MRP PR - As per Quota

Dear All :
We are runing MRP , want to generate PR as per source list  , quota arr.
I defined source list  , quota arrangement , source list activated in mm master.
Auto PO indicator in vendor master activated.
PR getting generated.
my question is :
1) whether i have to run me56 to assign source of supply to PR every time?
2) Can MRP itself generate PR which having assigned source of supply ?
2) system creating single PR , if in quota arrangement if i mentioned 2 vendors 70% and 30% share , how to assign single PR in two vendors  through me56 OR
3) how to generate source assigned two PR through MRP with help of Quota defined.
Vijay Vadgaonkar.

Problem pending ?

Similar Messages

  • MRP Rescheduling Error with quota arrangement

    Hi i have a problem when using a Quota arrangement in MRP. When i use NME59N to order,the system proposes to bring the first vendor 100% for a month and then the next supplier for a minimal share the following month. the quota is available clearly in PR'S but when converted to PO'S the rescheduling takes the first po as a referrece instead the assigned PR'S.Can any one help me sorting out this?

    When you run ME59N you will convert the requisitions inot POs (the same requisitions that you see in MD04). The vendor assignment is not modified by ME59N. This is already done by the Quota when the MRP runs.
    In ME59N you can control if each requisition will be converted into a single PO, if multiple requisitions are going to be joined and converted into a single PO, etc.
    I am still not sure if your problem is with ME59N or what you don't like is how the vendor is assigned (considering the Quota) when the MRP is executed? If you see in MD04, is the assignment correct? if the vendor assignment that you see in MD04 is not what you want.. then we should find a solution working with the Quota and with the MRP paramenters. Is your problem the vendor assignment that you see in MD04?
    Thansk and Regards,
    Mariano Cabalen

  • Subcontract MRP Area with quota usage - urgent

    We have a subcontractor supplying assembly X which in turn require us to supply component Y to the subcontractor. We have two vendor for supplying component Y to subcontractor. Scheduling agreement with component vendors are set up for direct delivery to subcontractor. Both the scheduling agreements are included in the source list with MRP indicator 2. Quota arrangement is set up for the component.
    We have set subcontractor MRP area and assigned the same to component Y material master. Special procurement key 20 is assigned in subcontractor MRP area. Quota usage and source list are duly enabled. Quota usage indicator is 3 which provides for MRP, PR, schedule line etc.,
    When we run MRP ffor component Y for subcontract MRP area, system is generating schedule line for but without update quota file. Further, the scheduling agreement picked up is not of the correct vendor as per Quota logic.
    Does SAP support quota usage with subcontract MRP area. If not, is there a work around.
    Shall appreciate urgent response

    Dear Ravi,
    you will get a seperate location product for your material. MRP areas in apo are represented by a seperate location (type 1007 = storage location mrp area). You can transfer your ecc mrp areas via cif (CFM1). The master data you maintain in mrp section of the material master in R/3 will be trasfered to that location product. Furthermore you can maintain it manually in apo MAT1 (location = name of your mrp area). That technique provides you the possibility to maintain different parameters for the plant and the mrp area.
    Kind regards,
    Christian

  • QUOTA ARRANGEMENT IN MRP

    Hi,
    We have three vendors a,b and c with the quota arraangment 5,3 and 2 resp.In MRP lot size is fixed for 1000 qty, reorder point is 150 , Now stock availiblity is 50 in mrp PR is generated for 950 qty. How the system distributed the requirment to these vendors? What are the config steps to be taken in this scinorios. pl guide me in detail.
    will reward points accordingly,
    Regards

    Hi,
    Pl. follow following steps -
    1) Maintain quota of each vendor in transaction MEQ1 with a validity period. e.g. For first vendor 50%. For Second Vendor 30%. Third Vendor 20%. You can also maintain minimum quantity splitting, so that the quantity calculated by MRP which is below this will not be split. For example, if you require 10 PC of material & min. qty aplitting is 50, then the qty 10 will go to first vendor. If qty more than 50 is detected, then only it will be splitt among the vendors as per quota.
    2) For splitting the quantity as per quota, you have to select proper lot size (For example FS - Fixing & Splitting) & maintain tick at 'Split Quota' for the lot size in your system customization for the lot size. You can access the customization in following way -
    SPRO --> Production --> Material Requirement Planning --> Planning --> Lot size Calculation --> Check Lot sizing procedure --> MRP Lot Size
    Select your required lot size & select icon 'Details'. Then mark tick at 'Splitting Quota'. Save the changes. Then run the MRP. System will now split the quantity based on your quota arrangement.
    G.Ganesh Kumar

  • MRP run on basis of lot size

    Dear all
                    I have two different lot size routing for a inhouse product are 0-2000 and 0-1500 nos . I planned for 5500 nos  , after MRP run system should create planned order as per selection of lot size as 0-2000 for 2 planned order and 0-1500 for 1 planned order .is it possible ?
    thans in advanced
    regards
    siva

    Dear,
    Quota arrangement can be used if the demand (100) is created in which is define the ratio 60:40 but it will create two planned order after MRP Run. Go to transaction MEQ1 maintain a quota arrangement for this material. In MRP 1 view choose lot size with quota splitting and in MRP 2 view maintain quota usage as 4.
    Refer this thread
    Re: Quota Arrangement
    Please try and come back.
    Regards,
    R.Brahmankar

  • Source List - MRP Run

    Hi all ,
    In our production server Source List is maintained for a material .
    The first line contains a vendor ( say Vendor1 ) with MRP relevant indicator 1
    2nd line contains another vendor (say vendor 2 ) with fixed indicator checked and MRP relevant indicator as 1 .
    1)For both vendor the date range is same
    2)No quota arrangement exists .
    But while MRP run for that material Vendor1 is automatically assigned instead of vendor 2 . (althoug vendor 2 is Fixed )
    What may be the reasons ?Please suggest .
    Regards,
    Anupam
    Edited by: Anupam Halder on Aug 10, 2009 8:23 PM

    Hi,
    System doe not take care of "fixed" indicator in source list during MRP run as per OSS note 668764:
    1. Question:
    The fixed indicator is set for a source list record. Is this source list record preferred for a planning run?
    Answer:
    Only the source list records, for which the indicator 'Source list usage in materials planning and control' is set, are taken into account during a planning run; the fixed indicator is of no importance here. See Note 206684 for more information.
    Please also check the mentioned OSS note (206684)
    Regards,
    Csaba

  • Multiple Requisition  line itme for Quota arrangement

    Hello
    We are maintaining the quota arrangement master data .
    The Purchase requisition is splitting in to two line items based on the demand and assigning the Vendor on it .
    Is it the right way or some thing missing in the configuration
    Please advice me
    Thanks
    Nick

    Hi,
    1) The creation of PR depends upon the lot size you have maintained in the material master record.
    a) If you have maintained lot size as FX (Fixing & Splitting) & the splitting indicator is maintained for the lot size in customizing, then seperate PR will be generated for each vendor maintained in quota, with quantity alloted to the respective vendor as per quota arrangement & delivery date being as per requirement of the material (probably being same for all PRs).
    b) If you are using other lot size (which does not have the splitting indicator) then one PR will be generated for each demand, which will be assigned to the first vendor in line as per quota arrangement. Next PR (probably after next MRP run) will be assigned to another vendor which will be next vendor as per the quota arrangement.
    2) Regarding firming, these PRs will not be firmed automatically. If required, you will have to firm the same manually.
    Regards,
    Prashant
    - Pl. reward points if the answer is helpful to you

  • Reg : Quota Arrangement

    Hi Gurus,
    I have made the settings for Quota arrangement.
    I have used 3 Vendors and made the settings in Quota arrangement.
    When i am creating the Purchase requisition, the system is suggesting 3 Vendor names.The particular vendor name is not getting selected Automatically. I have to select that Manually.
    Please advice what setting needs to be done for making them getting picked up automatically as per the Quota settings.
    With Regards,
    Saakithyan

    Quota arrangement is used for PRs created during MRP. System considers the quota arrangement while creating PR during MRP & assigns the source to the vendor from quota arrangement as per the quota calculation. If the lot size allows splitting of quantity then the PRs with split are generated on the sources as per quota arrangement.
    The Quota Arrangement is not at all considered for Manually Generated PRs

  • SL not getting generated via MRP

    Hi,
    Unable to generate schedule lines via MRP.
    Settings:
    Mat master - External proc , no spl proc
    OA - Maintained
    Source list - Maintained MRP Relevant - Indicator 2
    Quota arrangement- Exist with only 1 vendor(same as of OA) 100%
    MD03 - Planning data - Create PR (indicator-1), Create Sl(indicator 3)
    Please let me know whether there is anything else which influence SL generation.

    Resolved

  • Generate schedule lines via MRP

    Hi,
    Unable to generate schedule lines via MRP.
    Settings:
    Mat master - External proc , no spl proc
    OA - Maintained
    Source list - Maintained MRP Relevant - Indicator 2
    Quota arrangement- Exist with only 1 vendor(same as of OA) 100%
    MD03 - Planning data - Create PR (indicator-1), Create Sl(indicator 3)
    Please let me know whether there is anything else which influence SL generation.

    Hi,
    hi,
    1. Mark checkbox source list in material master.
    2. purchase info record for the vendor & material combination
    3. source list for the material - mention the scheduling agreement and mark as mrp relevant, schedule lines generated
    4. Use MD03, choosing 1 for purchase requisition, 3 for schedule lines and planning mode, prerequisites requirement exists for material. If requirement does not exists it will not create scheduling agreement line.
    I  hope you got all your answers. so kindly close this thread.
    YB

  • Mrp run to do  for different numbers in a sale order

    Dear Sir,
    we are doing make to order planning strategy 20  and receiving sale order on august 2008 of 7 nos and delivery date  is of 21 july 2009.
    my  client needs to do mrp run  as per the client planned date  , but in md04 the sale order is showing of 7nos .
    the client planning date are as follows  to do mrprun :
    31st May 2009 - 2 nos
    30th june 2009 - 2 nos
    21st july 2009 - 3 nos
    so I kindly request you to help me how we can do the mrprun as per the client planning date and also what is the flow  path to be done.
    In making a finished product we are giving packing as outsourcing ( i.e. labour coming from outside getting wood and othermaterial for packing )  for this how can i show in the routing of packing.
    regards,
    muralidhar.t

    Muralidhar,
    Let me understand, on what basis the client decides to run MRP for Schedule Line 3 & 4? Is is based on the deliveries for the next 2months and the other schedule line are behyond 2months from now?
    Though your scenario is not clear, with my little understanding I can suggest couple of options,
    1. You can define Planning Horizon for the Plant say for example "60" - Days, and then your MRP run can be with "NETPL"- Processing key in MD01. What this means is that deliveries or requirements which are falling within this 60days will only be planned.
    Planning horizon should be configured in the MRP - Parameter Master data section in SPRO.
    2. For all the schedule lines you can change the Schedule Line category to "CN" instead of "CP". CN related schedule lines are not considered in MRP for planning.
    Regards,
    Prasobh
    Regards,
    Prasobh

  • Tables relevant to MRP, MD04  tcode and stock related tcodes

    Hello gurus,
                 table related to STOCK, MRP, AVAILAIBILYT CHECK AND TOR, MD04 Tcode
    Thanks in advance
    Sameer

    hi
    for stcok
    MARC, MARD,
    MSKA     Sales Order Stock
    MSKAH     Sales Order Stock: History
    for MRP
    MDIP     Material: MRP Profiles (Field Contents)               
    MDKP     Header Data for MRP Document               
    MDKPDB     Header Data for MRP Document               
    MDLG     Customizing: MRP Area Storage Location               
    MDLL     Customizing: MRP Area Subcontractor               
    MDLV     Customizing MRP Area               
    MDLW     Customizing: MRP Area Plants               
    MDMA     MRP Area for Material               
    availabilyt check
    TMVF     Availability Check Control
    TMVFP     Availability Check: Blocks
    TMVFT     Availability check control: Texts
    TMVFU     Scope of Availability Check (Default Values)
    TMW00     MRP Default Values per Material Type
    for MD04
    VBBE     Sales Requirements: Individual Records
    VBBS     Sales Requirement Totals Record
    UMD04     Default Values for Planning Table in Repetitive Mfg

  • How to run mrp and capacity leveling through heuritics.

    Hi,
    How to run mrp and capacity leveling through heuritics.
    What are the setps required for production planning run this thing in the heuritics in pp/ds?
    Regards,
    Sunil

    Sunil,
    APO PP/DS doesn't have a 1-to-1 match for MRP/Cap levelling per se.  There are, though, a limitless number of ways to achieve the results you want.
    Start with a basic PP planning MRP - SAP_PP_002, which will should create all necessary planned orders
    Then try a DS heuristic to schedule your orders according to capacity.  Schedule Sequence SAP001 is a good starting point.  This can be used to schedule your cap relevant work centers such that they fully load the capacity available, similar to cap levelling.
    Rgds,
    DB49

  • Problem with Sickleave quota

    Hi Experts,
    My employee is entitled for 6 days of Sickleave quota for the fiscal year 2011-12.
    Somehow by portal he took 10 days sick leave.How the system allowd to take 10 days leave.
    The reaming 4 days has been taken from Casula leave quota.
    How to restict the system to use the leaves as per quota.
    Please advice,
    Sairam.

    HI Satya,
    as you said sick leave quota is taking leaves form casual leave quota.
    then there should be a link between sick leave and casual leave
    check in table V_556R_B for the following:
    1) Is casual leave and sick leave are maintained in this table.
    then automatically after the completion of sick leave then casual leave starts gets deducting.
    If you donu2019t want the leaves deducted from casual leave quota after sick leave quota is complicated then remove the casual leave from here and maintain separate deduction rule for it.
    2) second possibility is might be in table V_T556A negative deduction is maintained for the sick leave quota .I f you remove this i think leave quota  cannot be exceeded the limit.
    3) check with the validity and deduction rules in table V_559D .
    4) Might be a BADI is writen in such a way that the after compleating the sick lev quota directly it is takin quota from CL.Check with your ABAP  person once.
    Please correct i f i am wrong.
    Thx
    Jinnu

  • FG in MRP AREA and ROH comoonents are in different MRP AREA

    Dear consultantas,
    please i need to check this scenario with you if applicable or not:
    i have ine plant 0001 and i created 2 MRP Areas 0001 (plant MRP Area) and 0002 (storage location MRP Area)
    my finished product is planned in MRP Area 0001 and its components (in BOM) are planned in 0001 MRP Area.
    do you think this scenario is applicable.

    Hi
    You can map this business process very well in the standard SAP .Only thing is you have to make sure that both the MRP area are activated for MRP  and Planning file entry to be done foe those FG and componenet which are in different MRP area .You can include them in SCOPE of Planning in the configuration and run MRP in MD01.Or u can run MRP in two different MRP area as per your requirement .
    Hope this will help you .
    Regards
    JH