MRP Planned order finish Date calculation (Planned delivery + GR Proc.time)

Dear Gurus,
Currently in our system, when MRP runs, Planned orders are created and the order finish date is calculate based on Purchasing processing time OMEW + Planned Delivery time from Material Master + GR processing time from material Master.
My business requirement is that,  system has to take only Planned Delivery time + GR Processing time and exculde Purchasing PRocessing time.
I cant make it Purchasing Processing time as ZERO - because this is used for other Purchase orders and KPI will be affected for procurement department
Now we are going to Automate the Purchase orders for Materials - if outline agreement exist.
How to make system settings for a MRP run, the Planned order finish date - should consider only Planned delivery time from Material master + GR Processing Time ( it should exculed Purchasing PRocessing time). Is it posssible? if not by any user exit, ABAP coding should be done?
gurus please advice!
BADI : MD_PLDORD_CHANGE - is this can be used?
Please advice
Regards
RS
Edited by: RS on May 18, 2010 10:22 AM
Edited by: RS on May 18, 2010 10:33 AM
Edited by: RS on May 18, 2010 1:34 PM

Let me check, if I can find a way to paste /afs/md04 (AFS Envirnoment) screen shot . But in the mean time following are the
details
IHPT  - 12 days
GRPT - 0 days
SMK  - 000 (Op Period, Float After Prod., Float Before Prod.,Release Per. - 0 days)
Thanks,

Similar Messages

  • Req. delivery date and plan order finish date relationship

    Dear Experts,
    I have a question on setting the req. delivery date and plan order finish date relationship. Now, I want the plan order finish date is one day before the req. delivery date, is it possible to set it in configuration? Please advised! Many thanks!
    Regards,
    Matt Yim

    Matt,
    Please use a schedule margin key(SMK) in the material master MPR2 view which has float after production defined as 1day.
    If there are no SMK with that defination then you can define you own in customisation and assign the same in the material master. (SPRO--->Production ->MRP->Planning ->Scheduling and Capacity Parameters->Define Floats).
    Regards,
    Prasobh

  • Set Order finish date in planned order on Production order creation CO41

    Hi experts,
    I'm trying to set the order finish date, field SFC_POCO-PEDTR on transaction CO41, into Scheduled finish, field CAUFVD-GLTRS, of production order transaction.
    The issue is get the value of PEDTR. For change the value GLTRS i'm using the exit PPCO0007 and it works, but i haven't the value of field PEDTR.
    I hope to have been clear.
    anybody can help me??
    Thanks in advance
    Marco
    Edited by: Menegazzo Marco on Aug 3, 2010 5:20 PM

    Hi  DwarakanathS         
    Thanks for you reply....
    But if in the exit i try with the code you suggest, when i do the assign:
    FIELD-SYMBOLS <my_fs> TYPE SFC_POCO.
    ASSIGN SAPLCOUP(SFC_POCO) TO <my_fs>.        
    the program give me an error "Field "SAPLCOUP" is unknown. It is neither in one of the specified"...
    and if i try with this:
    FIELD-SYMBOLS <my_fs> TYPE SFC_POCO.
    ASSIGN 'SAPLCOUP(SFC_POCO)' TO <my_fs>.        
    the error is "SAPLCOUP(SFC_POCO)'" and "<MY_FS>" are type-incompatible."
    what's wrong?
    thanks
    Marco
    Edited by: Menegazzo Marco on Aug 4, 2010 10:16 AM
    Edited by: Menegazzo Marco on Aug 4, 2010 10:53 AM

  • Planned order start date & finish date

    Dear All ,
    I am running MRP for finished material ,
    But i am getting Planned order start date & finish date are coming same (todays date ). But when i am converting the order then proper scheduled dates are coming .
    Why for the Planned order the scheduled dates are not coming ?
    Regards

    Hi Venky,
    Pls try to understand how MRP works
    After MRP planned orders are created for the requirement(in house)
    In the planned order stage -basic dates are deteremined
    For the determintaion of basic dates system check the in house production time/replenishment lead time maintained in the material master
    For your requirement you maintain lot size dependent in house production data in the work scheduling view & check
    You have to key in data in set up time,processing time ,base qty etc
    Hope it is clear
    Rgds,
    SVP

  • Planned order start date is in the past

    Hi Experts,
    I am running MRP with lead time scheduling (2) at my production plant. The planned orders are generated against the requirements but the start date of the planned order is in the past. I have not mentioned anywhere in the configuration allowing the scheduling in past. I cross checked plant parameters, MRP group, settings for determining basic dates & scheduling parameters and every where start in the past check is blank.
    Since the planned order basic dates are calculated based on in house production time in material master, I maintained the lot dependant times in work scheduling view (Set up & processing time with base qty). But system is not considering this in MRP run. But its considering the lot independant inhouse prod time maintained in work scheduling view in MRP.
    Is there any other check to be maintained or system limitations? Your expert view on this please.
    Appreciate an early reply.
    Thanks & Regards
    Prathib

    Check OPU5
    S Anil

  • Planned Order creation date

    Hi,
    Please let me know where can we find out the date the planned order was created. In which table and which table it is tored. I have tried in table PLAF. Unable to find out this.
    Regards,
    V. Suresh

    hi
    Please try
    PLAF and Field PEDTR
    Order start date is Basis start Date  in the planned order.
    If you go to Det Scheduling tab of planned order in a Planned order there option Basic Dates , there are two dates Start and Finish ... these are the dates required by you......opt for  Help Window it Shows you a Description :           "Order finish date in the planned order
    Date, according to the planned order, that you should expect either the completion or the delivery of the planned order quantity."
    BV

  • SNP planned order availability date difference between APO and ECC

    Hi,
    I have observed that SNP Planned order availability date is not matching between APO and ECC. Details are as follows.
    I ran SNP Optimizer with bucket offset of 0.5. After publishing the optimizer created planned orders to ECC, only start date is matching.
    Example:
    I am using PDS as a source of supply.
    Fixed production activity in SNP PDS is 1 day.
    GR processing time: 3 day
    After running optimizer planned order is created with dates explained below.
    Start date/time: 09.05.2011 00:00:00
    End date/time: 12.05.2011 23:59:59
    Availability date: 16.05.2011 00:00:00
    Because of bucket offset defined as 0.5 optimizer planned order availability is start of next monday.
    After publishing this planned order to ECC dates on the planned order is as follows.
    Start date: 09.05.2011
    End date: 09.05.2011
    Availability date: 12.05.2011
    I have not maintained any scheduling margin key in ECC. Also if I dont define the GR processing time, planned dates between APO and ECC always match. Can anyone explain the impact of GR time on the availability date.
    Regards,
    Venkat

    Hi Venkadesh,
    What's "state stamp"? Do you mean different time zone?
    note : 645597  mentioned by Nandha is very helpful:
    In standard, CCR will use duedate - "the available date of the output product".
    Nandha's words "In SAP APO, if the receipt date of the primary product deviates from the
    end date of the last activity of the order, the receipt date
    always identifies this as inconsistent. You cannot rectify
    inconsistencies of this type by using CCR."
    I guess in your PDS or PPM, the output product is not assigned to the End of the last activity. Someone changed it?
    Please CIF the PDS or PPM again.
    If you really want to apply a note, please use note 815509 as you're using planned order,
    and system will use order end  date in CCR instead.
    GR time is always considered. BR/Tiemin

  • SNP Planned Order start date in past

    Hi
    After SNP run, for the past requirements it is giving avaiablilty data as today but the planned order start date is in past. Now this order fails in CIF as the production version in R/3 is valid from today.
    In the strategy profile we have backward+reverse with infinite scheduling. In this case the start date should be todays date for past requrirements... am I correct?
    Regards
    Abhishek Rai

    Hello Abhishek,
    We are also facing the same issue. Did you find any solution to this issue?
    We are on SCM 7.0 with EHP1.
    Thanks,
    Mangesh

  • How Production Order finish date and time is being comptued by SAP?

    Hello Expert,
    How Production Order finish date and time is being comptued by SAP? for example, we create a Production Order via CO01, the basic start date is 29.09.2008 and time is 04:00 it gives us basic finish date is 29.09.2008 and time is 13:28.
    how does SAP compute the time 13:28 as it finished time
    Please explain me briefly.
    Thanks
    Ryan

    Hello Guys,
    When we create Production Order in R/3 the time is calculated by routing but it is extended at SetUp machine time. It is not correct?. SetUp imachines time used only for first Production Order for the same product and it is plan manually, for others Production Order we need calculate time for production without SetUp machine time being pick up to compute finish time. how could we achieve this? only those Machine time will be check.
    thanks

  • BOM Explosion with order finish date

    Hi,
    In transaction OPPQ it is possible to configure the BOM explosion date used by MRP and creation of a process order (see SAP NOTE 506345).
    I suppose this setting is also considered when re-reading master data during release of an order.
    The field BESAL can have the following values:
                BOM explosion number/order start date
    1     Order start date
    2     Order finish date
    3     BOM explosion number/order start date
    4     BOM explosion number/order finish date
    What I do not understand is that value 4 also end up in using the order start date when re-reading master data. Here the function module CO_ZF_VALIDATIONDATE_DET is called which contains the following coding:
    + Festwerte Feld BESAL:+*
    * ' ' Seriennummer/Eckstarttermin
    * 1   Eckstarttermin
    * 2   Eckendtermin
    * 3   Seriennummer
    IF T399D-BESAL <> CHAR2.
    * Auflösung mit Starttermin
    u2026
    ELSE.
    * Auflösung mit Endtermin
    u2026
    ENDIF.
    which says only use the Order finish date if BESAL has the value 2. The comment showing the possible values gives me the impression that SAP simply forgot to adapt this coding when splitting the value 3 (prev. only BOM explosion number) into 3 BOM explosion number/order start date and 4 BOM exlosion number/order finish date.
    On the other hand the SAP Note mentioned above documents this behaviour.
    Does anyone know the reason why value 4 (BOM exlosion number/order finish date) results in using the order start date ?

    hi,
    The defination in OPPQ is only working for the MRP, when the planned order is created.
    Then the explosion date will be copied from planned order to production/process order when you convert the planned order.
    However, when the production or process order is created manually, or when you do a re-read master data process, then a different BOM explosion date process will be carried out as described in the SAP note 506345, it has explained the behavior clearly base on the different value of paramter:
    V_T399D_S-BESAL = initial, 1, 3 or 4
    V_T399D_S-BESAL = 2 (Explosion with order finish date)
    So there is no problem to have different behavior of planned order and production/process order.
    Regards,
    Rachel

  • Production finish date is later than order finish date?

    In my company, most of the plan orders in MD04 have an exception message "64 Production finish date is later than order finish date". The plan strategy of the materials are 40. The plan orders are created from Scheduling Agreements or Independent Requirements.  We set 'Scheduling' as 2(lead time) in the MD01/MD02. The self-production time in material master data is 0. The schedule margin code is 000 which all the parameters are 0.
    For a example, we create a requirement on 2007.04.24. After MRP run, plan order generate. It's basic date will be 2007.04.24, but the production date IS 2007.04.25. All the plan order like that, the production date are always later than the basic date for one day.
    Could someone tell me why? and how to settle this problem?
    Thank you in advance!

    Hi,
    check scheduling parameters for planned orders and scheduling parameters
    for production orders.In that set the various indicators like
    adjust basic dates to order start date
    do not adjust basic dates to order start dates and try.
    Tcode opu3 / opu5
    Thanks,
    s.nandhakumar

  • BOM explosion date after order finish date

    Hi
    We have issue with BOM explosion date. In process order, BOM explosion date is geting calculated after order finish date.
    Any idea why this is happening.

    Hi,
    Just to understand the issue better, can you list the scheduled and basic dates on the order.
    Anup.

  • Planned order is creating before planning bucket for a specific material.

    Planned order is creating before planning bucket for a specific material.
    Eg: Planning Bucket future: 12 months & Start date- 01/02/2012, but Planned order Availability/Requirement date is 12/23/2011.
    What causes this, how to fix it? Please suggest u2026
    Thanks
    Ravi

    Since your planning bucket start date is in the future, so this is normal that the system is trying to satisfy the demand in jan2012 bucket by creating a receipt on Dec23, 2011.
    Reasons for RECEIPT to be generated earlier is
    (1) There might be a FIRM HORIZON( SNP PROD HOR)
    OR
    (2) There might be a GR time and the system is considering that time
    In Customizing for Advanced Planning and Optimization -> Supply Chain Planning -> Supply Network Planning (SNP) -> Basic Settings -> Maintain Global SNP Settings, in the SNP:GR for Plnd Ords field, you have selected Processing Time.
    Blank out these times and see if it works, else do one of the following:
    (1) Set Period Factor(LOT SIZE TAB of PRODUCT MASTER) to 1, so that the receipts get created at the end of the bucket.
    OR
    (2) Create your demand at the end of the planning bucket period
    Thanks
    Kumar

  • Can GATP confimed date come from production order finishing date??

    Hi Expert,
    I have one question to ask.
    in the GATP , I want to the APO system can consider the production ability , that is, when I create a sales order, the system will make  a GATP check in APO, if there is no enough stock, the system will create a PPDS planned order and return the planner order finsihed date as the schedule line confirmed date.
    I do not know this is possible or not??
    I hope some expert can help me to solve this problem
    thank you in advance!

    Hi Liu,
    Why Planned order date.. It could be Production order date (planned order release date) + inhouse production time + Transporation lead time + GR processing time (at the original location where the order is placed) ..that should determine the material availability date. CTP exactly does this. Make sure that the "replenishment lead time is switched off" in the product-location master (in fact this is location independent)- as this take precedene over everything else.
    Also ensure that that end of checking horizon is larger than the interval established above, else MAD could be much earlier. Also enure that transfer of requirements is set both at header and schudule line level for CTP to work.
    Regards,
    Loknath

  • Handling Planned order created from Demand planning and Sales order in MTO

    Hi all
    In MTO\ Repetitive we genrate Dependent requirement from demand planning (PIR) after running MRP which finally planned order created but on the other hand in short term we have Sales order which generate planned order after running MRP(In MTO), How we should handle planned order generated from Demand planning and the ones generated from sales order.(both after MRP Running).
    Regards
    Babak Bolourchi

    Dear,
    You can combine the planning strategy also main as 56 and second as 65 and in demand managment MD61 you have the option select requirement type.
    Then while creating sales order use MTO strategy and take MRP run through MD50 and then MD02.
    and if you want to assign the stock to sales order then you and do it through MB1b with 412 E movement type.
    As per my knowledge, generally 56 strategy only takes Sales Order Stock into consideration.
    Consider setting the Individual/Collective indicator to 2.
    Mark those characteristics that should have a usage probability in demand management as Relevant for planning.
    Hope clear to you.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • PO purchase order non MRP relevant

    Hi, Is it possible to create a document type which is non MRP relevant? For instance, if we place an article XXXXXX in a NB purchase order, the article XXXXXX is MRP relevant and will be listed in MD04. Is it now possible to create the article XXXXXX

  • Adobe Reader XI-Not working on Windows 8

    Adobe Reader XI has suddenly stopped working on my Windows 8 laptop. It has worked previously and I'm not sure what has changed. I have the most up to date version of Adobe Reader. I have uninstalled it and reinstalled the program. I have also used t

  • Pre 10 - unable to upload projects to video sharing websites

    All my projects are in PAL-AVCHD_HD_1080i 25. the option to upload to video shearing sites does not work. Why?

  • Sync Issues post 6.1.2 upgrade

    I updated by 4S to 6.1.2 today.  Now, I cannot sync my phone with iTunes.  It states that I need an additional 2.6gb of free space available.  I haven't added anything to the phone since the upgrade and it shows that I have well over 8gb of available

  • No entry for CHARGEBACK

    Hello folks, In AR, No entry will be created when a chargeback is created for the balance $200. so how the customer know the remaing balace $200 need to send. do we send any invoice or just call the to collect the money. Thanks, Raghu.K