MRP not creating some schedule lines

Hello Gurus,
I hava peculiar issue for a Material.which has got dependent requirement from a header materila.
For some reason they want to run MD03 for this partnumber "ABC" . Materila is x type. It has got Valid SA, Valid SOurcelist,Valid QA.It has rounding value of 60, MRP type PD and EX .Not plannig teimw fence RLT is zero, GR time is 1 days .
In MD)4 below u can observe SChedule line is created except for feb 2nd, 03rd,o6, 7th.
QUESTION-1 :In below MD04 report no schedule lines were created for Dep req of feb 2nd, 03rd,o6, 7th.
Question 2:- even when STock is minus 6717 , the schedule line generated is for just 1400 etc
MD04 for "ABC" in Plant
02/01/2012     SafeSt     Safety stock               480.000-     47.000-
10/17/2011     OI-SL     0451404013/00030          6.000              41.000-
01/25/2012     DepReq     28299890               4.000-             45.000-
01/31/2012     DepReq     28299889               512.000-     557.000-
02/01/2012     ShipNt     0197672394/0550397074          540.000      17.000-
02/01/2012     DepReq     28299889               600.000-     617.000-
02/02/2012     ShipNt     0197676022/0550397074          900.000      283.000
02/02/2012     DepReq     28299889               300.000-     17.000-
02/03/2012     DepReq     28299889               3,300.000-     3,317.000-
02/06/2012     DepReq     28299889               1,400.000-     4,717.000-
02/07/2012     DepReq     28299889               1,400.000-     6,117.000-
02/08/2012     SchLne     0550397074/00010          1,320.000      4,797.000-
02/08/2012     DepReq     28299889               1,400.000-     6,197.000-
02/09/2012     SchLne     0550397074/00010          1,380.000      4,817.000-
02/09/2012     DepReq     28299889               1,400.000-     6,217.000-
02/10/2012     SchLne     0550397074/00010          1,380.000      4,837.000-
02/10/2012     DepReq     28299889               1,400.000-     6,237.000-
02/13/2012     SchLne     0550397074/00010          1,740.000      4,497.000-
GURUS PLEASE ADVICE
Edited by: HKR on Feb 1, 2012 4:43 PM

Hello
Please check if there is any rescheduling exception messages near the fixed planning elements.
Notes 71877 and 25388 provides more details about the rescheduling check during the MRP run.
BR
Caetano
Edited by: Caetano Almeida on Feb 1, 2012 12:33 PM

Similar Messages

  • MRP create more Schedule Lines than target quantity

    We already follow the OSS note 83343, we create a Schedule agreeement and validity date is the same as the Source List and Quota arrangement, also the Target Quanity is the same in the quota arrangement in the maximun quantity and Maximun release qty fields.
    After maintaining that data, we run the MRP as follow:
    Processing key          NETCH               Net change for total horizon
    Create purchase req.    2                   Purchase requisitions in opening period
    Delivery schedules      3                   Schedule lines
    Create MRP list         1                   MRP list
    Planning mode           1                   Adapt planning data (normal mode)
    Scheduling              1                   Basic dates will be determined for plann
    After that, still in teh schedule agreement was created more schedule lines that the quantoty is bigger that the target quantity in the sched Agreement.
    What else we miss??

    Thanks for your not help.
    That I can investigate is the quota arrenagement is incorrect but for some reason the QA is not working.

  • Strange MRP behavior - creation of schedule lines we don't need

    We are having a very strange MRP issue that I'm hoping there's a solution for.  If MRP looks something like this (extremely simplified):
    04/16 SchLine 100
    04/17 DepReq  100
    05/16 SchLine 100
    05/17 DepReq 100
    06/16 SchLine 100
    06/16 DepReq 100
    06/28 --- Time Fence ---
    Now a requirement comes along that increases requirements by 50 on each of the DepReq lines.  MRP wants to increase each of the SchLine lines by 50, but must put them after the time fence.  So far everything still looks Ok.
    04/16 SchLine 100
    04/17 DepReq  150
    05/16 SchLine 100
    05/17 DepReq 150
    06/16 SchLine 100
    06/17 DepReq 150
    06/28 --- Time Fence ---
    06/29 SchLine 50 (reschedule message, 4/16)
    06/29 SchLine 50 (reschedule message, 5/16)
    06/29 SchLine 50 (reschedule message, 6/16)
    We can't put these where SAP wants them.  We combine them into one schedule line for 150 and put it just inside the time fence.  Now here's the problem.  When we re-run MRP, it RE-CREATES the schedule lines for 50 so it looks like this.
    04/16 SchLine 100
    04/17 DepReq  150
    05/16 SchLine 100
    05/17 DepReq 150
    06/16 SchLine 100
    06/17 DepReq 150
    06/27 SchLine 150 (the line we added)
    06/28 --- Time Fence ---
    06/29 SchLine 50 (reschedule message, 4/16)
    06/29 SchLine 50 (reschedule message, 5/16)
    06/29 SchLine 50 (reschedule message, 6/16)
    How can we prevent it from re-creating the schedule lines for 6/29?  We've already added 150 on 6/27.  We can increase that quantity on 6/27 to one million, delete the three lines on 6/29, and SAP will still re-create them the next time MRP runs.
    Thanks,
    Randy

    Hi,
    Depending on the MRP type you have defined , procurement proposals are firmed and scheduled within the planning time fence.
    Hope have defined a Time fence and MRP type P1 , the procurement proposals inside the fence are firmed automatically and hence to compensate for the shortage (new reqmts), new proposals will be created on the end of PTF.
    yopu can choose from the following firming types:
    0  -- Procurement proposals are not firmed automatically. No firming takes place with this firming type.
    1 -- Procurement proposals within the planning time fence are firmed automatically as soon as their date is at least one day before the end date of the planning time fence. The date of new procurement proposals created in the planning time fence is moved to the end date of the planning time fence. As a result, these new procurement proposals are not firmed.
    2 -- Procurement proposals within the planning time fence are firmed automatically as soon as their date is at least one day before the end date of the planning time fence. No new procurement proposals are created automatically within the planning time fence; that is, the shortage situation is not adjusted within the planning time fence.
    3 -- Procurement proposals within the planning time fence are not firmed automatically. All procurement proposals required to cover the requirements are moved to the end of the planning time fence.
    4 -- No procurement proposals are created automatically within the planning time fence; that is, the shortage situation is not adjusted within the planning time fence.
    Regards,
    Sheik

  • Create a schedule line in sales order using Bapi

    Hi Guys,
    Here the requirement is automating the process of creating the schedule lines using Bapi.
    I am using the bapi BAPI_SALESORDER_CHANGE for the same.
    I could able to create a schedule line but the problem is,its not updating the CONFIRMED QUANTITY and COMMITTED  QUANTITY on
    sales order schedule line tab,its updating ORDER QUANTITY and ROUNDED QUANTITY.
    the structures and tables parameters i have updated are:
    IMPORT PARAMETERS: SALESDOCUMENT,ORDER_HEADER_INX-UPDATEFLAG= 'U'(change sales order).
    TABLES:SCHEDULE_LINES(ITM_NUMBER,REQ_DATE,REQ_QTY,DLV_DATE)
                   SCHEDULE_LINESX(ITM_NUMBER,UPDATEFLAG='I',REQ_DATE,REQ_QTY,DLV_DATE).
    Please help me out if i need to fill up any other parameters or anything am missing out here.
    Would appreciate your help.
    Thanks in Advance
    Ramu

    Dear Ramu ,
    Any solution to this Issue i have the same Requirement and faceing the very same problem.
    Thanks in advance for reply .
    Thanks alot.
    regards
    Prashant Singh

  • Create new schedule lines

    How to create new schedule lines for existing item programatically using bapi or function module?

    Hi,
    Check if this link helps you:
    http://forumsa.sdn.sap.com/search.jspa?threadID=&q=createschedulelines&objID=f50&dateRange=lastyear&numResults=15&rankBy=10001
    Regards,
    Swarna Munukoti.

  • Return key not creating a new line when using the horizontal text tool

    Going through the adobe after effects 'classroom in a book' examples - when writing a line of single line using the horizontal text tool pressing return does not create the next line underneath, the cursor stays on the same line?
    Anybody out there had this problem?

    Hi Bill
    Thanks for replying!
    My OS is windows 7. I think it is the first time I have needed to put more than one line of text in an after effects layer. I am new to CS5.5 - after effects and I'm going through an adobe tutorial  'classroom in a book' series book.
    I thought about using a paragraph text box as you suggest but could not find the function in the tools menu.
    I have since tried clearing the cache out and restoring default layout but with no joy.
    I have used the return key for multiple line text in premier pro and it works perfectly ok.
    Cheers,
    Alan

  • Backorder scheduling creating multiple schedule lines

    Hi,
    We have one issue wherein Backorder scheduling is creating multiple schedule lines for the same date.
    I would lke to know how to approach this issue, what all needs to be checked in config to prevent it from creating multiple schedule lines.
    Thanks

    Rajendra,
    You didn't mention what kind of order, but the first things to try are the same regardless.
    Use an availability checking type in your material master that uses daily requirements, similar to SAP standard 01.  You can review the checking types in OVZ2, use one that has a "Total Sales" entry of B.
    You can also change the default confirmation behavior.  OVZJ, set Avail check rule to "blank"  or B "full delivery" if you are talking about sales orders.
    Rgds,
    DB49

  • MRP is not generating any schedule line in my vendor's scheduling agreement

    Hello all,
    My question is: why the MRP is not generating any new line in my vendor's scheduling agreement?
    This is the scenario:
    I have created a vendor's scheduling agreement with transaction ME31L
    I have created a customer's scheduling agreement with transaction VA31 and those characteristics:
    - Forecast scheduling lines
    - JIT scheduling lines
    - MRP to DS type assigned to type C: Requirements according to forecast delivery/Deliveries according to JIT
    I have run MRP with transaction MD01
    MRP is generating some purchasing requistions, not purchase orders because we have set up a release strategy which requires 2 approvals, but those purchasing requests are not generating any new line in the vendor's scheduling agreement.
    Any idea why it could be? Please do not hesitate to ask for further explanations. Thank you

    Hi,
    Check if stock is available for the material in that plant.
    Also check the requirement date for the material and compare it with the planning horizon for that plant.
    Check your material master MRP view.
    Create source list(for material and plant in question) with MRP indicator 2.
    Thanks and Regards,
    Maheshwari

  • *MRP unable to create Delivery Schedule Lines in MM Scheduling Agreement*

    Hi Experts,
    I need your help...
    The issue is, in-spit of maintaining Source List with an u201CScheduling Agreement with item No.u201D & u201CSource List Usage in MRPu201D as 2 (Record relevant to MRP. Sched. lines generated automatically), MRP run does not generate Schedule Lines, instead PRs are created.
    Please help me to understand such behavior and fix the issue as the requirement is to generate Schedule Lines only.
    Thanks,
    Pratap

    Hello
    Please check
    1) Source List maintained properly in terms of Material # ; plant # ; proper POrg ; Schd Agr # and line item# ; proper validity date & MRP relevant indicator
    2) Please also check Quata arrangement if you are using. whether % is maintained correctly against the vendor
    3) MD03 , Delivery schedules- should be 3
    4) check your planning horizon whether it is NETCH or not
    5) check material master -MRP2 view, Procurement type is F- external procurement, schedule margin key if you are using
    if everything above is set, then I feel it should work
    Also please verify-
    lot size, safety stock and the corresponding prod volume for MRP input v/s the stock available in MMBE
    example.
    MD04, we can see the open del lines.
    if SS = 50 , prod volume is 150
    1) if MMBE shows 200 then it wont generate any schedule.
    2) if MMBE is 180 and your lotsize is 40, then after MD03, you will have a schedule line of 40 (provided if everything is set properly)
    Please ensure there are NO open delivery lines . if you find such in MD04, then please close open delivery lines
    in calculation of MRP, system considers such open delivery lines are going to receive and no additional schedule line generated even after MRP run
    thanks

  • PR created after MRP run, instead of schedule line

    Dear all,
    I want to create schedule lines automatically from the planning run, for raw material. I have maintained info record, scheduling agreement, quota arrangements and also the source list.
    For the raw material, safety stock of 1000 nos. has been maintained. The current stock of the material is 0.
    After MRP run, based on the upper level PIRs, schedule lines are generated properly. But, against the safety stock of 1000, a PR is generated.
    I donot want a PR to be generated.
    Please suggest a solution.
    Thanks in advance,
    Shrenik
    Edited by: Shrenik on Mar 8, 2008 4:17 PM

    Dear all,
    I checked an found that the schedule agreement date does not have any effect. Even if the requirement date falls outside the date range, i am able to create schedule lines.
    I also found that if i maintained GR processing time, then always a PR is created. If GR processing time is 0, then only schedule line is created. Moreover, planned delivery time does not have any effect on the calculations, even if it is 10 days, 20 days or 900 days.
    Can someone please clarify all these? How are these times taken into account?
    Thanks in advance,
    Shrenik
    Edited by: Shrenik on Mar 9, 2008 3:04 PM

  • Safety stock not covered by schedule lines in planning run

    Hi !
    In our organization we are trying to implement scheduling agreements and automatic creation of delivery schedule lines through MRP. We have MRP type PD and it considers the reservations created by PM orders and Production orders as requirement elements. When I do the planning run, it creates schedule lines for the PM order reservations and purchase requisition for safety stock. I need it to create schedule lines for all scenarios. Kindly help and suggest a solution.
    Regards,
    Satya

    Hi,
    Please refer the below links.
    Schedule Lines not getting created in MRP
    Re: No Scheduling line is generated when RUN MRP
    Hope it helps you.
    Thanks.

  • MRP Area and SA Schedule Lines

    Hello All,
        We are looking at using MRP Areas and noticed it can not be turned off once on (ECC 5.0).  Given that, is the following true with reference to schedule agreements:
    - Will seperate schedule lines be created for each MRP Area (same material)?
    - Does the receiving storage location come from the material master or the MRP Area (Does it matter if it is a type 01 or type 02 MRP Area)?
    - Is it possible to define differen't receiving slocs in a schedule line for a Plant MRP Area?
    Thank you,
    Jerry

    Thank you Charlie,
        The link is helpful however it doesn't come straight out and answer the questions - meaning there is a bit of ambiguity there.
    It would be appreciated if you or anybody that is using MRP areas with schedule agreements is doing the above.
    Regards,
    Jerry

  • Creating SD schedule lines in user exit

    Hello,
    We are automatically creating schedule lines for a certain kind of SD document (scheduling agreement, VA31) in a user exit. We are inserting directly into internal table XVBEP.
    Creating those lines works. The values in VBAP and VBEP are exactly the same as if they were created manually, even though the confirmed quantity is only calculated when the document is saved. The requirements show up in MD04 for example.
    However, for some reason index table VEPVG is not updated accordingly. Any ideas what we're missing?
    Thank you
    Roland

    Found it myself. We didn't maintain the client field when adding new lines to XVBEP. This didn't matter for database table VBEP, but it did matter for index table VEPVG for some reason...

  • Credit Status "Not allowed" but schedule line still confirmed

    I have a little issue. I know is sth from configuration, but I don't remember where it is.
    When automatic credit check is performed, and a sales order goes to "Credit Not allowed" I would like the position of the order remains unconfirmed, in order to leave the stock free for other orders.
    Now the system leave the schedule lines created, confirmed, even when credit stock is "not allowed". Could sb help on this?
    Regards

    Hi Eduardo Vartorelli
    For the Sales Order to stop the flow of requirements to MRP You have to set the status in the requirement.
    Go to T code OVB8 and then set what is your requirement in the routine.
    Currently the routine checks only for credit status in VBUK - CMGST if the status is B then it will not transfer the requirements to the MRP.
    I am not sure what is the Credit status of your document in the VBUK. If its not "B" and still you want to hold the requirements then you can modify the routine to handle your new requirement.
    If the status is B and then the requirements are trasnfering then you need to put a Break point in the rouitne and check if the routine is actually getting called or not.
    The Program Name is LV07A101.
    Thanks & Regards
    Srinivas.
    Reward Points if Useful

  • How to create multiple schedule lines for configurable products

    Hi -
    We have enabled variant configuration and would like to have multiple scheudule lines created , but it seems that only one line is avaialble, is there any way to configure the use of multiple schedule lines? 
    Note - we are not using KMAT material types, rather triggering a unique kit compoments within Sales BOM.
    We have been able to make the necessary adjustments to allow the creation of the Scheduling agreement and have the BOM explode correctly, but just am not able to trigger multiple sched lines.
    thanks
    Bill

    Your context node shall contain all these fields like country,city,etc as different attributes.so in your view configuration,add all these fields whatever you require from the AVAILABLE FIELDS section to the DISPLAYED FIELDS section.NOw all these attributes would be added in diff rows.What you need to do is,select the first attribute,lets say COUNTRY,click on this attribute and then on the buttn SHOW FIELD PROPERTIES.Thsi will show you the label name etc.Here you change the label name to NATIONALITY.Also ,it will show you the row no,cloumn span of the field and column span of the label.You need to reduce the column span of the field value.Ie if the column span is from D TO H,reduce it from D TO F.Now goto the next attribute eg CITY and in the same way,goto the attribute properties.Here ,There is a check box SHOW LABEL,uncheck this,and now goto the row no and the cloumn span.Make the row no same as that of the COUNTRY FIELD.The column span should howevrbe statring from where the column span of country field ended.Ie Teh column apsn of counrty field ended at F .So for CITY,the column span should start from G to amybe H.Now this is how you need to accomodate the other fields also in the same row,by changing the row no and column span in the field properties.
    Suvidha

Maybe you are looking for

  • WL6.1 Can't find my html file in .war

    I deployed a web application with in single html file "in.html". Here is the web.xml: <!DOCTYPE web-app PUBLIC "-//Sun Microsystems, Inc.//DTD Web Application 2.2//EN" "http://java.sun.com/j2ee/dtds/web-app_2_2.dtd"> <web-app> <servlet> <servlet-name

  • JProgressBar inside JDialogBox doesn't show up.

    Hi, I have a problem and kind of stuck. Here is the scenario..... Inside my actionPerformed method I create an instance of a class that extends java.lang.Thread and inside this class run method I create an instance of another class that extends JDial

  • I purchased adobe design standard and it wont download and open. help?

    whenever I go to open the downloaded program it gives me an error message. I think it has something to do with the fact that my computer is a mac and the program is for windows. what do I need to do to fix the problem?

  • Windows 8.1/IE 11 Does Not Automatically Connect to the Internet

    Windows 8.1/IE 11 Does Not Automatically Connect to the Internet I can't find the dial and redial options anywhere. I' m connecting through PPPOE but only manual. I know that in windows 7/8 a program like IE9 or IE10 could connect to the internet, bu

  • Asha 501- keyboard apps or multiple keyboards

    I'm an Asha 501 user, my fingers are very much large/fat so when ever I try to touch on the screen somtimes it goes to other keywords. my sister also used the same keyboard and her fingers are tiny, she has no issues in accessing the keyboard. but I'