Hello all. I have this situation.
I have material X with two storage locations: SL01 and SL02. Storage location SL01 has 15 pieces and SL02 has 5 pieces. In MD04, I can see a total of 20 pieces under the "Stock" MRP Element.
Material X also has five Order Reservations (OrdRes), for 5 pieces each. These Order Reservations are assigned to Storage Location SL02, because stock is procured from there.
What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
I tried deactivating SL02 in Material Master MRP4 for material X, but then the MRP Run doesn't generate any proposals because my reservations are in SL02, and it's deactivated. Even if my Availability Check is set not to look at "storage location", if I the requirement is in SL02, it won't propose anything.
Is there any other solution to my problem? How can I have the system ignore the stock in SL02, but still propose those 5 pieces I'm missing in SL01?

I have material X with two storage locations: SL01 and SL02. Storage location SL01 has 15 pieces and SL02 has 5 pieces. In MD04, I can see a total of 20 pieces under the "Stock" MRP Element.
Material X also has five Order Reservations (OrdRes), for 5 pieces each. These Order Reservations are assigned to Storage Location SL02, because stock is procured from there.
What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
Sorry, but your logic is not clear to me...
your stock:
5 pcs (SL02) + 15 (SL01) = 20 pcs
your requirements
5 x 5 pcs (SL02) = 25 pcs
Procurment proposal (w/o excluding SLoc):
20 pcs (stock) - 25 pcs (requirements) = -5 pcs > procurement proposal 5 pcs
You are saying:
What I want is to have the "Stock" line only show me the stock of SL01 (Stock = 15 pieces). I want SAP to "ignore" whatever it has in SL02 and only consider the stock in SL01, so MRP Run would give a proposal of 5 pieces.
So, you can see MRP will give a procurement proposal of 5 pcs without any SLoc exclusion...
Please clarify your requirement / business process. Why don't you want to consider the stock in Sloc2? What is your process?
You can see that you cannot exclude a SLoc with Sloc MRP and still consider the requirements relevant to that SLoc (unless you use reorder point planning in that SLoc).
Thanks,
Csaba

Similar Messages

  • During MRP run unwanted plant and storage location include and exclude

    Hi There,
    During MRP run how to include and exclude the unwanted plant and storage location pls let me know the required configuration settings.
    Thanks in advance.

    HI,
    To control whether a particular storage location will be included or excluded from the MRP run.  (MD02/MD41).
    To exclude it from MRP run :-
    OMIR - Define storage location MRP per plant
    Put the MRP ind. as.         1 - storage location stock excluded for MRP
    To include it from MRP run:-
    OMIR - Define storage location MRP per plant
    Put the MRP ind. as.      space - storage location stock also planned at plant level and save it
    Next go to transaction MM01 - tick only view MRP 2
    Key in Plant and Storage Location
    Look at the Storage Location MRP section
    change the SLoc MRP indicator to space  and save it
    MMD1 - Create MRP Profile - MRP profile is a useful entry aid and makes it easier to manage MRP data.
    You define which fields are filled with values when MRP data is entered in the material master record, which of these values can be overwritten and which not.   You use the information stored in a profile is standard information that is needed again and again in similar constellations when material master records are maintained.
    Regards
    KK

  • Excluding storage location from MRP run in Long Term Planning

    Hi,friends,
         In my scenario , i want to exclude storage location from MRP run in long term planning.When i set storage location MRP indicator "2" in SPRO and SLoc MRP indicator "1" MRP4 in material master, i can exclude the storage location after run MRP with MD01/MD02,and i can see the expected result in MD04.But in Long Term Planning scenario the storage location can not be excluded after run MRP with MS01/MS02,and the requirements list in MS04 include the stock in the storage location i want to exclude. i dont know if i miss something.Plz give me some advice.
    Regards
    Joey

    Hi,
    Refer the OSS Note 208017 - LTP: Long-term planning and storage locations
    ==========================================================================
    Symptom
    In long-term planning (Transactions MSBT / MS01 / MS02 / MS03), the MRP indicator of a storage location for a material is not taken into account (material master, view MRP 2 [up to and including Release 3.1I] or MRP 4 [as of Release 4.0A]).
    The storage locations excluded by MRP or planned separately are also planned in the plant segment.
    Additional key words
    LTP, MM01, MM02, MM03, master data, MRP indicator, LGORT ...
    Cause and prerequisites
    The MRP indicator for a certain storage location of a material is only taken into account in operative planning (requirements planning, MRP).
    The long-term planning occurs exclusively at plant level.
    Solution
    This is no error. The system works as intended.
    The individual storage locations should not be distinguished in the long-term planning, in order to perform a comprehensive long-term planning.
    This is important, for example, within the kanban processing where the storage locations with kanban MRP are excluded from the MRP, but in spite of that should be included in the long-term planning.
    ==========================================================================
    Regards,
    Siva

  • MRP run by excluding storage location

    Dear PP experts,
    I have excluded storage location e.g. storage location 0001 from MRP in OMIR and also maintained the same in MRP 4 view in material master. As far as MRP run is considered system is ignoring the stock and giving the results.
    But now we are facing the problem in quantity confirmation in sale order in transaction code CO06. The stock is existing in storage location 0001and is not confirmed for any other sale order.
    We need to exclude the storage location in MRP but it should allow stock determination in sale order.
    Pl. let me know how this can be achieved.
    Thanks in advance,
    Regards,
    Prashant

    Dear Prasobh,
    Thanks for the reply. There is no storage location mentioned in the sale order. I tried confirming the sale order by activating the No storage location check box, still it does not confirm the quantity. If we keep the check box "Check without RLT" blank then the sale order quantity gets confirmed. But the problem here is that it confirms quantity greater than what is available in stock i.e. if we enter any quantity it is confirmed.
    I would like to ask one more question. The sale order confirms quantity available as per the ATP logic. When we have excluded the storage location from MRP the quantity is seen at storage location level and not at Plant level and hence it is not proposed in cummulative ATP quantity. Should the quantity be available in cummulative ATP quantity. If yes, how can be get that quantity in cummulative ATP quantity?
    Is there any impact of MRP area? as we have MRP area activated. Within this Plant we have one MRP area at storage location level and the other MRP area as Plant excluding this storage location.
    Regards,
    Prashant

  • To exclude Storage location frm MRP run

    Hi Friend s
    In my secnario MRP should not consider the storage location  stock planning
    i using stratgey 11 gross req planning ,
    and  (SPRO), In MRP  -define storage location MRP  per Plant , i set the indicator 1 i.e storage location stock excluded frm MRP
    But still i mrp considers  stoge location stk .
    is there any setting ?
    Regards
    Sandeep

    Sandeep,
    For strategy "11" system automatically will not consider storage location stocks, so no need to define that in SPRO>MRP->Planning-->Sloc MRP/Plant as told by you.
    Couple of checks....i would suggest.
    1. Check whether you have maintained "2" - Mixed MRP indicator in MRP3 view.
    2. Check whether the PIR you have created is having requirement type "BSF".
    Regards,
    Prasobh

  • Exclude storage locations from the MRP run

    Hi all,
    Is it possible to exclude stock of specific storage location from the MRP run?
    Thanks for your help
    Thomas

    Hi,
    2 things,
    1. In OMIR for the storage location set that this location is excluded from MRP run (if am right the value to be maintained is 1)
    2. In MM02 go to MRP-4 view of the material master, specify plant & the storage location which you want to exclude & in the field SLoc MRP indicator specify that this is excluded for MRP run (if am right the indicator is 1).
    The step 1 ensures that all materials which are extended to this storage location will by default have the value 1. And step 2 ensures the materials already having this storage location view are excluded from MRP run.
    Regards,
    Vivek

  • Need to exclude storage location from MRP.

    Hi Gurus,
    Is there an option to exclude a specified storage location from MRP at configuration level. But not at material level as in MRP4 view.
    We have excluded the stoarge location in config OMIR, however the system considers that stock if the same is not excluded in MRP4 of that material.
    Now, the problem is every time i need to go to the material master of every material  i have to excude from MRP, which is very time consuming..!
    Please advise me is there any option in point of view of Storage Location,  just simply  define the storage location to be excluded from MRP run.
    Thanks in advance.
    Naveen.

    Dear,
    Yes you can do it though OMIR or MMSC 1-Storage location stock excluded from MRP.
    Also check this link for more details,
    Exclude purchase order on storage location from MRP
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on May 25, 2009 12:22 PM

  • MRP4 view exclude storage location & material provided by vendor/customer..

    Hi
    Could anyone please tell me in MRP4 view for a material,where is the option so that i can exclude or include the storage location stock from MRP?
    and also in which T code i should indicate the material is provided by vendor/material provided by customer?In CS01wher's this option?
    Please help me
    Thanks & regards
    Raj

    Hi Karthik,
    MRP area is nothing to do with storage locations settings in MRP4 view. If you want to activate MRP area and use the MRP run at MRP area level then you have to customized MRP area either at storage location level or sub-contractor level (in MRP master data settings )... then you need to assign this MRP1 view of the material and with valid MRP type.  Now when you run the MRP then planning will be carried out at this MRP area for this part.
    With storage location indicators in MRP4 view (must enter with putting the stoarge location values from MM02/MM03) you can exclude the stock of this storage location (indicator 1) in the palnning run or you can plan seperately with indicator2 with using re-order level. Here no need of MRP area.
    If helps rewards points.
    Regards
    TAJUDDIN

  • Exclude storage location from Availability check

    Hi,
    We have to exclude 4 storage location out of 46 storage locations from availability check in sales order processing.
    Please advice how to do it.
    We can not use MRP area and MRP Groups to control this because of certain reasons. 
    Regards,
    Avnish

    Please check this..
    spro...material management....consumption based planneng....planning...define storage location MRP...
    Here give plant name and enter...
    Against every storage location you ll have indicators for excluding,including the stock....
    hope this clarifies..
    For material availablity check in production order,
    1. you need to delete the storage loation in OX09 (it is possible If no stock)
    2. Or you need to transfer post the materials to a storage location xxxx which you can name as Blocked storage location...
    F Y I....In OVZ9  you can exclude all the storage locations which is not your reequirement..
    katrthick
    Edited by: karthick PP on Mar 26, 2009 12:40 PM

  • Exclude storage location during batch determination

    Dear SAP Gurus,
          My client senario is PP-PI. We are using batch determination in process order. Suppose my raw material is 'A'. It is present in ST1-100 qty, ST2-200 qty and ST3-150 qty. Now during batch determination i want to consider only ST1 and ST2 in determination and don't want to include ST3 in determination. But during determination system consider all 3 locations. So how can i exclude ST3 from batch determination.
    What things i have to do for this. Please help me out.
    Thanks and Regards,
    Harish Gunjatay.

    Hi,
    Sol 1:
    U can create Storage location as one Characteristic and while determining the batch, you can play with this characeteristic. Just this logic strikes my mind. See the posibility. And by "Reference Characteristic" concept if u can establish automatic updation of this characteristic, it will be superb.
    Sol 2:
    In Bactch Information Cockpit I think u can filter the storage location out. Try this also.
    Kiran.

  • QM exclude storage location from QM

    Dear All,
    is it possible in some way to exclude a storage location from QM in a plant managed with QM.
    The case is this:
    We have the material AAA with QM active for good receipt.
    -If the material arrive in st. location 10 we want have stock in Q status.
    -If the material arrive in st. location 20 we want have stock in Free status.
    St location 10 and 20 belong to same plant.
    If it is not possible, do you have some suggestion to solve this case (u.exit?)?
    Thanks in advance. Best regards.

    Tanks,
    but finally we have used another u.exit, EXIT_SAPLQAAT_002.
    This one is called directly in the MIGO and allow to deactivate QM setting X in the parameter NO_INSPECTION.
    Best Regards.
    Alby

  • MRP requirements (material = "no dispo", storage location deleted)

    Good morning,
    I have two different problems and hopefully, you can help me.
    - I see stock information in MMBE for a storage location I deleted
    - MD04 shows requirements for this storage location after it was deleted and the material was set to "no dispo"
    How can this be?
    I remember a report from SAP, which clear all wrong requirements for a material, but I did not find it. Anyone remeber the report??
    Thanks
    Nicole

    If by saying "I deleted the S/L" you mean that you deleted that entity in customization, this is a NONO practice. By deleting it from customization you are not deleting all the database references that exist in many objects (tables) as well, and this leads to inconsistencies that in some cases are not manageable.
    I suggest that you you recreate the S/L, name it something like "DELETED-DO NOT USE", and gradually make sure that all references (like in your example stock, requirements, etc.) are gone.

  • How to carry MRP run based on MRP areas

    Hi All,
    I want to run MRP for selected MRP area irrespective of plant and material.
    Is there any configuration to get this option.Please let me know ASAP.
    Regards

    Please check these answered links:
    Run MRP by MRP area - Tcode?
    MRP-Run settings
    Re: material provide to vendor for MRP run
    Re: mrp run
    Re: MRP Run in an excluded Storage Location
    Edited by: Afshad Irani on May 5, 2010 12:30 PM

  • Generate Plan Order from MRP Run (MD51) by WBS Element

    Dear All,
    1. I have created sales order with assigment WBS element (VA01)
    2. Then I created Routing & BOM for Material (CA01 & CS01)
    3. Generate MRP Run (MD51)
    The problem the generated mrp run doesnt consume planned order .. i have set the planning strategy 21 or 40, but still doesnt works.. is there any other parameter that i should configure..???
    Help Me...
    MamaRara

    Hello,
    Hopefully, the following link can assist you.
    - Re: After firming planned order, new planned order is generating in MRP run
    - Basic Scheduling in MRP run
    - Re: MRP run
    - During MRP run unwanted plant and storage location include and exclude
    - MRP run does not consider the common stock
    Thanks & Regards
    JP

  • How to run MRP at storage location level?

    i know to run the MRP at plant level. i want to know to run the MRP at storage location level. what are the setting have to do for that? please can help any one....

    Hi,
    I think your question is answered by Sarita Doddi.
    If you have several storage location for your plant, you cannot plan for them separately unless you assign them to a separate MRP area.
    If a storage location (alone) is assigned to an MRP area, it means you wan to plan for it separately. If several storage locations are assigned to an MRP area (or let's say to a plant), it means you want to plan using all of them - and you cannot choose only one and plan for it (you can exclude a SLoc from planning w/o assigning it to MRP area).
    So, planning is not SLoc wise, it goes MRP area wise.
    BR
    Csaba

Maybe you are looking for

  • Lack of a print preview button on the toolbar

    Like several users, I miss the availability of a Print Preview button on the toolbar. The reason: Many, many, many web sites configure their web page outputs so that they ignore the size and limitations of the user's printer. For instance, a web page

  • Lost music & Music video`s

    I have a first generation iPod touch & run iTunes on a Dell Windows 7 PC.  I recently deleted a programme "Homestream", used for listening to music & viewing photos on a Sony TV.  In so doing, it deleted all my ITunes music & music videos & much more

  • Suppress cloumn in ALV

    How to suppress column in ALV?

  • Jdeveloper 11gR1 download does not start

    http://download.oracle.com/otn/java/jdeveloper/111/jdevstudio11111install.exe does not download neither using download manager nor using the direct download using Firefox I need it urgently, please tell me how to get that .. Thanks in Advance

  • Does anyone else have a "*" show up in front of old files once you upgrade to CS6??

    When I open files from an older version of InDesign, the files now have a strange "*" on the front of them? What is this? and why does it happen?