MRP & schedule margin key issue

Hi All,
My client is running MRP on daily basis they have maintained schedule margin key 001 with opening period as 0010.but while running MRP & MD04 they
found below are the issues.
We have tested many times using SMK as 000 & 0010 but every time system displayed below errors.
Some times they are not getting the purchase requisition created in time (System should drop the purchase Requisitions according to parameters maintained in material master).
Some time system creates planned order instead of Purchase Requisition (Their requirement is to create purchase requisition always)
They get the exception message past due planned order
As per my understanding there will be problem in buffer period.How can we avoid these exception messages & how can we create always PR instead of pl order.
I will appericate if anybody suggest me how can we rectify above mentioned causes.
Thanks,
Ravindra.

Hi Caetano /Ram
Thank you for replies.I have following doubts on your reply
I understood if I create Variant including only PR system will display always PR in MD04.
1.If I run MRP using option 2 PR in opening period in this case system behave like same or do I need to include this parameter in variant
2.How can I avoid exception message"Past open due" for Ex :- 10,20,30 etc... permentaly in MRP run?
I have not tested solution yet I hope if I create MRP group & during background MRP run if I create variant with parameter 1 (PR only) it will create PR.
Can you pls assist on SMK? For your clarification check below is my actual scenario
if I assigned SMK with 000 (All periods like opening period,FAP,FBP & release period is 000) then what happen in MRP run if I made your suggested setting is system means it will always create  PR.
If I assigned SMK with 001(opening period 0010,FBP 5,FAP 2 ,release period =5) also
if I maintained GR time= 2 days,
Pl.delivery time =10 days  in this case will above setting  work? if i run MPR using opening Period as well as PR only.
Kindly correct me if i am wrong.
Thanks,
Ravindra

Similar Messages

  • Make optional from material master of Schedule Margin Key

    Hi PP Guys
    I am using MRP Type PD & there is no floats in schedule margin key.
    So client want make a optional of schedule margin key from material master.
    I tried from L-G --> Material Master --> Field Selection --> Assign Fields to Field Selection Gruops / Mainatin Field Selectio to data Screens.
    Bur here this filed is optional.
    I think some relation from MRP Type or What ?.
    Pls suggest.
    Regards
    Ashish

    Dear Asish,
    This is the required master data to create order also, based on this only all your order dates are calculated, like when to release the order, start and finish and finaly material available to dispatch.
    So for MRP calculation and to promise the delivery to sale order also it is must.
    When u create order this gets copied to the order this u can see in production order Genaral data tab.
    i hope u r clear
    sree

  • The scheduling margin key 000 does not exist

    Hi guys
    There is query from my side please do help me out
    to get a solution for the following query
    i was asked to give schedMarginKey = 000 while creating
    a material for MRP(material requirement Planning)
    but if i give schedMarginKey = 000 and save this it shows the
    following error
    The scheduling margin key 000 does not exist for plant JOP1
    is ther any transaction code to overcome this?
    please do help me out in this!!
    Regards
    Jino.

    Hi
    You can miantain the schedule margin key using t.code OMDC.
    reward points if useful
    Thanks & Regards
    Kishore

  • Schedule Margin Key behavior during External Procurement and Inhse Prodn

    Hi Gurus
    Could you give me detailed illustration in a visualising manner the Application of Schedule Margin Key in
    "External Procurement for Raw Material" and "Inhouse Production for Production Order" with one scenario
    Stating each and every floats in more detail
    a) Opening Period -applicable for ext and inter
    b)Float before prod-applica only for external

    Hi,
    The complete explaination for your requirment is available in help.sap.com, under MRP-->scheduling section
    Regards,
    Nataraj

  • Opening period (schedule margin key) in forward scheduling

    Please advise whether opening period is used in forward scheduling that we specify in schedule margin key? if not, what will be the reason?

    Hi,
    Opening period is used only in Backword scheduling.
    b'cause opening period is period of workdays deducted from the start date to determine the creation date of order.
    reward points if useful to you.

  • Scheduling Margin key ( Float before production - Float after production)

    Dear Expert ,
    I maintain in material master float before and after production
    When i rescheduling in house production in routing and display the result i found the time for float is calculated in Interoperation time
    And I as i know Scheduled start & Scheduled finish determined the production dates only & FBefProd is time between basic start and Scheduled start and FAftProd is the time between Scheduled finish date & basic finish date
    Why he put it there at the time it's not actually maintained in production date ?
    Regards
    Rami

    Dear,
    In the routing, click on scheduling result push button,
    Here you can see how this interoperatioon time is calculated
    how much is Float before and after production.
    example-
    schedule margine key - 001
    float before production - 2 day
    Float after production - 1 days
    Routing data- for 1 qty - 24 hrs
    After you schedule in routing and see the details of scheduling result, the following result
    Basic start date - 30.11.2008
    Basic finish date - 03.12.2008.
    Scheduled start date - 02.12.2008
    Scheduled finish date - 02.12.2008.
    base qty - 1 TO
    Processing time - 1 day
    interoperation time - 3(all inclding floats)
    Total inhouse production time - 4 days
    Now repeat it for 2 qty, results are as below
    Basic start date - 30.11.2008
    Basic finish date - 04.12.2008.
    Scheduled start date - 02.12.2008
    Scheduled finish date - 03.12.2008.
    base qty - 2 TO
    Processing time - 2 day
    interoperation time - 3(all inclding floats)
    Total inhouse production time - 5 days
    I hope you got the idea.

  • Include the Scheduling Margin Key to the LOIPR02

    hello Experts,
    I am trying to find some details on how to include the Scheduling Margin Key(SAP1 in our case) to the IDOC before passing it to the
    ME.
    Please let me know if there is any standard way of achiving this.
    We are using : SAP ME 6.0 and MII 14.0
    Thanks in advance,
    Pradeep D

    Here is a document how to extend an iDOC
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/80677e5d-dc79-2c10-b7bb-a7e99767c8f6?QuickLink=index&…

  • Schedule margin key

    i am a beginner in SAP.
    could some one tell me how to find the appropriate 'Schedule margin key'.
    i was trying to create a new material under a new plant.
    so while filling the 'Schedule margin key' tab what should i type,how can i find the appropriate schedule
    margin key. what is the rule for that .when i type some value randomly ,the following message displays
    the message says as " the scheduling margin key  does not exist for the plant"
    could some one can help me.
    thanks
    zuhair

    Dear Zuhair,
    1) As i already told you, schedule margin key is for defining floats or Production scheduler
    2) Floats are basically calculated in Days
    3) if you press F4 for the schedule margin key then u can see
    4) float before production float after production release period
    5) this are nothing but  the days ( or extra days ) are given for production scheduler
    for converting plan order to production order
    6) and if we are maintaining floats ( schedule margin key ), then this will be copied to
    production order. even scheduling considers this floats & calculates dates for plan order
    Hope This Helps You
    Regards
    Madhu Kumar

  • Configuration of Scheduling Margin Key

    Good day!
    Where can I add a "scheduling margin key"?
    Thanks!

    Hi,
    There are many paths for defining the same;
    Go to path SPRO > Materials Management > Consumption-Based Planning > Planning > Define Floats (Scheduling Margin Key) and add it for your Plant.
    Also you an add it in path SPRO > Production > Material Requirements Planning > Planning > Scheduling and Capacity Parameters > Define Floats (Scheduling Margin Key)
    Also SPRO > Production > Shop Floor Control > Operations > Scheduling > Define Scheduling Margin Key
    Also you can maintain under transaction OPPQ for you Plant under "Floats" button.

  • Scheduling Margin Key

    Hello Friends
    This is regarding inspection lot, as per my knowldge, Inspection lot will be based on purchse order item level. Is lot will be based on PO header level. if so could u please explain and the details?
    Thanks
    Vijayakumar TVN

    Hi,
    Inspection lot will be based on PO Item level.
    When ever purchasing team do Gr with respect to PO inspection lot will be created
    so when ever there is a GR one Inspction lot will created
    For example if there is a PO for 100Kg and during GR the buyer will do GR 100 kg for 5 times
    From my understanding 5 inspection lot will be created
    Set Control inspection lot to 'X' (For each purchase order item, batch and
    storage location) for inspection type 01, in the inspection setup tab in
    material master.
    regards

  • Mrp scheduling

    Hi, if production order basic start date exceeds the todays date, then system will do forward scheduling (for backward scheduling). in that case sales order delivery date and the production order completion date will not met. in such case how to ensure that our production orders are going to meet the customer delivery dates? please help me.

    IF your scenario is MTO( Strategy 50, 82). then these date are interlinked.when a sales order is placed it will have a materials availability date in it (check shipping tab in sales order for this information).
    this date will be the basic finish date taking in to consideration your schedule margin key and your production lead time .
    IF you miss that dates physically. then it means that the customer requested date can not be met. IF you reschedule your production order in a MTS scenario it will automatically change the dates in the sales order too. Not customer requested date but the estimated delivery date.

  • Tecra M10 - Stuck CTRL key issue -- perhaps to do with BIOS?

    Hello and thanks for reading.
    I recently switched my Tecra M10 to Windows 7 (from XP) and it soon developed the dreaded "stuck CTRL key" issue. This causes the keyboard to behave as if the CTRL key is permanently depressed. Sometimes hitting a combination of keys, or bringing up the onscreen keyboard, temporarily solves the issue, but then it returns.
    It seems to be an issue many people have, with no simple solution. I've looked at every thread about it I can find, and tried many things to do with drivers etc. without any success.
    So firstly, if anyone knows a remedy that works for this particular machine, I would be very grateful to learn it!
    Then, there are two things I've not yet done: update BIOS and disable pinch zoom.
    I was looking at the following BIOS update:
    http://www.toshiba-asia.com/sg/support/drivers/details/25244
    ... which is version 3.00 and seems to be most recent. My own version is 1.90.
    However version 3.00 is labelled "For PTMB0* ONLY". I don't know what this means or whether it applies to me. Can anyone help? Should I install this BIOS?
    For the pinch zoom, I've been told that disabling it does sometimes cure the CTRL problem -- but I can't find any pinch zoom facility on the M10. I suspect it simply doesn't have one. Is that right?
    Many thanks for any help you can give.

    Hi
    > I was looking at the following BIOS update. which is version 3.00 and seems to be most recent. My own version is 1.90.
    There are different Tecra M10 models on the market.
    Check the labels at the bottom of the unit. There you should find some numbers like for example PTMB0E-01K00LGR
    The first 6 characters are important: for example PTMB0E
    I assume your notebook belongs to European series.
    In such case you should check the Toshiba EU driver page for possible BIOS update.
    http://www.toshiba.eu/innovation/download_drivers_bios.jsp
    However, on Toshiba EU driver page you will find also the BIOS v3.0 for all European Tecra M10 units.
    Anyway, back to the CTRL button issue: guess what, you should connect an external USB keyboard and should check how the CTRL button acts.
    In case the USB keyboard would work properly, the CTRL button of internal keyboard is affected and you will need to replace the internal keyboard.
    PS: it could be possible that the option "sticky keys" has been enabled. To disable this function, you have to press SHIFT button 5 times in the row.

  • Windows 8 Key Issue

    Here's my problem.  Windows 8 came preinstalled on my computer; however, I accidently deleted the Windows 8 key from the bios and now Windows keeps asking me to enter the correct key.  Since there is no longer a sticker with the key included with the computer I have no way of finding the key.  Does HP keep a record of the keys tagged to the serial number?  Or am I just out of luck?
      I called HP Support about this and they told me to get the key off the CDs which were included with the computer.  When I told him there were no CDs, he said I had bought a used computer mascarading as new because all of their computers ship with Windows CDs.  When I disputed this he said that Microsoft could solve the issue for me.  Microsoft said that HP could solve it.  Can anyone help me?  I'd rather not spend money on buying Windows 8
    Thanks in advance,
    Mike
    This question was solved.
    View Solution.

    HP does not retain records of the keys issued .  HP also does not ship Windows CD's with the computers unless they were specifically ordered.  If you have somehow deleted the key then you are out of luck, sorry.
    Please mark my post as SOLVED if it has resolved your problem. It helps others with similar situations.

  • T400 stuck key issue

    I bought my T400 2764-CTO in last December, and started using it on mini dock without any problem. Until recently, it starts to show stuck key issue randomly (not always failure) both at boot up or under Windows Vista.
    ERROR
    0210 Stuck Key FF
    Press <F1> to SetUp
    Note: the stuck key keeps changing, sometimes 13, sometimes 1F, sometimes other key.
    I opened the laptop, and checked the connection of the keyboard but couldn't locate any problem there. Can this be a keyboard issue? Or even a motherboard issue?
    Can Lenovo swap a new keyboard for me? If so, what do I need to do then? 
    Thanks!
    Best Regards  

    You can call Lenovo service, and log a service call, they will make the necessary arrangements. If you are not confident with bios update then please don't do it youself, and let the warranty department do it for you, as any mistakes can make your laptop useless and you will be paying couple hundreds of euros to get the motherboard replaced. 
    Regards,
    Jin Li
    May this year, be the year of 'DO'!
    I am a volunteer, and not a paid staff of Lenovo or Microsoft

  • Repeating key issue

    I just moved to the Mac a couple of months ago. I love it and haven't looked back. However, today, I used my Mac twice. First, this morning, I didn't do anything unusual. I cleared out my trash, browsed a bit on the Internet and answered e-mail. Then I modeled some artwork. I shutdown my machine, shutdown my cable modem & router and went to work. When I came back at lunch nothing was wrong and I hardly did anything (Internet still wasn't on).
    However when I came home after work, I started the machine up and the hard drive icon kept popping up and it was difficult to use the menu because I had to hold down the mouse button instead of just click. It turns out that the space key is repeating spontaniously. I thought it might be the keyboard but it doesn't stop when I unplug the keyboard.
    Has anyone had this before? How do I cure it? Thanks.

    Hi Redspark,
    Did you arrive at any solution to your repeating key issue? I've recently joined the discussions forum because I'm having a similar problem - without having typed anything, my backslash spontaneously inserts itself into any text box available and starts repeating itself across the page. In the Finder, I also get various folders spontaneously highlighting themselves, if I pull down a finder menu, it flashes which makes it almost impossible to select anything. As well I get sudden outbursts of the error chime.
    Have done an Archive and Install, reset the PMU. I've also zapped the PRAM, checked my RAM slots, checked Permissions, etc.
    Let me know if you've got any further insights.
    Thanks.

Maybe you are looking for

  • Is Automation possible in SAP BW

    Hi,   I am working in BW testing (manual testing).Is there any way that BW automation testing (like using ECATT, QTP tools)can be done? Can anyone help me out in this.

  • Error in the Adobe Flash Player in EPM WEB Screen

    Hi Team , We are using EPM 10 NW SP 15 . While logging in the SAP EPM 10 Web screen , We are getting one error related to Adobe Flash payer That's Error asking 2 options one is Dismiss & Another is continue. Please let me know , Why this error pop me

  • BP with Archive flag found in Duplicate check records

    hello we have duplicate check fuctionality active in UI,while maitaing BP in UI ,duplicate records were found and when the same is selected to check the duplicate records ,we noticed that BPs with Archive flag active were also taken as Duplicate reco

  • Not able to un-apply a cleared receipt

    Hi, when i try to do un-apply of a receipt which is in cleared status, its throwing an error: ORA-01403: no data found ORA-06512: at "APPS.ARP_PROCESS_APPLICATION", line 522 FRM-40735: ON-UPDATE trigger raised unhandled exception ORA-01403. The same

  • Crawling xmp metadata from pdf's

    We have some PDF files which we are crawling in. These PDF's contain XMP metadata tags. I suspect that the PDF accessor is ignoring these tags. We've tried a number of different proprty mappings all to no avail. Has anyone else had any luck crawlingi