Hi,
The In this step, you can maintain all the plant parameters
1.Environment : Here you define the number ranges and the Backorder checking rule.
2.Master data: Like mrp controller,Speical procurment type and the Float - scheduling marging key can be configureed here
3.Conversion of planned order to productin order /Purchase requistion can be configure here
4. Planning urn : the selection of BOM ,Bom explosion,available stock etc and lot more can be configured here
Even though we have separate areas where we can define each of them separately here we can define most of the mRP related to single plant can be configured at this one.
Kindly let us know if this solves your query or if you are looking for anyother thing.
Reg
DsK

Similar Messages

  • About plant parameters

    hi
       everybody
        plz. tell me
      wat is mean by plant parameters
      whrer we maintain it
      wat functions or values we maintain for this
      wat it effects in SAP
       where we use it
       give details
       thanks in advance

    Plant parameters carries important control parameters during MRP run
    when you convert planned order into  a prod order, the order type is copied from the plant parameters (oppq>>planned order coversions)
    During MRP run ( if MRP run type is NETPL - Net Change Planning with Plannign Horizon), the planning horizon period
    is defined in the Plant Parameters (OPPQ>>Planning Run>> Planning Horizon)
    If Order start date is in the past, the system automatic does forward scheduling. In some scenarios if its ok to
    have order start date in the past then you make setting over here (OPPQ>>Planning Run>> order start in the past)
    Like wise, Special Procurements key from issuing plant are maintained in the plant parameters
    SMK is also maintained in the plant parameters
    Under the setting of Available stock, what type of stock you consider as Available stock ( like Stock in Transfer, Blockedd Stock, Restricted Use Stock) is considered  as
    available stock
    The plant parameters are maintained in OPPQ
    Also, Before maintaining MRP plant parameters, you need to activiate MRP for the respective plant in OMDU

  • Difference between To maintain and initial in plant parameters in MRP custo

    Hi, Gurus,
                  Can anyone explain me about the difference between status showing
    to maintain and initial in plant parameters in MRP customization
    Thanks & Regards
    sathyanarayana

    Dear Sathyanarayana,
    In T code OPPQ - Maintain Plant Parameters,it does not
    mean we have to maintain a value in all the parameters
    present under different tab keys.
    IF you check generally MRP controllers,Floats,Number
    Ranges,BOM/Routing Selection,Planning horizon,Available
    stock these values will be maintained.
    Some of the settings like Start in Past will be as Initial(not
    allowed in the past).
    IF you use some special procurement key,then that settings
    has to be maintained.
    I hope this will help you.
    Regards
    Mangal

  • Difference between MRP group and plant parameters

    hai friends,
    please let me know, what is the main difference between the MRP group and plant parameters?,
    what are the extra activities or features with one, when compare to the other?.
    Edited by: Mourya.v on Sep 22, 2010 6:36 AM

    Dear Mourya,
    Why to assign MRP group? - If planning for each plant is not specific enough for your purposes and you would like to assign
    control parameters that differ from the control parameters defined for the plant to certain material groups.
    1.For all materials without an MRP group, the system uses the plant parameters that is the settings present in OPPQ, or the
    entries in the initial screen of the planning run.
    2.For all materials with an MRP group, the system uses the parameters recorded in the MRP group that is the settings in OPPR.
    3.The MRP group is an organizational object that can be used to allocate special control parameters for planning to a group of
    materials. You can maintain MRP groups if planning control per plant is not precise enough for your requirements and you want
    to allocate certain material groups different control parameters from the plant parameters. For this purpose, MRP groups are
    defined with these specific control parameters and are assigned to the material in the material master record (MRP 1 screen).
    4.The MRP group, groups material from the material requirements planning point of view to allocate them control parameters for
    planning.The control parameters include the strategy group, the planning horizon and the creation indicator for the planning run.
    Also check this link [Settings in OPPQ & OPPR|oppr and oppq]
    Regards
    Mangalraj.S

  • MRP SPRO- Plant Parameters-Direct Procurement

    In the spro Plant Parameters-Direct Procurement
         Direct procurement only when creating production order
    1     Trigger direct procurement in requirements planning
    2     Direct procurement only when creating production order
    3     Trigger direct procurement in requirements planning
    Here 1,3 are seems to be same
    thanks
    K.Prabakaran

    hi
    it looks like even 'blank' & 2 are also same similar 1 & 3..
    but, options description clearly mentions the usage..
    Thanks
    JK

  • Plant Parameters

    Hi ,
    Pls tell me how to maintain plant parameters?
    And who is defining this Plant parameters PP or MM?
    Regards
    Gitesh

    Dear,
    Plant parameter you need to define in OPPQ. As it is relevant to MRP so its PP person responsibility but it is integration between PP and MM like number range for Purchase requisition. availability check etc.
    Hope clear your Doubts.
    Regards,
    R.Brahmankar

  • MRP Control Parameters

    Hi All,
    Pl. let me know where we define the MRP Control Parameters that gets displayed ,when we execute MRP(MD02), like
    Create purchase req
    1. purchase requisitions
    2.purchase requisitions in opening period
    3.planned orders
    etc.
    Normally we select these parameters while execution only.
    I want to know where these parameters are defined.
    best regards,
    Kumar.

    Hi kumaran
    As Mr.Prashob said these are internal SAP setting. like this many settings are there. For example order type category is 10 for prod order. This also you cannot change, This will execute many functions internally in SAP.
    If you want to set the indicators with respect to MRP group. you can ssign in MRP group setting.
    Regards
    J. Saravan

  • MRP Control parameters(MD02)-Regarding.

    Hi,
    Can anyone explain me what values(MRP control parameters)should i use for MRP run.
    For Eg for an 1.Inhouse produced material(FERT),
                        2.For externally procured (HALB) materials,
                        3.For Sub-Contracted items,etc
    So that i'm getting proper planned orders or Purchase requistions.
    what's the meaning for "Purchase Req.in opening Period"what's the meaning for opening period.
    Thanks & Regards
    Raj.S

    For all materials type you can run withfollowing control parameters from MD02.
    1) Processing key: NETCH
    2) Create purchase requisations: Keep 1...by doing this for F parts MRP creates PR and for all E parts MRP creates Planned orders...This will work according to procurement type. If you keep 3 "created planned orders: then MRP created only Planned orders..no PR will be created.
    3) Create scheule lines: Keep 3...if schedule lines are mainatin then scheudle lines will be created..otherwise no impact.
    4) Create MRp list: 1... to see the MRp results.
    5) Planning Mode: 1..This is better to improve the system performance . if you new data eevrytime then keep planning mode 3.
    6) scheduling type: 1...Basis dates scheduling if you are not working with capacity planning.
    If you are maintaining scheudle margin key in MRp2 view with opening period for example 10 days and in MRP control parameters :create PR in opening period" then MRP creates PRs only in the opening periods of the schsdule margin key if the opening dates of the PRs are falls within these 10 days. Otherwise MRP creates planned orders..later you can convert these Planned orders into PRs.
    If helpful rewards your points.
    Regards
    TAJUDDIN

  • Field selection for plant parameters

    In plant parameters - in external procurement tab-i want to change field selection for Account assignment for non valuated materials field to optional,.Presently it is required field
    can sombeody tell me path

    Hi
    Go to SPRO>Production>Material Requirements Planning>Plant Parameters> Carry Out Overall Maintenance of Plant Parameters and execute.  (Transcation OPPQ)
    Select Maintain and give the plant
    Select External procurement Tab and select Unknown account assignment.
    But, you need account assignment for non-valuated material for external procurement.
    Hope it solves your issue.
    regards,
    Edited by: Raju DS on Dec 4, 2008 7:47 AM

  • Consequences of maintaining Plant Parameters

    Dear All,
    I would like to know that what could be the consequences for maintaing plant parameters under ' Inventory Mangement and Physical Iinventory ' for the plant which is copid from the existing plant for which plant parameters have not been maintained.
    This is what SAP is saying (the extract is from spro implementation guide)
    Plant Parameters
    In this step, you make the general plant settings for
    Inventory Management. All settings are also contained in the individual steps of the Implementation Guide for Inventory Management. If you want to allow negative stocks in your plant, you have to set the XBKNG indicator in addition to the settings in this step. To maintain this indicator, choose the step Goods Issue/Transfer Postings -> Allow Negative Stocks in Customizing.
    Recommendation
    SAP recommends that you do not make the plant settings here, but in the individual steps of the Implementation Guide, so that the settings here are not without a context. Dependent settings are not contained in this step.
    Activities
    If you have created a plant in the enterprise structure using the Copy plant function, you do not need to make any settings.
    If you have created a plant manually, you have to create a new entry for the plant parameters.
    What should I do? Should I go for it or not?
    Thanks and regards,
    Saleel Kulkarni

    Hi,
    If you created a plant by copying the standard plant 1000 , the plant paramaters foe inventory management will automatically come to your newly created plant. N o need of creating parameters separately in inventory management. If you create the plant without copy function you  have to maintain plant parameters. I hope this will help you. Thanking you.

  • Plant Parameters in GR Conversion

    Hi All,
    During GR conversion, we got the message,
    "Plant parameters not maintained"
    Any guess which plant parameters will have effect on GR conversion?
    Thanks

    How did you create a Plant. I mean to say Whether you have created a Plant with reference to another Plant. If this is the case Plant parameters will be automatically copied.
    If you created a Plant using Create function You should maintain All the Plant Parameters in the SPRO -> IMG ->Mat Mgmt -> Inventory Management & Physical Inventory -> Maintain Plant parameters.
    Reg,
    Ashok
    Reward if Useful.

  • Carry out plant parameters

    Hi Gurus ,
    In SPRO -> MM-> Consumption based planning ->plant parameters -> carry out overall maintenance of plant parameters.
    I am copying the plant parameters from plant 'X' to plant 'Y ' . But  both of these plant are from different company codes .
    What is the impact if the two plants are from different company code ? what changes do I need to do in plant 'Y' parameters after copying ?
    Please explain in detail
    Regards,
    Saurav

    Here is used to specify plant parameters for the material requirements planning, I also don't see the potential impact which might caused by different company codes.
    In
    Enterprise Structure
    Definition
    Logistics - General
    Define, copy, delete, check plant
    You could copy plant refering to template, which has company and plant's combination.
    Regards
    Lauren

  • MRP Group Parameters VS Plant Parameters

    Is working with MRP group mandatory in MRP? If we do not maintain MRP group do we lose any advantage?

    Geetika,
    You lose some flexibility.
    OPPQ settings are plant wide.  That means that everything you set here will affect all MRP materials that are extended to that plant.
    OPPR allows you to have differing settings within a plant.  For instance, you may have different types of production orders you wish to use, depending on the material.  You may wish to use different Production order availability checks within a plant.  You may wish to allow some orders to start in past, but not others.  You may wish to have differing planning horizons or different scheduling horizons, depending on the material.  These differences can all be accommodated within one plant by use of MRP groups.
    I have seen plants set up both ways.  It really depends on the requirements of the business.  I don't make that decision until all the client's requirements have been gathered, and I am deciding how complex the solution needs to be.
    Rgds,
    DB49

  • PP- Authorization check to set plant parameters

    Hi team,
    I have created Ztransaction to maintain some plant specific parameters. I have assigned this new ztransaction to single role. Currently i have 12 plants and the user is requesting that only the respective plant users can able to maintain the entries for only the respective plant and not for all plants.
    How to implement this?
    your input will be very much appreciated.
    thanks
    psk

    Hi,
    As per my undestanding it's not fesible to define user-specific roles in SAP.
    You can have SAP process-specific roles like purchasing/production/sales etc.
    Each transaction related to above processes will have a authorization object linked to it which further will have different parameters on which we restrict the authorizations to users like plant/pur org/sales ord etc.
    So looking at your scenario, define Plant specific roles with required authorizations and assign only roles of Plants to which you think that a user should get access.
    For more inputs talk to your basis consultant.
    Hope it will help.
    Regards,
    Anup

  • In plant parameters how the start date in past will be applicable for order

    Hi All,
    Can any one explain me in detail start in past for plant parmeters (OPPQ).
    Regards
    sailendra

    Hi,
    Start date of order proposals allowed in the past
    This indicator defines that the system does not automatically switch to forward scheduling if the order start date lies in the past for determining the basic dates. With this indicator, backward scheduling is always used to determine the basic dates, even if the start date lies in the past.
    e.g Bacward scheduling type, Today date is 08.06.2009
    If u give basic finish date say 25.06.2009,and system propose you basic start date in 06.06.2009. That is 06.06.2009 is lies in past date.In this case system propose you forward scheduling.Means order basic start date is 08.06.2009 .If you don't want to system propose you for forward scheduling tick mark Start in past in OPPQ.
    Hope this clear you.
    Regards,
    Raja.

Maybe you are looking for

  • Adobe creative cloud photoshop cc download

    when downloading adobe creative cloud photoshop cc ... you are asked to open with an application? What application?

  • SOAP_EXCEPTION - Value cannot be null. Parameter name: s

    Hi All, I'm getting the following error whicle executing my soap scenaraio. "Message processing failed. Cause: com.sap.aii.af.ra.ms.api.RecoverableException: SOAP: response message contains an error XIAdapter/PARSING/ADAPTER.SOAP_EXCEPTION - soap fau

  • Control strip disappears

    When I click on a video link, the video will appear on another control and will be played. If I click the link again, the video is playing but the control strip does not appear. What seems to be the problem? The control strip appears the first time.

  • Skype Number - Recurring Charges

    Hello Skype Team, I have just bought my new Skype Number that I have to use for 2-3 months only. When I go to Manage Feature >> Settings, it says that my next payment shall be made in August, 2014 whereas I dont want the recurring payment to occur. P

  • Parameters fields - how to disallow entry of non-valid business days (i.e. Sundays or holidays)

    <p>Hello,  </p><p>I'm new to Crystal Reports and was wondering if anyone can advise on using Parameter Fields and Dates. </p><p>I'm developing a report where users will be prompted to enter an "AS OF" date. Because this report is based on the US Dome