The requirement can be mapped using period Based MRP type
1) create Planning calendar in MD25 for the plant giving period as 7 and week days as Tuesday and Thursday and from/ to periods
2) Use MRP type as R1(Time Phased Planning)
3) Assign the planning calendar u have created in Planning cycle in MRP1
Regards
Brahmaji

Similar Messages

  • MRP Planning during Purchasing

    need some favour regarding the MRP
    Could you let me know what should be the better process in SAP for this client  ( Distribution Company just buy and sell  ) in making purchasing decision how much to buy and when to buy?
    Based on
            Confirmed back orders from customers .
         (ii)   Anticipated Projected demand from customers .
         (iii)  Forecast based on 3 months sales history. 
         (iv)  how much safety stock levels need to be maintained?
    thanks for help
    Purna

    Hi There
    You can use the MRP type- VM (Automatic ROP)
    For this you have to have the past historic values,, so that you can do the MRP Run based on VM and system will decide the ROP
    Check the below link for more details,,
    http://www.sapstudymaterials.com/2008/05/materials-planning-procedures-in-sap.html
    And safety stock exists to cover both excess material consumption within the replenishment lead time and any additional requirements that may occur due to delivery delays.
    So based on your RLT and daily consumbtion(avg) you can define the Safety stock,,
    Thanks
    Senthil

  • User Exit or BADI For MRP Planning

    Dear all ,
               I want to Control the MRP Planning ( MD01 ) only for Demand Orders..
    Tell me any User exits / Badi for that Issue..
    i checked in this enchancement M61X0001, this is correct or wrong ,,,,
    With Regards ,
       GJ

    HI
    Possible exits
    LMDR2001  User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001  User exits in additional planning.
    I hope there are no BADi's for this try for implicit enhancements if u r using ECC 6.0
    Regards
    Edited by: Rasheed salman on Dec 20, 2008 9:54 AM

  • MRP Job not picking 'few materials'

    Hello,
    I am facing strange issue. We have been  running MRP daily job (since July09) for few MRP controllers.
    We have found that system is not selecting 'few materials'...
    One of the mateial ABC has not been selected since 29th Aug and other XYZ since 2nd of Sept...
    But User has converted the Planned order to PR on 2nd and 3rd Sept respectively....
    Whereas when I displays the results for MRP run (MD03)for these materials it does shows the PR.
    But MRP job does not picks these....
    Even I changed the 'processing indicator' 'ON' but it did not work.
    Please suggest any possible causes.
    kind regards,
    JPS

    Hello DB49,
    I did run MDAB then MDRE and then MRP run for MRP controller ;Material belongs to...
    But No results; MRP run did not pick the ABC material.
    Even I have set the 'display list' parameter during MRP run but it did not pick material in question....
    Any Idea, When I try to create planning file manually MD20.....
    And select any of the 'check box' it says "The material ABC has been marked for the MRP run"
    Please suggest...
    ======================MDAB=============================
    Number of set planning file entries:          0                              
    =======================MDRE===================
    Plng file entries for operational planning run:                       
    No. of deleted panning file entries:          0                                                                               
    Planning file entries for long-term planning:                                                                               
    Complete statistics:                                                  
    Plng file entries for operational planning run:                       
    No. of deleted or changed planning file entries:          0                                                                               
    Planning file entries for long-term planning:                         
    No. of deleted or changed planning file entries:          0                                                                               
    ==================MRP run for (MRP controller; Material belongs to)====================
    regards,
    JPS
    Edited by: Bhatti JPS on Sep 10, 2009 9:30 AM

  • How to make MRP run based on Target Safety stock

    Dear Experts,
    For our MRP-planned materials with safety stock we would like MRP run to take into account  target stock level defined for each month.
    for example: we know the target stock level values will be for M1 = 1000, M2 = 0, M+3 = 5000 etc.
    MRP should then propose orders to replenish up to the target stock level at the end of each month:
    needs for current month = (target stock level defined for current month  minus safety stock)
    needs for M1 = (target stock level defined M1 minus safety stock)
    needs for M2 = (target stock level defined for M2 minus safety stock)
    etc
    Do you know if there is any simple way to achieve this?
    Thanks you!
    Elynn

    Dear Experts,
    in my company, we are facing exactly the same issue,  we would like the MRP to consider a target stock exaclty as described by Elynn.     To be more clear, if we could reproduce the TDSS like in SNP in MRP, we'll be happy !.
    We imagine already to manage the target stock level in APO DP and released into ECC6 as a different MRP element than Forecast.  this target stock should not be considered as forecast neither consumed by any sales order.   Only to force the MRP to generate planned orders to increase the final stock when needed.  This is only an idea, we have nothing tested yet.
    someone have an idea if there's a standard solution for make this ?  I mean, why this fonctionality exist in SNP but not in MRP?
    thanks for any help
    Celia

  • Reg planning of long lead materials

    Dear all,
    To make a finished material there are 4 stages below which we have raw materials which are expensive and require 8-10 months lead time to procure and here planning of raw materials is done once in a quarter, how to plan for such long lead time materials ( can we use MRP planning) here we should plan only raw materials and later on all the semifinished materials once we get the customer order
    please help me
    Thanks in advance
    venu

    Venu,
    Use planning strategy "50" for your finished product, and you can create PIR for the forecast for the Finished Product. Take up MRP run and after MRP run for finished product you would get Planned orders of type "VP" and you would get dependent requirement for Components which can be processed further. Planned orders VP cannot be converted to Production orders, when a sales order is created for this product this planned order quantity would be reduced and new planned equal to the quantity of sales order would be created for execution.
    Regards,
    Prasobh

  • Planning based on availability of prt's

    Hi, we plan our prod based on availability of dies. if same die available then only we schedule the prod order on certain day. die are specific to materials. is there any pp functionality whether certain dies are availble on certain day? can we do capacity planning based on availability of dies (prt's). pls help.

    Yadav,
    I dont think we can do a capacity planning based on availability of PRT. You can only stop release of the production order based on availability of PRT based on the check defined in OPJK transaction for business transaction 2, for your Plant/Order type combination.
    Regards,
    Prasobh

  • MRP Plan Error

    Dears All
    I'am testing the MRP to Release a PO as follows:
    1.  Create sourcing rule
    2.  Assign sourcing rule 
    3.  Create quotation or create blanket PO
    4.  Create Apporve Supllier List 
    5.  Set MRP: default Sourcing Assignment Set
    6.  Run MRP and release planned order
    The MRP plan is going well.
    But as soon as i set the sourcing rule separately(ex. supplier A:60% rank 1,supplier B:40% rank 1),  the MRP launch concurrent process(Memory-based Snapshot) is performed with errors.
    And when i set the sourcing rule with whole one back(ex. supplier A:100% rank 1, or supplier B:100% rank 1),  the MRP launch concurrent process is performed well again.
    So i am do sure that this error is related with sourcing rule.
    Can someone help to resolve this?
    Best Regards
    Leno

    Error log :
    +---------------------------------------------------------------------------+
    Master Scheduling/MRP: Version : 12.0.0
    Copyright (c) 1979, 1999, Oracle Corporation. All rights reserved.
    MRCNSP module: Memory-based Snapshot
    +---------------------------------------------------------------------------+
    Current system time is 24-JUL-2013 18:32:03
    +---------------------------------------------------------------------------+
    Page Length = 93, Page Width = 132
    ===================================================================
    Debug Mode :        Disabled
    Output to Terminal : No
    Argument Method :   Database Fetch
    Trace Mode :        Disabled
    ===================================================================
    Argument 1 (ORG_ID) = 141
    Argument 2 (COMPILE_DESIG) = THMS_MRP4
    Argument 3 (LAUNCH_CRP_PLANNER) = 2
    Argument 4 (SNAPSHOT_WORKER) = 0
    Argument 5 (MON_PNAME) = 0
    Argument 6 (MON_REQUEST_ID) = 0
    ===================================================================
    The value of profile option 'MRP_RETAIN_DATES_WTIN_CAL_BOUNDARY' is N
    SELECT  TO_NUMBER(TO_CHAR(MIN(calendar_date),'j')),
    TO_NUMBER(TO_CHAR(MAX(calendar_date),'j'))
    FROM    bom_calendar_dates
    WHERE   calendar_code = :calendar_code
    AND    seq_num IS NOT NULL
    AND     exception_set_id = :exception_set_id
    Loading workday calendar. Please wait ..
    SELECT TO_CHAR(calendar_date, 'j')
    FROM   bom_calendar_dates
    WHERE  calendar_code = :calendar_code
    AND    exception_set_id = :exception_set_id
    AND seq_num IS NOT NULL
    ORDER BY calendar_date
    Loading workday calendar. Please wait ...
    Loading workday calendar. Please wait .                                     0:00
    args->default_demand_class = 
    args->demand_class = 
    args->sched_desig = THMS_MPS4
    args->request_id = 632499
    args->current_date = 2456498
    args->min_date =  = 2456447
    args->max_date = = 2460098
    args->first_date  = 2456447
    args->plan_type = 1
    args->part_include_type = 1
    args->reservation_flag = 1
    args->wip_flag = 1
    args->po_flag = 1
    args->cutoff_date = 2456682
    args->sched_type = 2
    args->demand_tf_type = 2
    args->overwrite_option = 1
    args->operation_schedule_type = 2
    args->plan_safeyt_stock = 1
    args->assignment_group_id = 0
    args->include_mds_days = -23453
    args->category_set_id = 1
    args->user_id       = 1150
    args->snp_worker   = 0
    args->org_id  = 141
    args->in_pipe_name = snp_ORA$PIPE$011611500001
    args->out_pipe_name = mon_ORA$PIPE$011611500001
    args->compile_desig = THMS_MRP4
    args->hour_uom = HR
    args->plan_capacity = 2
    args->unit_eff_enabled = 2
    args->mon_request_id= 
    CONCURRENT MRP MRCMON "ORG_ID=141" "COMPILE_DESIG=THMS_MRP4"             "REQUEST_ID=632499" "IN_PIPE=mon_ORA$PIPE$011611500001" "OUT_PIPE=snp_ORA$PIPE$011611500001"
    APP-FND-01406: Cannot find a printer driver for printer type HPLJ4SI and print style 1099RPORTRAIT
    Cause: A printer driver for printer type HPLJ4SI and print style 1099RPORTRAIT does not exist
    Action: Check that print style 1099RPORTRAIT is supported on printer type HPLJ4SI and a record exists in FND_PRINTER_INFORMATION
    APP-FND-01406: Cannot find a printer driver for printer type HPLJ4SI and print style LANDWIDE57
    Cause: A printer driver for printer type HPLJ4SI and print style LANDWIDE57 does not exist
    Action: Check that print style LANDWIDE57 is supported on printer type HPLJ4SI and a record exists in FND_PRINTER_INFORMATION
    APP-FND-01406: Cannot find a printer driver for printer type HPLJ4SI and print style ERW2Potrait(2001orlater)
    Cause: A printer driver for printer type HPLJ4SI and print style ERW2Potrait(2001orlater) does not exist
    Action: Check that print style ERW2Potrait(2001orlater) is supported on printer type HPLJ4SI and a record exists in FND_PRINTER_INFORMATION
    APP-FND-01406: Cannot find a printer driver for printer type HPLJ4SI and print style W2PAPER(2001orlater)
    Cause: A printer driver for printer type HPLJ4SI and print style W2PAPER(2001orlater) does not exist
    Action: Check that print style W2PAPER(2001orlater) is supported on printer type HPLJ4SI and a record exists in FND_PRINTER_INFORMATION
    APP-FND-01406: Cannot find a printer driver for printer type HPLJ4SI and print style ERW2Paper2001orlater
    Cause: A printer driver for printer type HPLJ4SI and print style ERW2Paper2001orlater does not exist
    Action: Check that print style ERW2Paper2001orlater is supported on printer type HPLJ4SI and a record exists in FND_PRINTER_INFORMATION
    APP-FND-01406: Cannot find a printer driver for printer type HPLJ4SI and print style RL1PAPER
    Cause: A printer driver for printer type HPLJ4SI and print style RL1PAPER does not exist
    Action: Check that print style RL1PAPER is supported on printer type HPLJ4SI and a record exists in FND_PRINTER_INFORMATION
    Launched concurrent request 632501 for workers
    Selecting Items                                                        9    0:00
    Flushed all buffers into MRP_SYSTEM_ITEMS                              9    0:00
    Selecting Discrete Job Info                                            7    0:00
    Selecting repetitive schedules info                                    0    0:00
    Selecting line capacity info                                           0    0:00
    Selecting BOM                                                          4    0:00
    APP-FND-01564: ORACLE error 1426 in mrllis_load_item_sourcing
    Cause: mrllis_load_item_sourcing failed due to ORA-01426: numeric overflow
    The SQL statement being executed at the time of the error was: begin :l_sourcing_history := MRP_SOURCING_API_PK . mrp_get_sourcing_hi and was executed from the file 6676358/mrp/lib/mrlnex.pc.
    APP-MRP-22075: An internal error has occurred (mrnspxt, 14, 10005,  )
    @ERRORTEXT            Cause:        The current routine encountered the specified@ERRORTEXT  x        Action:        Contact your customer supportrepresentative.
    APP-MRP-22075: An internal error has occurred (mrnspgpt, 14, 202 , 10005,  )
    @ERRORTEXT            Cause:        The current routine encountered the specified@ERRORTEXT  x        Action:        Contact your customer supportrepresentative.
    APP-MRP-22075: An internal error has occurred (main, 13,  ,  )
    @ERRORTEXT            Cause:        The current routine encountered the specified@ERRORTEXT  x        Action:        Contact your customer supportrepresentative.
    gthsk1=10
    gthsk2=2
    gthsk3=1
    gthsk4=1
    Statement with the error:
    begin :l_sourcing_history := MRP_SOURCING_API_PK . mrp_get_sourcing_hi
    6676358/mrp/lib/mrlnex.pc
    SQL Error Code: -1426
    ***** End Of Program - Memory-based Snapshot *****
    +---------------------------------------------------------------------------+
    Start of log messages from FND_FILE
    +---------------------------------------------------------------------------+
    +---------------------------------------------------------------------------+
    End of log messages from FND_FILE
    +---------------------------------------------------------------------------+
    +---------------------------------------------------------------------------+
    Executing request completion options...
    Output file size:
    0
    Output is not being printed because:
    The print option has been disabled for this report.
    Finished executing request completion options.
    Concurrent program returned no reason for failure.
    +---------------------------------------------------------------------------+
    Exceptions posted by this request:
    Concurrent Request for "Memory-based Snapshot" has completed with error.
    +---------------------------------------------------------------------------+
    Concurrent request completed
    Current system time is 24-JUL-2013 18:32:57
    +---------------------------------------------------------------------------+

  • Planning based on Six month sales

    Hi Frnds,
    Currently we are using Flexibe planning method where we enter the 4 months projection quanity and then run the mrp at the start of every month.
    Now my company needs a planning based on the last six months sales, where the system should automatically pick up the billing qty of the last months of the products and then on that basis Mrp run should take place.
    Is there any standard procedure available for this in sap???
    Regards
    Rajesh

    Hi Rajesh,
    I think you need to check it by implementing Forcast process from SAP.
    Regards,
    Hiren

  • MRP Planning

    Hi,
    We have an issue where the part created the purchase requistion and gets rescheduled daily and thus the Release date in the purchase requistion gets Changed daily.As of result of which, the PR is not falling within a varint which is used to convert PR into PO.
    Part is not used in any BOM and there are no open orders or sales orders for this part. MRP considered this part and created a PR as the safety stock has been consumed. Now whenever MRP runs(MRP runs daily), the requirement date gets Changed automatically, though there is no entry observed in planning file.Backward scheduling is applied in this case.
    Your thoughts on this issue is appreciated!
    MRP type for the part is PD - MRP
    Safety stock is in negative
    Planning mode 1 - Adapt Planning data (Normal) in MD03.
    Planning file entry - no MRP planning type is checked
    let me know if I am missing anything!
    Thanks

    Hello
    On the tab "Quantities/dates" you should check the flag "Fixed ID" so that MRP won't change the requisition anymore.
    BR
    Caetano

  • I want to retrieve data from p0001-PLANS based on the below condition,

    Hi,
    I want to retrieve data from p0001-PLANS
    based on the below condition
    select stext from hrp1000 where plvar = '01' and otype = 'S' and objid = p0001-plans and begda GE pn-begda and endda LE pn-endda.
    Thanks,
    Rama.

    Hi
    Based on the Query you have specified thoise are stoerdin an Internal table- then
    select stext from hrp1000 into table t_hrp where plvar = '01' and otype = 'S' and objid = p0001-plans and begda GE pn-begda and endda LE pn-endda.
    The check table for this PLANS is T528B .
    if t_hrp[] is not intitial.
    select * from t528B intot table t_528 where plans eq t_hrp-plans.
    endif.
    Now you can get the PLANS data.
    Refer to the Text tbale for PLANS -  T528T
    To get the TEXTS -
    if t_hrp[] is not initial.
    select * from T528T into table t_528T where plans eq t_hrp-plans.
    endif.
    Regards
    Lekha

  • Planned order for MPS items can be unfirmed in MRP plan

    Hi All,
    I'm using SCP functionality (not ASCP) in MRP module. I run a global MPS first and then use it as supply schedule to drive mrp plans. I noticed that some planned orders (for MPS items) loaded into MRP from MPS can be unfirmed in MRP and I can enter new quantity and new date for them, whereas other planned orders for MPS cannot be unfirmed.
    What is the logic behind it? How to control it?
    thanks in advance,
    Tom

    Hi Ram,
    I don't think that there should be any issue due to the planned order created in the system against the PIR for the next month ....& it will not lead to improper planing even if the demand changes still we are not going for the firmed planned order....... if the PIR changes during the next MRP run then it will adjust the planned order accordingly .....
    Still you want to  restrict the planning to the current month then the simplest way that  I can think of is planning horizon....
    Thanks
    Kaushik

  • MRP planning improved delivery date

    Hello you all,
    I have a question regarding the MRP planning of improved delivery dates. Let me schedule the scenario.
    As material is ordered, the expected delivey date is indicated by delivery rules. If for some reason the supplier can deliver earlier, this is mentioned in the PO tab Confrmations confirmation catagory AB.
    As we run the MRP via transaction V_V2, the updated delivery date is not shown in MD04.
    What do i need to do to see the correct data in MD04?
    If this is all a bit fuzzy, please ask for further details. I am not a SD consultant.
    Thanks in advance for your reply.
    Best Regards,
    Peter Lans

    Hi,
    Run the program SDRQCR21 in SA38.
    This will correct the data in MD04.
    Hope this helps.
    Regards

  • MRP plans sales orders outside planning horizon

    MRP plans Sales order for Finished Goods Outside planning horizon even when using NETPL. Strategy 40 is in use with 3 level BOMs. Planning horizon - 200 day. How could it be prevented?

    Dear,
    Please check have you assigned any MRP group to your material masters in MRP1view? Then check the planning horizon maintain in MRP group in OPPR also check same for your plant in OPPQ.
    If you define it as 200 days then system will only plan the requirement which falls under 200 days with processing key as NETPL.
    If we set planning horizon as 200 days then in the material in which MRP relevant changes happened in last 200 days will only be planned. Planning horizon is the period beyond it, requirements don't generate planned orders
    Please check and revert back.
    Regards,
    R.Brahmankar

  • MRP: Planning horizon & opening period

    hi MM Experts,
    please, explain what is "MRP planning horizon" and what is the impact on MD03 ?
    please expalin elso "the MRP Opening  period" and what's his utility ?
    both of them are in the OMI8 tcode.
    thanx in advance.
    SDA

    Hi. Hope this helps.
    Planning horizon is the Time period in days, MRP will consider the requirements for Planning. We can define this in number of days in OPPQ and/or in OPPR.
    Simply it is = Cumulative lead time + Longest batching period.
    You can define the Planning horizon in OPPQ/OPPR as mentioned above
    & under MRP group then we assign this MRP group to material master in MRP1 view.
    NETPL ( Net change planning in planning horizon) you will get it in MD02, MD01: With this processing key only material where the indicator NETPL has been set in planning calendar are planned.For example if we set planning horizon as 30 days then in the material in which MRP relevant changes happened in last 30 days will only be planned. This planning restricts the scope of planning or number of material which reduces the runtime of planning run. Planning horizon is the period beyond it, requirements don't generate planned orders.
    Opening Period is...
    Opening period is like a "release window". The length of the opening period is the window of opportunity a planner has to convert the planned order to a purchase req.
    For example - Component A has a lead time of 14 days and opening period of 5 days. Requirement on 12-22-03
    Opening Date - 01/12/09
    Start Date - 08/12/09
    Finish Date - 22/12/09
    Now the planner can convert the order starting Dec. 1st, instead of Dec. 8. It basically is a buffer in the lead time to get things on order a little sooner than needed.
    Thanks.

Maybe you are looking for

  • Zero quantity in line item when creating a sales order

    How to avoid the error when the quantity is entered as zero during sales order creation

  • How do i completely remove headers from email messages

    Hi everyone. Can someone tell me how to completely remove the headers from showing up in messages i send, forward or receive? I know how to make the headers shorter, but that's not what i want to do. I want to completely remove them from all outgoing

  • Flex air datagrid setfocus cell by cell

    Hi all, I have a datagrid with custom itemRenderer. Now I need to setfocus int the grid cell by cell. For that I Googled & got a way i.e var findrowindex:int = 0; //nextButton Click Handler var focusedCell: Object = new Object(); focusedCell. columnI

  • Can we have descriptions in an LoV?

    I have an LoV attached to a parameter that contains 55 different school codes (each code is a 3 digit number). A particular school's staff member might not necessarily know the code for his/her school, so I was wondering if it were possible to add a

  • Safari Spinning Beach Ball after 10.5.5, Camera Raw Update, and Rmt Desktop

    Safari is having real problems after remote desktop and camera raw update. Safari is totally unusable. Spinning beach ball forever and brings the entire machine to a hault. Hope someone can help with a fix soon I zapped the pram. Tried deleting safar