Plannung). Is there any Functionality like this in APO PPDS or SNP to exclude the Stock.
    Regards
    Sunil Kumar

    Hi,
              Its possible in SNP, try modifying stock on hand macro in planning book and overwrite initial column value to zero. hope this helps.
    Regds,
    Prasad

  • MRP Net Required/Available  Qty

    Hello Gurus ,
    I am carrying out MRP at plant level .After that MD04 We are analysing the result .We are developing Z report where we need to show Net Required Quanity(-) or Avaialable Quanity .We are using MDKP/MDTB table .
    1.Material Requirement Planning No xxxxxxx is not getting updated in MDTB table .I am getting MRP Table no from MDKP using Plant /Material Combination .
    2.What is the SAP Table -Filed name   to retrive Net Required/Available Quatity  (Planned quantity on the time axis that results from comparing receipts, issues, and current warehouse stock)
    Thanks and regards
    JH

    Hi,
    You can try with below function module, goto SE37 and test it
    MD_STOCK_REQUIREMENTS_LIST_API
    Regards,
    Sankaran

  • Net requirement calculation considering stock ( Strategy 52 )

    Hi All,
    we are using the planning strategy 52 for process industry and according to the standard functionality the stock of finished product will NOT be considered when MRP run and consumption.
    For various reason like customer return we might have the stock of FG. when forecast is finalized and PIR is build in demand management MRP will generate the planned order (type VP) based on the consumption logic. but if stock exist system will not consider it and continue to generate the dependent requirements for the raw material. this is really not acceptable by my client. we want the MRP run considering the stock of FG whensystem generates planned order for PIR.
    Is there any other way to fix this issue?
    we try to use user exit and set consumption indicator 4 for requirement type of VSE.but we failed. the answer is PIR ONLY consumes the requirement elements. Stock somehow a receipt element.
    any pointer is highly appreciateed.
    Reagrds,
    Mao Ye
    Edited by: Mao Ye on Apr 7, 2008 5:38 PM
    Edited by: Mao Ye on Apr 7, 2008 5:41 PM
    Edited by: Mao Ye on Apr 7, 2008 5:43 PM

    Dear,
    Stg 52, will create planned order equivant to the PIR created. and when sales order is created, the planned order is created.
    Hence the wayout is use stg 40. this will suit your requirement, create PIR and run MRP. Planned order is created.
    Do not convert the planned order to production order and give this autjorization to one who can take decision in shopfloor and coordinate.
    You can also use stg 74 ...just see the help link
    http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm

  • MRP net requirement calcualtion for Lot sizes

    Hi all ,
    Can some one help me on this ..
    I want to set up the MRP for the Raw materials Procurement .
    for this i want use MRP type as PD and lot size as WB Weekly lot size .
    but as per the requirement the MRP is run daily , i need clarification on certain things such as how does the system calculates the weekly lot size ?  say if the requirement is converted into PR on the first day of the MRP run ,followed by that if the requirement varies does the system creates a new PR or it changes the Qty in the existing PR if its was not converted to PO .
    what are the stock types considered during PR creation and how are the delivery dates determined during the PR creation ?
    thanks ,
    ksr

    Hi Chris
    You can try to set up a maximum lot size and a takt time on the material master.
    Take a look on the F1 help of this field on the material master:
    Takt time
    If a requirement quantity (for example, for capacity reasons) cannot be procured in a single lot, you have to schedule several receipts. In conjunction with the overlap indicator in the lot size (set in Customizing for the lot size), you can use the takt time to specify that these receipts are offset, that is, that they are delayed by the takt time.
    You enter the takt time in workdays.
    Use
    The system uses the takt time if a requirement is covered by several receipt elements due to restrictions on lot size such as maximum lot size (with all lot-sizing procedures) or rounding value (with fixed lot size with splitting).
    BR
    Caetano

  • Regarding mrp pr requirement

    Dear Gurus,
    we are working on MRP
    Through MRP purchase requisitions are raising on date basis.
    i.e.  suppose in aweek  raw material is required  @ 100 KG.
          with referance to BOM  & Qty of header level it raises  5 purchase requisitions.
    I require the system should raise one PR consolidating the qty of 5 PR.
    so that i can assign one PR to the delivery schedule
    is it possible. ?
    confirm the custmising  & process.
    thanks in advance.
    suhas inamdar.

    Suhas,
    What you are describing is 'Periodic Lot Sizing", which means basing the procurement proposals on a time period.
    This is effected by making the appropriate changes in the Material Master of the materials you are planning.  I believe that the Lot Size (MRP1 tab of Matmaster)  you want is the standard SAP lot size WB, 'weekly lot size'.  If you select this SAP standard lot size, no other configuration is needed.
    In this case, when MRP is performing its net requirements calculation, it finds the first instance of a shortage.  It then looks forward in time for all additional uncovered requirements, for one week, and then it proposes a single proposal (purchase req) that will satisfy the entire set of requirements, regardless of parent part.
    Rgds,
    DB49

  • Best Method to calculate Net requirement

    Hi Expers,
    can you suggest the best methods to calculate net requirement for FMCG products in APO Production and distribution planning.
    Best Regards,
    Anandharaj

    Hi Anandharaj,
    There are multiple threads, SAP Notes and documentation in the web about this.
    Please read this note that explains everything about Net Requirements:
    448960
    - Net requirements calculation (documentation)
    You can also check this article:
    Net Requirements Versus Pegging in SAP ERP and SAP APO - SAP Planning
    Hope this helps.
    Kind Regards,
    Mariano

  • Pricing - Requirment / calculation type / base value

    Dear Friends,
    Thnaks for the support and guidance provided by you for my previous posts
    In Pricing Procedure we give Requirment, Calculation type and Alternative formula for condition base value, I would like to know where do we exctly define all this?
    Or are they standard? If standards where we can see how they works?
    Regards
    Vishal

    Hi,
    go through the below Examples for better understanding ..
    Example: 1
    Condition Type: PR00
    Requirement 2 Item with Pricing
    Purpose:
    This is an example of a pricing requirement.  This requirement is met if the document item category is relevant for pricing and no previous condition in the pricing procedure has set the condition exclusion flag. This requirement can be assigned to condition types in the pricing procedure to avoid unnecessary accesses to the database when an item is not relevant for pricing or a condition exclusion indicator has been set.
    Example: 2
    Condition Type:  Net value
    Calculation Type: 2 Net value
    Purpose:
    This is an example of a condition value formula.  This type of formula can be used to influence the value shown for the condition in pricing.  A condition value formula is assigned to a condition type or value line in the pricing procedure.
    Formula '2' sets the value equal to net value that has been calculated so far for the item in the pricing procedure.  It contains the amount excluding taxes.
    Example: 3
    Condition Type: R100
        Alt.Condition Base Value: 28 (100% Discount)
    Purpose:
    This is an example of a condition base value formula.  A condition base value formula can be used to influence the basis the system uses when computing a pricing value.  A condition base formula is assigned to a condition type in the pricing procedure.
    Formula '28' sets the rate of the condition to a 100% discount.  This formula was delivered with condition type R100 to support free goods functionality.
    Reward if it is useful,
    Chandramohan

  • WIP flag MRP net

    Hello,
    can somebody explain the usage of the "MRP net"  box within the Material Requirement screen?
    In the past with 11i this was set as default, now in R12 it is not set for Non-Standard Wip Jobs.
    We are using Non-Standard Wip Jobs for Repair.
    Can we change this? What impact this will have?
    We are using MRP and also Manufacturing Wip Jobs.
    regards
    Ilona

    Dear,
    Length-based MRP is designed to deliver optimal allocation of requirements (length items in sales orders, for example) to available stock and production. This is achieved by ensuring that real-time changes in the stock/ requirements situation are taken into account by MRP. Allocation of stock to requirements is carried out by APO  modules with different control logic. Customer specific logic can be implemented for that.
    Hope clear to you.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • ITunes 10.5 on Windows 7 (32bit) doesn't display the iTunes store

    Hello there, on my Windows 7 (32bit) system, already with iTunes 10.4 I encountered the problem that the iTunes store remained inaccessible - it simply wouldn't load/display. Problem was solved by removing all Apple software, cleaning up the registry

  • Upgrading to Mac OS 10.4.10 from Mac OS 10.3.9....

    Hello all, I finally broke down and purchased my first ipod and also an airport express with itunes. My bright idea was to play music from my ibook through the airport wirelessly to my stereo. Of course, on trying to set up both the ipod and the airp

  • Issue with PDF links and opened Adobe files

    I have tested and IE 8 opens correct links inside PDF's. When I open link in Mozilla or Chrome it will not work. Is this related to Adobe Plugin which is installed inside Add-ons? Strange is that link inside PDF shows the following link:resource://pd

  • Upgrades from BW 3.5 to BW 7.0

    Hi Experts, I have done SAP BW 3.0B and wants to know aboout upgrades from BW 3.5 to BW 7.0 Please Help as i have to prepare for the interview .This is urgent . Thanks in advance Sunitha

  • Getting Started in 8i Personal

    Hello!! Some days ago i download Oracle 8i Personal Edition. I don't have any problem to install in my Win98 But is hard to me begin to utilizing it, already read all the documentation that find but as newbie is very dificult to understand many thing