Hi, we defined 3 order types like zp01,zp02, zp03 for std orders, r&d orders, sample orders resp in one plant. In oppr we mentioned the conversion order type between planned order to zp01. incase of std orders, it can be converted into zp01 order type. Please advise incase of zp02 or zp03, how to tell the system to convert in zp02 and zp03 etc. I afraid otherwise all the mrp generated planned orders will be converted in zp01 only. Is there any setting for the same? Please advice.

Hi ,
        Assign the production order type in the MRP GROUP (T-CODE :OPPR) in the configuration , Crete the 3 separate MRP groups with order types ZP01, ZP02,ZP03 .
For Ex : 
MRP GROUP     :   TES1 (Order Type :ZP01)
MRP GROUP     :   TES2 (Order Type :ZP02)
MRP GROUP     :   TES3 (Order Type :ZP03)
For those materials you want the Order ZP01 assign the MRP group TES1 , for ZP02 assign the MRP groups as TES2 and for the ZP03 assign the MRP group as TES3 in the MRP1 view of the material master .
In another case if you want to choose manually the order type at the time of Planned order conversion in to Production order Do not assign any order type in configuration of Plant Parameters (t code :OPPQ) and do not create any MRP groups .
Hope my answer will solve your issue...
Regards ,
Pathi

Similar Messages

  • Planed order type NB instead of LA during MRP Run

    Hi,
    All my components are externally procured and I maintained planned delivery time for scheduling purpose. But system is automatically picking the order type LA which is inhouse production when I am running MRP. What setting I need to make for MRP to select order type NB for Planned order so that system picks the plnned delivery time form material master to calculate basic finish date.
    We are generating planned order instead of Purchase requistion through MD02 setting.
    Regards
    Raghavendra

    Tested the mentioned scenario in the system, it explodes the BOM with Procurement type "F" and generates the dependent requirements for the components (planned orders with order type NB )
    Master Data Settings:
    Maintained "F" under procurement type for procured items
    Ran MRP with following parameters (MD02)
    Processing key     NETCH
    Create purchase req.     3
    Schedule lines     3
    Create MRP list     1
    Planning mode     2
    Scheduling                           2
    Lastly, check on " Plan Unchanged Components"

  • Service order type from repair orde

    Hi,
    Is there any custo  to define the service order type from a sales order type.
    Thanks in advance for
    Regards

    Hi,
    If u want to create service order from sales order,then some prerquisits for this are as.
    MRP strategy group is - 84 in material master,
    Fill all the data in t-code OISD
    Now create sales order >> put material & enter >>>system automatically create's service order, you can latter view it by in shedule line tab at item level or By t-code IW32.
    Kapil
    Edited by: Kapildev Farakte on Dec 28, 2009 11:22 AM

  • Third party sales order type

    Dear Guru's,
    I am configuring third party for the first time.
    Gone through the search.
    The order type NB is missing in my standard list of sales documents. Item cat TAS &  sch line cat CS is there.
    Pl suggest how do I go ahead to complete configuration?
    Thanks & Regards,
    santosh.

    Hi
    You can use Or or copy OR and can name as ZOR and use for third party
    Third party sales is controlled by item category and schedule line category settings
    So any order type you can take in VOV8
    In MMR the third party item category group is defined as BANS
    For this BANS with any order type we maintain default item category determination as TAS in VOV4
    In VOV7 we define controls for TAS mainly billing relevance as F and automatic PO ticked
    In VOV5 for this TAS and MRP type of the item as per MMR we define schedule line category as CS
    In VOV5 we define controls for schedule line category  CS
    Main settings
    1. order type NB (the po type to be triggered)
    2.Item category as 5 (third party)
    3.Account assignment category as X
    These controls whole process
    In MMR also purchasing view automatic PO  check box to be ticked
    If you ensure these settings then when you save a sales order with order type OR or any others a Automatic PO will be created
    Regards
    Raja

  • Order type settings for  convert planned order to production order

    Dear sir,
    I have 1 company code ,under 2 virtual plants are there.My scenario is plant 1(main plant)and plant 2 (virtual plant)
    both plant same FERT material.in plant 2 i am creating sale order and atual production will be done in plant 1.
    FERT material plant 2(strategy-40 sp.procurement-40 setting in spro ref plant (plant1) )and  plant 1 material (strategy 82)
    run the MRP MD50.panned orders are created but iam not getting production orders directly not getting the production orders
    .i have done settings in spro OPPE order type is given.in MD04 manual conversion planned order to production order system asking order type ,but i given order type in OPPE
    What are the settings for  production order directly from sale order at the time of RUNNING MD50
    Regards,
    Naresh.

    Hi,
    You will not get a production order out of MD50. That would have to be set up in the SD customizing for the sales order item, but I am not sure that would work with your two-plant setup.
    After MD50 you need to run CO41 for the collective conversion (and I also recommend the mentioned production scheduling profile customizing and then maintain this profile in the material master work scheduling view)
    BR

  • Planned order to production order type

    hi
    when ever converting planned order to production order system aumatically picks production order type pp01 from MRP group assignment. if i not assigned mrp group in material master means, how the system picks production order type. I think its pick from strategy assignment in order type?????
    thx in advance

    Hi, 
    Check with OPPQ..
    What is the Planning Strategy you are using??
    Regards,
    Siva
    Check with the Transaction OVZG..(Requirements Classes)..
    Depending on the Pl. Strategy you can specify the Order Type here.
    Regards,
    Siva
    Edited by: Siva Kumar M on Jul 25, 2008 3:55 PM

  • How to create a record for table PLAF with order type 'NB'.

    How to create a record for table PLAF with order type 'NB'(standard purchase order).
    who can tell me the T-code or some usefull information?
    Thanks.

    Hi
    This will be updated automatically when generate planned orders thru MRP. (MD02)
    regards
    Srinivas

  • Process order type conflict

    Hi,
    I am trying to create a process order from a planned order. I have generated the planned order through MRP run. The process order that is generating taking process order type which is not desired. I want to know from where it takes the process order type while creating process order from a planned order. i have given the desired process order type in production scheduling profile i.e. TS03. but it is taking PI01. i want the type as TS03
    the screen shot given below.
    thanks in advance.

    Hi Swastik,
    Check to which planning strategy (MTS or MTO) you assigned the order type in the prod. scheduler profile. Make sure you use the same in the material master MRP 3 view.
    Also check whether you have assigned the prod. scheduler profile in the material master work scheduling view.
    Regards
    Suri Pratyush

  • PP Order types

    Dear All,
    My client has a requirement that he needs two different Order types for both semi finished and Finished product..But we can assign only one order type in plant parameters for MRP...How this can be possible...
    Please Suggest...
    Regards,
    Pawan Shetty

    Hi,
    the order types in MRP parameters are for default only.
    You can more order types.
    For this you create order types, create Order type dependent paramerters, Production scheduling profiles (normally for each order type) and availability check control, scheduling paramters and confirmation parameters.
    In the material master data for the semi finished materials assgin the production scheduling profile (which contain the semi finished order type).
    In the material master for Finished material as the respective scheduling profile.
    during the planned order conversion to production order system will pick the order type based on the scheduling profile attached in the Work scheduling view of the material master.
    Thanks,
    JK

  • Order type is not picking while converison Plnd to process order

    Dear Dudes,
    i have maintained production scheduling profile in all material masters in which order type is specified. while converting planned order to process order order type is not picking.
    thanks in advance.

    Robert,
    Since you are using same order type for both MTS & MTO, you can define this order type "PI01" in the MRP plant parameters using transaction OPPQ in the Conversion of Planned order section.
    I am not sure, why production scheduling profile is not working for you, hope you are using the Production scheduling profile configured using CORY transaction check this part alone.
    Regards,
    Prasobh

  • Use of field "Open Item management" in Configuration of order types?

    Hi All,
    Can any body explain me the use of BOX for selectind or de-selecting "Open item management" field for order type in "Configuration of order types"?
    I need to understand the use of selecting it and not selecting it?

    it will activate the commitment management for your order type. 
    From SAP help:
    " Commitments are contractual or MRP-relevant obligations that are not entered in accounting but that lead to actual costs as a    result of various business transactions,   for example for purchase orders.
    Commitments Management is used to enter these obligations at an early stage and to analyze their cost- and finance-related results. "
    Hope this helps

  • Want to select the Order type automatically when creating production order

    Hi Gurus,
    Please help to select the order type automatically while creting the production order..??
    Please what configuration settings are avialble to make this happen to me.
    THank you in advance.
    Naveen.

    Naveen,
    First priority is the order type defined in the Production schedulling profile(OPKP), assigned to that particular material in workscheduling view. If this is not maintained then,
    Second priority is configuration at MRP Group parameters in transaction in OPPR, this MRP Group if assingned to Material master MRP1 view.
    Third priority is Configuration at Plant level parameters in transaction OPPQ, this defines the order type when convert planned order to Production/Process order.
    Regards,
    Prasobh
    Edited by: Prasobh Karunakaran on May 28, 2009 8:49 PM..added MRP group paramters also

  • REM Planned Orders being generated with Order type LA instead of PE

    Hi All,
    I'm running the Repetitive Manufacturing scenario and when I execute the MRP run for my Planned Independent Requirements, Planned orders are automatically generated with the order type LA. I understand that for repetitive manuf., planned orders should have the order typ PE.
    Is there something missing in config? How can I get the orders to be generated with the Order type PE??

    HI,
    Check the following settings which is required for REM
    1. Master Data -
    - Create Material master - MM01
    -Create BOM - CS01
    -Create rate Routing - CA21
    Create Rem profile - SPRO ->Production planning -> Rem.Manuf->Control data or use existing one
    Assign Bom seelction method = 2 & 3 (Prod version) in MRP view
    Rem MFG indicator - mrp view in MM01.
    Assign the REM profile to a material - MRP view in MM01.
    create Valid Production version - MRP view in MM01 & Check Rem mfg ind
    Assign the BOM and routings in Prod. Version
    2.For Preliminary Cost Estimate:
    Create version specific product cost collecter for Header material and preiminary cost estimate - KKF6N as per the settings in Rem profile. -
    3 For standard cat Estimate.
    create std Cost estimation(CK11n)
    std cost Estimation Mark & release(CK24)
    Thanks
    Hrishi

  • Different Order Types within a Collective Order

    Dear PP Gurus,
    I have a requirement for having different order types with in a collective order. For example, in a BOM of 3 levels, the order type for each assembly should be different say ZPP1, ZPP2 and ZPP3.
    For this, I have maintained separate production scheduling profiles in each of these assemblies with the respective order types. Also, I have maintained MRP groups separately for each of these materials. Further, in Plant Parameters, no default order type is assigned.
    However, when I create the order, the system creates all orders with order type ZPP1 which is for the header material.
    As per SAP help, this is possible but I am not able to create collective order with different order types.
    Please suggest any SAP Note or configuration changes which I have missed out.
    Thanks!
    With Regards,
    Nitin

    Dear Sabine,
    Thanks for your reply.
    However, as per SAP help, this is possible. Please refer to the link http://help.sap.com/saphelp_470/helpdata/en/ee/b6532cae8011d19e97080009b0db33/content.htm
    In this link, under Pre-reuisites section, in Point 2 it is mentioned
    "This indicator is transferred into the order header (master data) of the orders. If there are differing order types within the collective order, the setting of the indicator of the order type of the leading order takes precedence. This indicator is transferred to all lower-level orders and overrides their original indicators."
    The above line implies that different order types are possible with in a collective order.
    Please suggest some way out.
    Thanks!
    With Regards,
    Nitin

  • Order Type

    Dear Expert
    In the spro ->Production->Material Requirement planning->Procurement proposal ->conversion of Procurement proposal->Define conversion of planned order in to purchase requisition
    here in the purchase requsition item  i.e. object type 2 we have order type for purchase order NB . how can we create another order type and assign purchase requsition to that order type
    Regards

    Dear,
    Please refer the OSS Notes- 46919 has the answer for your query also refer same thread.
    Purchase req doc type in MRP
    Regards,
    R.Brahmankar

Maybe you are looking for

  • IPhone not syncing to iTunes music, But iPad OK... Restore?

    I updated to IOS7 on both my iPhone 4s and iPad 2. But when I go to sync music on my desktop through iTunes I get stuck in the final step of transferring for my iPhone but not the iPad. Is there anyway to go about fixing this without restoring my pho

  • Premiere Pro performance suddenly slowed down to be virtually unusable, even for simple projects

    I'm running latest Premiere Pro update on a late 2013, 27" iMac, with a 3.4 GHz Intel Core i5 processor with 8GB RAM, Mac osX version 10.9.5.  I know that's not a lot of RAM, but up until the past week or so I was able to edit an hour-long 4K project

  • Re: Satellite A300D: winload.exe missing or corrupt

    Hi I tried to make recovery to my system by using F8 and its works but suddenly the battry fail during the opration, So i repated the steps again after i connect the charger but i coudn't, and i received the message... +Windows failed to start. A rec

  • Error communicating with FTP server....

    Hey everyone, I registered a domain through GoDaddy.com two days ago, but only finally settled down with a host yesterday (Monday). My free host is byethost.com. After signing up for a host, adding my domain, and changing the domain's DNS's, I am awa

  • Sales doc assignment

    After defining the sales area and document type when i create sales order system gives me as error message as sales area has to be assigned to the document type, I do not want to assign the sales area defined to any specific document type, please let