Hello,
Here I am using strategy group 20 for header materials but for raw materials I would like to group together multiple requirements from many sales orders and raise one planned order for the same. Is there any way this can be achieved?
Sincerely,
Aji
for raw material maintain collective indicator in MRP 4 view, it will combine the requirement and give single plan order
Similar Messages
-
How to write a requirement for sales order outbound iDOC
i need to write the requirement for sales order IDOC
Please helpHi
From the sales order screen itself you can create the delivery from the menu
Sales order -> deliver/y
or from VL01N , enter shipping point and Order number, create and save
Reward points if useful
Regards
Anji -
MRP-Delivery Schedule for Sales order is not updating in Production order
Dear Experts,
I have created Sales order and maintained delivery scheduling, Then Run MRP through MD50,
We received Planned order then through this we have converted to Prodcution order.
When we observe the delivery schedule for sales order under assignment Tab in Produciton order which is showing zero instead showing line item of Delivery schedule.
I am able to see Sales order and Line item but i am not abel to get any delivery schedule line item.
Please suggest where settings are missing.
Thanks in advance
Regards
DonDear Experts,
Please provide me solution.
after Running MD50 transaction against Sales order.
If I maintained different Scheduling Line Item for First Line item of Sales order.
The Respective Scheduling Lines should update against Each Production order which has converted from Planned order.
Thanks in advance.
Regards
DON -
BOM business requirement for sales order and PGI
Hi Experts,
Current setting
The BOM structure is A = A1+A2
1) Material A created in MM master item category group = ERLA
2) Sub component material A1 and material A2, MM master item category group = NORM for both component.
3) Maintained in CS01 BOM header is A and items are A1 and A2.
4) Item category in IMG was created and assign item category also created.
4.1) OR-ERLA-TAQ-TAE
new business requirement as listed below.
5) The material A is alway zero quantity on hand, no goods receipt required with no physical with such material or package at all. (it is dummy material number in SAP).
6) while SO created.
6.1) Fro material A sales price captured at BOM header level only, NO QTY and COSTshow in the sales order.
6.2) Material A1 and A2 are actual physical inventory item in the ware house.
6.3) The sub component of material A1 and A2 is required to captured QTY and COST. NO SALES PRICES NEEDED.
CONCLUSION
HOW to setup/configure such a business scenario?
- Is it logic to configure as OR-ERLA-TAE-TAN that's what i think of?
My problem is how to make the material A is alway ZEROS stock on hand and allow in sales order creation with ZEROS order qty?
MATERIAL QTY COST SALES NET VALUE
A 0 0 1,500.00
A1 1 100.00 0
A2 1 50.00 0
Thanks & Regards,
Yong Kok Wah
Edited by: Yong Kok Wah on Jan 27, 2010 11:16 AMAs per your post,
- You are creating Main item which is a dummy material without any physical inventory maintained, but the pricing/billing should be done @ main item level.
- here you are not dispatching main item, but billing should be carried at this level. in such case, I suggest you to go with the new sch.line cat w/o maintaining any mov type to it. & use Zitem category for this main item in VOV7, mark "Order qtty=1" so that min order qtty for this main item should be 1, so that you can calculate price.
- You want to capture Cost of sub items , summation of sub items cost is total cost of main item & Profit will be calculated accordingly.
Sub items, sch.line category should have mov type, item cat should be not relevant for pricing & billing , but relevant for sch.lines. In Copy control from delivery - Billing @ item level, for the main item ,- item category, choose "Cumulate cost", so that cost of the sub items will be cumulated to main item.
eg:
MATERIAL QTY COST SALES NET VALUE
A 0 0 1,500.00
A1 1 100.00 0
A2 1 50.00 0
My problem is how to make the material A is alway ZEROS stock on hand and allow in sales order creation with ZEROS order qty?
To avoid this, mark order qtty=1, in item category for main item, but for the same item, sch.line category should not have mov type. so that there will nt be any PGI document. But PGI should be done for sub items to capture inventory & cost.
Test & revert, if any issues. -
BADI or Exit Required for Sales Order
Hi Experts,
In the sales order, when i entered the item, depend upon the pricing determination I need to display message with condition base value and a popup should be automatically raise with 3 variants.
Can any one suggest me the suitable BADI or Exit for this.
Thanks in Advance.Hi,
Can please elaborate more about your question.
Regards
Goutham -
Pricing Details Required for Sales order Item
Hi Gurus,
I have a requirement to get pricing details of sales order line item to be displayed on smart form.
Please let me know the tables which i need to refer to get the pricing details. Please let me know how I can link those tables from VBAK or VBAP.
OR
Please let me know if there is any function modules to get the pricing details of sales order header / item
Regards
AviHi,
Check with the below table
Table : VBRK, VBRP, VBFA, KONV tables.
In VBRK and VBRP you can link with VBELN field. In VBFA table you can link with VBELV fireld.
Regards
Thiru -
MRP is conflicting with Sales order requirement Qty and date
Hi experts,
We have below scenario:
Material has the stock 100. It has reorder point 3 and MRP type V2 (Automatic reorder point with external requirements) and planned delivery time 10 days.
MRP run creates purchase requisition whenever the stock falls below reorder level or/and based on customer orders requirements.
We created first sales order for Qty 80 and delivery date 03/01/2012. Qty 80 is confirmed against this sales order.
We created second sales order for Qty 50 and delivery date 01/31/2012. Now remaining Qty 20 is confirmed against this order. So we have requirements of 30 Qty for this second order.
When we run MRP, it supposes to create Purchase requisition for Qty 33 (30 + 3) including reorder point (3 Qty). As the delivery date for this order is 01/31/2012 and requirement Qty is 30, and planned delivery time is10 days, MRP run should create purchase requisition. But it is not creating.
If I change the planned delivery time to 30 days, it is creating purchase requisition. It is considering sales order delivery date of First order (delivery date: 03/01/2012), but not for second order (delivery date: 01/31/2012).
So MRP is conflicting with Sales order requirement Qty and date.
Appreciate your help in this regard to resolve the issue
Thanks,
SriniHi,
We are using manual reorder point planning with external requirements (V1)
Thanks,
Srini -
Dear Friends,
I want to run MRP based on the sales order delivery schedules. My sales orders are spread for the next 2 years.
For example for material A, I am having sales order for 40 quantity (item 10) and material B -20 quantity (item 20). My sales order delivery scedule is defined such away that each month I may required to send 4 items of material A and 2 items of material B starting from March 08.
In this case I need not to consider all the quantity. I want to run my MRP for which I need to deliver for the next 3 months period.
If you need any further clairification, please let me know.
Regards,
Surya.Dear Surya,
Make sure that the scheduleline in the sales order are having 4 qty of A and 2 qty of B for each month as below
Schedule line of A
31.03.2008 - 4 qty
31.04.2008 - 4 qty
31.05.2008 - 4 qty
Schedule line of B
31.03.2008 - 2 qty
31.04.2008 - 2 qty
31.05.2008 - 2 qty
Make sue that your planning horizon is only one month. and you are running MRP with NETPL option.
This with consider the sales order line item schedulelisewise and give planned order only for one month.
i hope u got it -
Using MD50 to run MRP for Sale Order
Dear all,
I have some problem when using MD50 with Mill Product Industry.
When SAP system not activate Mill Product yet. I used transaction code MD50 to run MRP for Sale Order, the system have generated planned order for multilevel. But when SAP system have activated Mill Product, I used transaction code MD50 to run MRP for Sale Order, the system only generate planned order for single level. I think that we have to configure something based on Mill Product Industry. So can you help me for this
Thanks, RegardsHi,
Check with following links which may help you resolve your issue :
http://www.sap.com/sme/whysap/industries/millproducts/index.epx
http://help.sap.com/saphelp_di471/helpdata/en/4e/1796374b088e5ce10000009b38f8cf/frameset.htm
http://help.sap.com/content/documentation/industry/docu_is_mill.htm
Regards,
Tejas -
Execute MRP for Sales Order with selected Warehouse
Hi Experts,
When we execute MRP Scenario which include Sales Order. Can MRP only include Sales Order by Warehouse?
For example:
1) We include existing stock for Warehouse-A in MRP Scenario.
2) We include Sales Order in MRP Scenario.
3) We have two Sales Order created, 1st SO is taking from Warehouse-A; 2nd SO is taking from Warehouse-B.
4) I notice that both Sales Order Qty will appear in MRP simulation.
Is there any place to configure to resolve this problem?
Thanks.
Regards,
Lay ChinHi Lay Chin,
By the current B1 design, MRP is only working on the item level. That means it consider all on hands in regardless of warehouses. It is not configurable to warehouse level.
Thanks,
Gordon -
Steps for sales order to MRP Run
Dear all,
Could you please explain what are the steps to process after creating sale order to run MRP and delivery?
Regards
RajasekaranHi Rajaseshekhar,
Following will be detailed end-to-end process steps.
Create Sales Order Entering Finished Goods Material
Master
Auto Generate Alert(E-mail) to Production Planner
Create ‘Order BOM’ by Copying Finished Goods BOM (Sales
Order Item). Amend by deleting/adding Items in Order BOM at all levels
Auto Generate Alert(E-mail) to Product Cost Controller
Recalculate 'Sales Order Costing' to reflect changes to ‘Order BOM’
Auto Generate Alert(E-mail) to Production
Run Sales Order MRP
Convert Planned Order to Production Order
Capacity Leveling
Release Production Order
Pick Components (Picking List)
Confirm Assembly Activities
Post Goods Receipt (Production Order)
Delivery Processing for Sales Order
Create Invoice
Hope ite helps,
Jatin -
Crystal Reports for SAP Print Output requirements like Sales Order O/P
Hello,
Has anybody used Crystal Reports for Sales Order or Invoice Print Output type requirements?
Typically these outputs get triggered via Output Management Configuration on Save of a Sales Order or Configuration.
Traditionally in the Output Management configuration of say Sales Order, we can specify the "Output Program" and the "Sapscript" or "Smart Form" or "Adobe Form".
How do we tell SAP t trigger a Crystal Report output if it is a feasible way to go?
Also can anybody tell what is SAP's strategic direction for Print Output requirements?
regards,
AtulHi Atul,
Do you have answers for your questions? If so, could you please share?
Thank you in advance,
Joã -
How to get the back order quantity for sales Order
Hi Friends,
I want to get the back order quantity for sales order . in MD04 t-code,
there is a field(MDEZ-MNG01) for Received Qty/ Required qty. But MDEZ is a structure.
I tried from MDTB table, but the table is not updated with the values in MD04.
Please guide me from which table I can get the back order Qty for sales Order
(ref: t-code MD04, MRP element = CusOrd).
Thanks,
Sagar>
VIdya Sagar wrote:
> Hi,
>
> Isn't there any difference b/n Open Sales Order and Back order??
Yes Quite Difference.
Read:
http://www.sap-img.com/sap-sd/explain-the-meaning-of-an-open-sales-order.htm
http://help.sap.com/saphelp_sbo2005asp1/helpdata/en/b6/bdb9b2f02842348c9edbe78af863c4/content.htm -
Outbound message control for sales order SISCSO.
Hi...
I am trying to generate IDoc for Sales order using message control. The IDoc of type SISCSO is getting generated as per the requirement.
I want to calculate certain things before generating IDocs. I have done the following configurations:
1. A function module 'ZIDOC_OUTPUT_SALES_ORD' is created with interface same as 'IDOC_OUTPUT_ORDRSP'. (Where i am planning to write a code)
2. WE57 where Function module is assigned to SISCSO as outbound FM.
No BD51 is done as it is only for inbound process.
3. New process code ZSO is created through WE41, which is made message independent and FM created in step 1 is assigned to it.
4. In WE20 , this process code is attached to V1 type of application under message control.
Still, my FM is not getting called... I have checked it by applying Break point as well as raising exception in the FM. But still it's not working..
Where am i going wrong??
Can anybody suggest solution??
Thanks,
Audy.Hi,
You need to use FM : MASTER_IDOC_DISTRIBUTE to create outbound idoc.fill the data in the tables EDIDC,EDIDD and generate the IDOC.
check this link:
Re: Master_IDoc_Distribute
and use transaction : WEDI for IDOC configurations.
here you will have all the transactions(step by step) to set the outbound IDOC configurations.
Regards
Appana -
How can we identify what are all user exits are there for sales orders,deli
Dear All,
How can we identify what are all user exits are there for sales orders,deliverys and invoices
thanks
nitchel vHi Nitchel
There are many ways to find out the user exits..
For example for VA01.
Goto Transaction ie VA01:
goto System-- Status
doubleclick on the program name ie SAPMV45A
SE38 -> Enter the program name and in the program( SAPMV45A) goto -- attributes
get the package name from here ie VA
note the package(VA) and get back to main screen
goto SMOD tcode and click on find button in the package spec giv the package name ie VA and execute it
you will find list of exits available
check out the exit that suits ur requirement
goto cmod and create a new project and implement in that user exit.
You will get the following exits in SMOD..
SDTRM001 Reschedule schedule lines without a new ATP check
V45A0001 Determine alternative materials for product selection
V45A0002 Predefine sold-to party in sales document
V45A0003 Collector for customer function modulpool MV45A
V45A0004 Copy packing proposal
V45E0001 Update the purchase order from the sales order
V45E0002 Data transfer in procurement elements (PRreq., assembly
V45L0001 SD component supplier processing (customer enhancements
V45P0001 SD customer function for cross-company code sales
V45S0001 Update sales document from configuration
V45S0003 MRP-relevance for incomplete configuration
V45S0004 Effectivity type in sales order
V45W0001 SD Service Management: Forward Contract Data to Item
V46H0001 SD Customer functions for resource-related billing
V60F0001 SD Billing plan (customer enhancement) diff. to billing
For Delivery you will get .. here the package name will be VL.
V02V0001 Sales area determination for stock transport order
V02V0002 User exit for storage location determination
V02V0003 User exit for gate + matl staging area determination (h
V02V0004 User Exit for Staging Area Determination (Item)
V50PSTAT Delivery: Item Status Calculation
V50Q0001 Delivery Monitor: User Exits for Filling Display Fields
V50R0001 Collective processing for delivery creation
V50R0002 Collective processing for delivery creation
V50R0004 Calculation of Stock for POs for Shipping Due Date List
V50S0001 User Exits for Delivery Processing
V53C0001 Rough workload calculation in time per item
V53C0002 W&S: RWE enhancement - shipping material type/time slot
V53W0001 User exits for creating picking waves
VMDE0001 Shipping Interface: Error Handling - Inbound IDoc
VMDE0002 Shipping Interface: Message PICKSD (Picking, Outbound)
VMDE0003 Shipping Interface: Message SDPICK (Picking, Inbound)
VMDE0004 Shipping Interface: Message SDPACK (Packing, Inbound)
For Billing VF01..Package is VF..
SDVFX007 User exit: Billing plan during transfer to Accounting
SDVFX008 User exit: Processing of transfer structures SD-FI
SDVFX009 Billing doc. processing KIDONO (payment reference numbe
SDVFX010 User exit item table for the customer lines
SDVFX011 Userexit for the komkcv- and kompcv-structures
V05I0001 User exits for billing index
V05N0001 User Exits for Printing Billing Docs. using POR Procedu
V60A0001 Customer functions in the billing document
V60P0001 Data provision for additional fields for display in lis
V61A0001 Customer enhancement: Pricing
Or another way is ..
- Get the program name for that T-Code
- Go to that program
- In that program, search for word 'EXIT' or 'CUSTOMER-FUNCTION' by using where-used list which will give u the list of user exits for that program
And also you can check in the tables in SE16 for user exits..
MODSAP - Stores SAP Enhancements
MODSAPT - Stores SAP Enhancements - Short Texts
MODACT - Stores Modifications
And there are other ways as well , pls check the forum for this ,
Regards,
Vvieks
Note : If you have any specific requirement then pls let us know , we will guide you
Maybe you are looking for
-
Help me sync all my iPhone's tabs with Mac - beginning to despair!
Hi, iPhone 4S 16GB, White, iOS 6.0.1; Mac Pro 2010, Mountain Lion 10.8.2 Supplemental Update 1.0; iTunes 10.7 (I am NOT upgrading to iTunes 11). I can't get all the aspects of my iPhone to sync with my Mac Pro without receiving the dreaded, "Do you w
-
FM or BAPI or BDC for clearing open items...
Hello Gurus, I have to write a code to clear/ close 12 million open G/L items in SAP. Is there a standard SAP FM or BAPI to do this ? Or do I have to write a BDC for this. If I have to write BDC, do I write BDC on T-Code F.13, FB05 or other T-Code. R
-
hi Folks, I am trying to release any request and I get the following error message: ERROR: Buffer check failed I've already checked the files permissions, updated the tp, re-configured the Route (my scenario the route is a single one). Please, please
-
i hav created the PR bt nt able to release it. it says tht PR cannot be released. Could u tell what r the possible resons? Thanks, Krutika
-
Hi, In my laptop wi-fi is not working. When I troubleshoot it,it says "The window wireless service is not running on this system not fixed" Please tell me how to fix it.