MRP no purchase requisition generated

Dear Experts,
I have a problem that I can't generate purchase requisition after MRP run.
Example : I have a finished goods material FG and under which has 1 component Mat 1.
The setting in material master of Mat FG is internal procure(E), MRP type = "PD".
Mat 1 is external procure(F) and MRP type = "ND"
I entered the forecast requirement in MD64 for Mat FG  and I set the Create PR indicator to 1 in MD02
and start running MRP.
Planned order created for Mat FG, but no PR created for Mat 1 which only shows dependent requirement for Mat FG in MD04.
I can't see there is Mat 1 in the planning file(MD21) under Mat FG.
Any settings I missed and can anyone help?
Thanks a lot.
Claude

Hi,
IF you  do not maintain mrp type PD then system wont consider the material during MRP run, so convert it to PD.
Also go through the below link which will clear your doubts of master data maintenance for MRP.
[http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/30f4d6c1-0808-2d10-2ea5-f9b2863cfed8?QuickLink=index&overridelayout=true&47034186922243]
Please check and revert.
Thanks
Hrishi

Similar Messages

  • MRP - Single Purchase requisition for multiple Items

    Hi
    We have recently introduced MRP module in SAP .In some specific scaeanrios , we want to create a single Purchase Requisition for multiple items .Standard SAP generate different Purchase requisition for each item
    Is there any way out

    Sandeep,
    This topic has been covered numerous times in this forum and in the MM forum.  You evidently have not used the search feature.  There are thousands of posts in these forums, and the search function will be very helpful for you in future questions.
    To answer your question, No, nothing is available to make standard SAP MRP create Purchase requisitions for multiple items.
    Most companies address this issue during the conversion of Purchase Requisitions to Purchase orders.  During this process, you can add many items to a single purchase order.
    Rgds,
    DB49

  • No Purchase Requisition Generated after MRP Run MD02

    Hi All,
    After runing MRP Run MD02 for finish product with MRP Control parameters for create purchase requisition as 1 (Create Purchase Requisitions) . System is not generating any purchase requisitions for raw materials required for assembly.
    If we select 3 create planned order system is able to generate planned orders for raw materials required for assembly.
    Plz guide why am not able to generate purchase requisition directly.
    Regards,
    Sipra

    Sipra,
    Couple of checks,
    1. Check whether the Material is defined for "F" - External Procurement in MRP2 view of the material master.
    2. Check whether the material type used for the material is enabled for "External Purchase orders". Transaction OMS2.
    Regards,
    Prasobh

  • MRP and Purchase Requisitions..

    Hello,
    I want to know
                 When MRP generates the Purchase Requisitions which has many due dates per lines,  how does the dating logic work. Can we state create one PO for all lines due on a specific date and create a second one for other dates.  So there for a Purchase Rec, could turn around multiple PO based on dates. We want one PO per due date, not nested due dates within the PO. It is also my understanding that this can be automated. If you automate rec to PO, can you do this per question above on PO per due date
    Thanks
    Kris

    Please see response below:
    When MRP generates the Purchase Requisitions which has many due dates per lines, how does the dating logic work.
    [ANSWER] The due dates or delivery dates are completed as follows:
    Delivery Date = PR Release Date + Purchasing Processing Time + Planned Delivery Time
    with the following notes:
    1. PR Release Data -> Time that the PR is ready for conversion to PO
    2. Purchasing Processing Time -> the period it takes for the purchasing department to convert the PR's into POs; measured in work days and is maintained in Materials Management under Consumption-Based Planning u2192Plant Parameters u2192 Carry Out Overall Maintenance of Plant Parameters.
    3. Planned Delivery Time - period it takes from the receipt of the PO (by the supplier) to the delivery of the goods onsite. This is measured in Calendar days and is maintained on the Material Master Record, Vendor Master Record or the Purchasing Inforecord
    In addition, the Material Availability Date is computed as
    Availability Date = Delivery Date + GR Processing Time
    where
    GR Processing Time - time it takes to process the delivery (i.e. unpacking, storage, etc) for internal use; measured in work days and is maintained in the Material Master Record
    Can we state create one PO for all lines due on a specific date and create a second one for other dates. So there for a Purchase Rec, could turn around multiple PO based on dates. We want one PO per due date, not nested due dates within the PO.
    [ANSWER] We can do that by using the delivery date as one of the parameters for PO creation. Although, please note that there are a lot of factors to be considered for PO creation, not just the delivery date
    It is also my understanding that this can be automated. If you automate rec to PO, can you do this per question above on PO per due date
    [ANSWER] Yes, this can be set in ME59N, to create a new PO per delivery date. Again, please take note of the other dependencies/requirements for creating POs as well as the other requirements for automatic generation. Note that your business processes must be healthy enough to allow the system to automatically create the Purchase Orders
    Hope this helps
    Regards,

  • MRP and purchase requisition document type.

    Hi
    where can I set the purchase requisition document type for
    MRP?
    MRP generates purchase requisitions using document type NB instead of
    a custom document  type.
    <b>How can I set the system so that generates purchase requisitions with
    a custom document type?</b>
    Best regards

    hi,
    in Tranasction : OPPQ, you can assingn the user defined document type.
    here standard is NB. There you can change the doucment type to ZNB like.
    hope this may help you,
    Regards,
    Srinivas

  • Purchase requisition generate for alternative bom use for finished product

    i hav alternative BOM for finished product in which different raw material component in both BOM of same finished product.But when i RUN MRP that time only one raw material requisition generate another alternative bom raw material requision not generate.
       Is there any option when i RUN MRP that time we select one of the alternative bom component of  raw material for generation purchase requisition.
    Thnaks in Advance

    Dear ,
    MRP will select the BOM based on the MRP4-BOM Explosion tab -Selection Indicator .It can eitehr of these ways :
    1.Maintain Production Version with  different Alternative BOM  and keep Selection Indicator -3 .So sysetm will look into only the Valaidty  and lot size of the Production version and select the correct BOM to explode  and generate PR for depednts based on stock situation
    2.If you maintain Blank -then it will look into order qty and select the BOM according ly
    As in your case , selection methods 3 will fit  and you need to maintain PV with correct validity and lot size in MMR-MRP4-PV option .
    Try in sand box with different lot size and validity with indicator-3 .Create Order and run MRP-MD02-1,,3,3,3,2
    Check and revert
    Regards
    JH

  • MRP: Delete Purchase Requisitions and Create Planned Orders

    Hi there,
    I have a scenario, where in a material (HALB) was marked as externally procured. MRP was run for FERT material. The dependent requirements for FERT were created. Planned orders of the HALB material were changed to Purchase Requisitions.
    Later, the procurement type of material was changed to Inhouse Production.
    Now, I want all the Purchase requisitions that were created to be deleted and Planned orders should be created when I run MRP.
    I tried all the possibilities, but of no success.
    Please lemme know if there is any possibility to delete the P.Rs and Create Planned orders by running MRP.
    Regards,
    ABC

    I Haven't read the Plan order is converted in to PR Before
    If YOU convert the plan order in to PR, system will firm the Requirement, YOU need to remove the firm indicator FIxed iD in PR Before doing the MRP Run Again
    Do the following thing in PR
    In PR Remove the  Fixed ID in Quantities and Dates tab of the item
    and Rerun the MRP with Planning Mode 3 It will create a plan order
    Edited by: Sundaresan . E. V on Oct 29, 2010 6:39 PM

  • MRP split purchase requisition with same date

    Hi guru
    When I run MRP, if there are more requirements for the same material with same date, the system creates one purchase requisition grouping requirements.
    So, if I have two requirements of 3 and 2 pieces for material A, with date 18042015, the system creates one purchase requisition of 5 pieces
    I tried to use a BADI in order to split purchase requistion and have in this case a purchase requisition of 3 pieces and another one of 2 pieces but maybe I wrong something because MRP works wrong.
    Is there anyone that could give some tips about this request? Is there anyone that had same problem?
    Thanks
    Regards
    Raffaele

    Hi,
    Hope your BAdI is working now.
    MD51 is used for project. It creates replenishment orders against a WBS element. After this, you can run MD01 which will create replenishment order by material/plant level.
    If you have a question related to PS, maybe you can post your thread in this space:
    SAP Project Systems (SAP PS)
    Kind Regards,
    Mariano

  • MRP Apportioning purchase requisition .

    Hi friends,
    I would like to ask for your help redgarding the process or function, its possible I apportioning (purchase requisition )  per vendor.
    Example 1:
    Vendor A = 30%
    Vendor B = 70%
    Requeriements = 100 Ton
    Split:
    Purchase requisition 1 Vendor A = 30 Ton
    Purchase requisition 2 Vendor B = 70 Ton
    Example 2:
    Vendor A = 25%
    Vendor B = 25%
    Requeriements = 100 Ton
    Split:
    Purchase requisition 1 Vendor A = 25Ton
    Purchase requisition 2 Vendor B = 25 Ton
    Purchase requisition 3 = 50Ton ( no vendor split)
    Your help is highly appreciated.
    Thanks,
    Molina

    Hi,
    It is possible by using  Quota Arrangement, so first you need to active  Quota Arrangement in MRP2 view and lot size with quantity split. Then define quota arrangement MEQ1 with diffrenet % of material for different vendors.
    After that MRP Run and check the result.
    Regards,
    R.Brahmankar

  • Purchase requisition generated before service order release

    Dear Experts,
    We're testing the Logistics Integration Scenario for the Procurement of materials.
    When we enter a spare parts item(which is configured to create a purchase requisition in ERP)
    and just save the service order,
    the purchase requisition is created in ERP as soon as the order is saved even though the order is not Released.
    Is this a standard behavior?
    We expect that the purchase requisition should not be created until the service order is released.
    This symptom happens not only with purchase requisition scenario but also with the purchase order, reservation, too.
    Does anyone have an information on this? Any information would be highly appreciated.
    Thanks in advance for your help.
    F.T.

    As far as I know the standard behaviour is that the PR is created upon order save and not upon the status of the order or items changing to released.
    To get around this you can set user status and use status management to prevent the PR getting created or use the BADI CRM_SRV_FIND_LOG_SC to supress creation of the PR.
    Hope this helps.

  • MRP Put Purchase Requisition date one day before the Independant Req

    Hi Experts,
    There one  Independant Req per month dated the 1st day of the month.  When I run the MD02, the Purchase Requisition is placed the 1st day of the month. we do not maintain Planned delivery time. We would to have as Purchase Requisition date ; the last date of the previous month.
    We have :
    01.12.2010     PurRqs     0010011236/00010
    01.12.2010     IndReq     ZLS1
    We would like to have
    30.11.2010     PurRqs     0010011236/00010
    01.12.2010     IndReq     ZLS1
    Pl explain me what to do!
    Thank you for your help!
    Rgds
    Thibaut

    Thibaut,
    The easiest way to offset the date of the supply element from the date of the demand element by one day is to put one day into "Goods receipt processing time" in the Material master of each material.  (purchasing tab or MRP2 tab).
    Rgds,
    DB49

  • Purchase requisition generate again

    Hi Experts,
    Please help.
    I have created one sales order & run MRP ( MD02 ) . I got purchase req. for raw material. Convert this pur.req. to purchase order & done GR for partial qty. System genrate again pur req. when I run MRP again with planning mode 1. as per my consideration system should not create Pur req. Please tell me where I did wrong.
    Regards,

    Hi,
    My guess is that you did the partial GR with "delivery completed" flag ON, which means that you don't expect to receive any more from that PO.
    In this case there are uncovered requirements, and MRP will create new PR.
    Regards,
    Mario

  • No purchase requisitions generated

    Hi,
    How come no PRs are generated after the MRP run for my raw materials? My demand comes from PIR for the FG, which has a strategy group of 40. In MD04 after MRP run, IndReq are created. However, in the lower level material, no dep reqs are created. how can i fix this?

    Hi,
    After checking everything that others have stated,
    just check the stock of the material in question in the plant
    Also check the MRP type of the material in MRP view.
    Hope this would help.
    Ghanshyam
    Edited by: gnk gnk on Jan 14, 2009 12:36 PM

  • Multiple Purchase Requisition generate in the same date WHY ?

    Hi All,
    In MD04 Tcode for one Material No , I can see multiple PR getting generated for the same Date !! I would like to know based on what settings same date is appearing ?? and also please tell how to combine all this PR into one PR !!! Please guide me
    Thanks & Regards,
    Vinoth.

    Hi,
    Che on it:-
    Re: Third party Drop Ship
    Re: Single PO for Multiple PR
    Re: MD04 + Auto PR generation
    pherasath

  • How to attach Source of Supply to Purchase requisition(by MRP)

    Hi Friends,
    Source list - we are maintaining Source list for source of supply.
    Please tell me how to attach Source of supply by means of source determination to the Purchase requisition(generated by MRP) ?. What are the configuration and transaction steps?.
    Thanks

    Define fixed indicator in the source of supply , and set the source list usage of MRP to "1 "
    Below is help from sap:
    ==================================================================
    Determining the Source of Supply via the Source List
    The system first checks whether a quota arrangement has been maintained for the material, which has a validity period that covers the requirements date of the purchase requisition.
    It then checks whether only one entry exists in the source list that is relevant to MRP. The indicator for source list usage must therefore be set for a particular vendor so that purchase requisitions and delivery schedules, which are created during the planning run, are automatically assigned to this vendor. In the case of a delivery schedule, you must also have maintained a scheduling agreement for this entry.
    If you have maintained all the entries correctly, the system creates a purchase requisition with the source of supply that is recorded in the source list.

Maybe you are looking for