MRP schedule lines are not created by MRP

Hi !!
I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product
*but no schedule lines are created for the raw materials.*
Please Guide , Itz very urgent.

Vijay , Pleae clear
I have a doubt
I am having one finished product & in its BOM i have three raw materials.
I have created the scheduling agreement for these three raw materials and source list too.
now when i run the MRp for finished product using t-code md02 the schedule lines must be generated for these three raw materials.
or
i have to run the MRP (seperately using T-Code Md01 ) for these three raw materials
Please guide , its very urgent.

Similar Messages

  • Scheduling lines are not created in mrp running

    Line 1 & 2 are having same items with different schedule lines qty 250 & 275 nos. respectively. Stock was 250. System bokked stock 250 against line 1 & given proposed delivery date for line 2. In MM module, by running MRP system generated requirement only for 25 pcs.(may be it taken again stock 250 against line 2 in consideration while running MRP). This is happened in various cases.KINDLY HELP ME in solving this problem.
    REGARDS,
    G.V.SHIVAKKUMAR

    Hi,
    With my experience I will share something:
    1) Do you have valid Schedule Agreement?
    2) Have you entered Sch. Agreement number in source list?
    3) Have you selected MRP as " 2 " in source list?
    With your earlier checks, please chekc these also.
    Karthik Params

  • Schedule lines are not coming after MRP run for HALB material

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Dear All,
    I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
    Thanks for all the reply.
    Thanks & Regards'
    Kundan Kumar

  • When we run the MRP schedule lines are not generated automatically.

    Hi,
    In MD04 requirement date is on 5.12.2009.My source list validity starts from 1.12.2008 onwards.When i run the MRP for the material system generates the Purchase requisition instead of the schedlue lines.When i change the source list validity as 25.11.2008 now i run the MRP system generates the schedule lines.
    My question is why the system couldn't able to generate the schedule lines when the validity starts on 1.12.2008.In the source list we maintained the scheduling agreement and maintaine the MRP setting as 2.

    hi,
    Let me know your purchasing processing time defined in the SPRO settings for CBP?? It may be due to this also...
    Regards
    Priyanka.P

  • Schedule lines are not getting generated during MRP Run

    Schedule lines are not getting generated during MRP Run. I have maiantained source list for the material with proper validity date and also maintained scheduling agreement . MRP relevvant Indicator , I have marked - 2 which means -Record relevant to MRP. Sched. lines generated automatically.
    Still I am not able to get schedule lines and instead of that *Purchase Requisitions* are getting generated.
    Can any one help me and suggest me what to be done in this case .
    Thanks & Regards ,
    Nirmalya

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Schedule lines are not in sink for PO

    Hello Everyone,
    We are using ECS.
    So we create PO in SRM with some schedule lines and transfer it to the ECC system.
    But sometimes the schedule lines are not in sink on both the sides because buyer update the schedule lines on SRM side.
    So we need to check that is schedule lines in SRM and Basic quantity in SRM are same or not?
    So is there any OSS note to check this?
    Regards,
    Khushbu.

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • Schedule lines are not getting generated through MRP

    Hello Experts,
    While running MRP, we observed that the system is creating PR instead of schedule lines, although all the necessary prerequistes to generate schedule lines through MRP are maintained. For e.g.
    1. MRP Schedule line relevant indicator '2' is maintained in the Source List.
    2. Sch. Agreement dates and Source List validity dates are same.etc...
    Further after some analysis, we observed that if we change the source list validity from date to some back date then system is creating correct schedule lines.
    Example: Material M1; Planned delivery time 7 days; GR processing time 5 days; MRP Type PD; Lot Size WB;
    SA validity dates - 07.09.2011 to 31.12.2011
    Source List validity dates - 07.09.2011 to 31.12.2011
    If MRP run on 12.09.2011 and source list dates are retain same as mentioned above, system creates the PR.
    If MRP run on 12.09.2011 and source list dates changes to 05.09.2011 to 31.12.2011, system creates the schedule lines.
    Could you please let us know, why the system behave like this?

    Dear,
    Welcome to SDN,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.
    Regards,
    R.Brahmankar

  • Schedule Lines are not getting generated after MRP run.

    Hi,
    I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
    Create pur.req.  2
    Schedule lines   3
    Create MRP list  1
    Planning mode   1
    i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
    In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
    Any help is appreciated. I can give more info if required.
    Thanks.

    Dear Rakesh,
    Scheduling agreement:An outline agreement against which materials are procured at a series of
    predefined points in time over a certain period.
    1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
    schedule.
    2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
    relevant to MRP,Schedule line generated automatically.
    Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
    So for the materials for which scheduling agreement exists,schedule lines will be generated.
    Check and revert back.
    Regards
    Mangalraj.S

  • Schedule lines are not generating properly in MD04

    Hello All,
    I have a issue in MD04, in which schedule line for Schedule agreement is not getting generated on the same day as sales order is created (09.05.2014). But Schedule line is getting created in different date. Because of which i am creating schedule lines manually at required dates. 
    Note: I have attached screen shot of MD04
    Kindly help me to overcome this issue.
    Regards,
    Manoj  

    Hello Manoj
    Please observe that there are rescheduling exception messages and rescheduling dates for your scheduling agreements. It generally happens when you have sales orders in the past and you don't allow "start in the past" for replenishment proposals generated by MRP.
    Go to the customizing transaction OPPQ and change the customizing "start in the past". After that, run MRP again for your material and the schedule line dates should match the sales order. Please observe that firmed schedule lines wont't be changed.
    BR
    Caetano

  • Schedule lines are not getting confirmed even though stock is there

    HI,
    i want to discuiss one sensitive issues which is a simple one.
    my schedule lines is not getting confirmed even stock is there at sales order.
    there is no delivery block.
    there is no minimum stock level.
    there is no credit check for that.
    there is stock of 2 EA in that plant and storage location, but stock is not getting confirmed at sales order level or transaction level.
    even stock is there it is going to avaliability check overview screen and giving stock confirmation after 12 days.
    even i checked all the dates.............but its of no use.
    what to do ?
    after testing all the possible options i am taking help from
    please help me in this regard,
    regards,
    balajit

    Hi
    you need to check the following.....
    First check the Factory calander of your plant whethear some holidays or not
    Second most importantly you have to check which stretagy group is assigned  in the material . whethear it is make to order or make to stock. change it as make to stock.
    "What happened if material stretagy group is make to order then from sales order system generate requirement of that material against that particular stock, that time system do not consider the unrestricted stock and not confirm schedule line."
    Regards
    Shambhu Sarkar

  • Schedule lines are not coming for HALB after MRP run

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • Schedule lines are not modified when i change the requested delivery date

    Hi  
    i have a issue when i am created sales order with requested delivery date 10.11.2011
    and the same is copied in to item schedule lines as a 10.11.2011
    before saving the order i change the requested derlivery date to 11.11.2011
    this new requested delivery date is not dopied to schedule lines at item level (still is having 10.11.2011)
    can any one tell me this is system standard behaviour or can we correct this
    Thanks and Regards
    Kishore

    Hi DevarapalliKK,
    I tried this solution & problem is solved.
    --Go to VA01 & enter the material & qty
    --Select the line item in VA01 & click on Edit
    --Select Fast Change of & click on Delivery date & mention the Delivery date as 11.11.2011. & click on copy.
    --Check the request delivery date in header level in sales tab it will change to 11.11.2011 & also check the Schedule lines in Item level the date will be 11.11.2011 & Save it.
    Please let me know if your problem is solved
    Regards
    Pradeep

  • Purchase requisitions are not created for Component by MRP

    Hi,
    I have created planned orders for assy. When I run the MRP the purchase requisitions are not created by  MRP for the components. If I check the planned order the components tab is showing all the raw materials list as per the BOM. The master data tab shows the BOM,Routing,Production version etc. But when I run the MRP the components planned orders/purchase requisitions are not created.  There is no stocks available for the components in the plant, still the purchase requisition are not created by MRP.
    I have tried in both transactions MD01 and MD02.
    I could notice one thing. Supoose if I enter 31.12.2009 is the order finish date, the system creates exception mesage 10- Rescheduling in with proposed date 01.12.2009.  Why the system is propsoing rescheduling in with date 01.12.2009 which past date.
    Please sugest.
    thanks and regards
    Murugesan

    Hi,
    I am using MRP type PD  for assy and components. There is no planned orders for assy.
    If I run MD02 the planned orders created for assy and purchase requisition are created for raw materials. But if I run MRP in MD01 neither  the planned orders nor the purchase requisitions created.
    I tried the Control keys NETCH,NEUPL but still the planned order and purchase requisitions are not created if I run using MD01.
    Please suggest.
    thanks and regards
    Murugesan

  • Schedule Lines not created from MRP

    Hi !!
    I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
    For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
    Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product 
    *but no schedule lines are created for the raw materials.*
    Please Guide , Itz very urgent.
    Regards
    Rahul Bhardwaj
    9909986406

    Dear Rahul,
    When u r running MRP maintain '3' for Delivery Schedules Field under MRP Control Parameters ( T Code MD02). Sheduling Agreement should be valid. If there is sufficient stock on hand compared with the requirement then system will not create any Schedule Lines. In material master of raw Materials on MRP2 view Procurement Type should be Maintained as 'F'. If u have maintained 'E' or 'X' then MRP run will not create schedule lines.
    Regards
    Sunil Kumar

  • Schedule line date changes after each MRP run

    Dear Experts,
    Clarification needed on how the system plans the MM schedule lines.
    Setting: Start in the past not allowed.
                  3 days for processing of order
    The issue is after each MRP run the system is moving the schedule line to the current date + 3 days for processing + the planned delivery time.
    If the schedule line is not firmed, after each MRP run ( which happens everyday) the system is moving the schedule line and then giving an alert saying the " order has to be rescheduled to the previous day"
    on the second day after the mrp run the system moves the schedule line again by one more day and gives the rescheduling date as " -2 days from today"
    this change is happening every day after the planning run. - because of this there are really no backorders ( schedule line in the past ) in the system. we were not able to know if the vendor is actually delayed in this case.
    can you kindly suggest what went wrong here ??
    we are using strategy 10 for the planning of procured parts. Let me know if more info is needed.
    Note: we are also using stock transfer process for some procured parts. there too the PR date gets changed after each MRP run. There there is no lead time in this case. the order is placed on the same day as the requirement as both plants are nearby. There the PR date is changing everyday to the current date.
    your advice would be of great help
    thanks
    Nagendra Kumar

    Hi Caetano,
    thanks for your suggestion
    Yes, we use firm zone for few of the vendors. there the system don't change the schedule lines.
    Also for the stock transfer PR's there is no firm zone and the lead time is one day. in this case it changes everyday after the MRP run.
    the stock transfer PR's leads to the creation of Schedule lines from the source plant. Since this PR gets changed everyday. the alerts coming out of MD07 gets changed and we really did not know if this order is delayed or not.  In the source plant we use the firm zone to avoid moving the schedule line. But then the alerts are always not correct.
    is there any setting which helps in not moving the PR everyday without using " start in the past"
    thanks
    Nagendra Kumar

Maybe you are looking for

  • E-Recruiting 3. 0 IT0001 of Internal Candidate Not Displayed

    Hi The E-Recruiting system is running on the same instance. I have copied internal candidates using report HR_SYNC_PERSON. As per IMG notes, the following infotypes are copied: IT0000, IT0001, IT0002, IT0006, IT0105. I can display all the other infot

  • How to decrease the size of a 52 page document?

    InDesign Help:  Original 52 page document (5.5" x 8.5"- .25" margin) needs to be be reduced to 5.375"x .375" with a .375" margin.  Is there an easy way to fix this?  I created alternate page layout with the new dimensions, but margins are off.  I don

  • Tracking websites visited by employees

    Hello all, Need a little advise. Our owner got really upset when he found out about a couple of employees that were spending time surfing on the web and not taking care of bussiness. We are currently running SBS 2008 Premium. The router we have in pl

  • People with vista having problems with adobe flash player 9

    this seems to be a very big problem that this many people are having problems with the adobe flash player 9. I can't get it to install at all and many can't get it to work..how many have vista I wonder? Please help us fix this frustating problem.

  • ITunes image does not appear

    Hello and thank you for taking the time to view my question. Our current LoudBlog program is dead and I am now producing my own RSS feed. I am having trouble getting the image to appear, the URL is accurate and the xml tags are correct. Any suggestio