Dear Experts,
I have a requirement from client. In planning strategy 40, a sales order is entered of delivery  date more than 60 days from today.
Today is 17.04.2015, and the sales orders which under range of 1 month from today, i.e 17.05.2015, that much sales orders should only be considered by MRP run and other should be unplanned by MRP.
I tried to test with planning horizon of 30 days in MRP and run MRP with MD02. But, still it is planning sales order 01.07.2015
Please suggest how to map this. ( Soln Other than Schl Line category CN/CP manual change in sales Order)
Best regards
Shailesh

Hi Shailesh,
Use planning horizon as you mentioned and while running MRP use the Processing key NETPL on the MD01/MD02 screen as shown below.
If you use this key, system will plan the requirements with in the planning horizon.... in your case 30 days.
Hope this helps.

Similar Messages

  • MRP is conflicting with Sales order requirement Qty and date

    Hi experts,
    We have below scenario:
    Material has the stock 100. It has reorder point 3 and MRP type V2 (Automatic reorder point with external requirements) and planned delivery time 10 days.
    MRP run creates purchase requisition whenever the stock falls below reorder level or/and based on customer orders requirements.
    We created first sales order for Qty 80 and delivery date 03/01/2012.  Qty 80 is confirmed against this sales order.
    We created second sales order for Qty 50 and delivery date 01/31/2012. Now remaining Qty 20 is confirmed against this order. So we have requirements of 30 Qty for this second order.
    When we run MRP, it supposes to create Purchase requisition for Qty 33 (30 + 3) including reorder point (3 Qty). As the delivery date for this order is 01/31/2012 and requirement Qty is 30, and planned delivery time is10 days, MRP run should create purchase requisition. But it is not creating.
    If I change the planned delivery time to 30 days, it is creating purchase requisition. It is considering sales order delivery date of First order (delivery date: 03/01/2012), but not for second order (delivery date: 01/31/2012).
    So MRP is conflicting with Sales order requirement Qty and date.
    Appreciate your help in this regard to resolve the issue
    Thanks,
    Srini

    Hi,
    We are using manual reorder point planning with external requirements (V1)
    Thanks,
    Srini

  • Incomplete Sales Order requirement to MRP

    How to stop transferring Blocked Sales Order requirement to MRP?
    We have scenario there we entered 100 line on orders, due to one or other reason we need to block the orders and do not want to transfer the requirement to MRP till the time the particular blocked removed manually.
    How to do this? There is suggestion to use VOFM - Routine for transfer requirement. But not sure as that is the solution.
    Thanks
    PP

    Hi,
    Define a new delivery block whee check the Confirmation and assign the block to the order. System will not pass the requirement to the MRP.
    Path: LE >>Shipping >> Deliveries >> Define reason for blocking.
    Thanks
    Sri.V

  • Reg.MRP Run without sale order

    Dear Experts
    We are in need of MRP run without sale order. I have created Finished product material (T-Shirt) and assigned components to that and then I ran MRP, If I do so, MRP is exploded but result is not satisfied some non components are displayed.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Pls help what is the configuration for MRP run,
    Thanks
    Rajakumar.K

    Hi Raja,
    One of your requirements isn't available in R/3.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Standard MRP will create Dependent requirements (demand elements).  MRP will create order PROPOSALs (purchase reqs or planned orders)(supply elements).  MRP can be immediately followed by an additional program that will convert planned orders to Production orders.  All these things are possible.
    However, MRP will not check for the availability of components, and then selectively create production orders.  Availability check, which is not part of MRP, is usually performed at a later part of the production order cycle.
    Regards,
    DB49

  • Sales Order Required Qty...

    Hi,
    Where should I get a Total Sales Order Required Qty. Field & table.
    E.g. : X = 3
             Y = 2
             Z = 1
                 ===
                   6 Total Sales Order Qty. for same Material.
    Yusuf

    Topic: Free ABAP eBook Download
    Link: http://www.sap-img.com/
    Very imformative knowledge on tables & table joints.
    It has already been rightly suggested to use table VBAP. You can enter the table name in transaction code SE16. You will get details of most of field of sales order - item level.
    Above topic & link will resolve most of your query with respect to appropriate tables in future also.
    Regards,
    Rajesh Banka

  • MRP Run Against Sales order

    Can you run MRP against a sales order , if so which tcode can i use to accomplish this.
    Thank you

    Did you try MD50?.
    Reg
    Samson

  • ATP Logic for Sales Order Requirements not Confirmed

    Hi Colleagues
    I am running ATP with checking rules to include 'inbound shipping notifications'
    We want the ATP check to calculate sales orders that are both as requirements only (Not yet confirmed) and those that are already confirmed.
    We would like this so that when we are looking at Inbound monitoring we know how many orders are required and confirmed prior to running back order scheduling. Otherwise new orders can come in and steal the stock
    Example prior confirmation
    Material A
    Stock                                       0
    Order A           Req -10     Conf 0
    Order B           Req -10     Conf 0
    Inbound Del     Req +100
    ATP                                       100
    So at present if you place a new order then the ATP ignores those orders that are not confirmed and allows the full confirmation of 100
    Example after confirmation
    Material A
    Stock                                       0
    Order A           Req -10     Conf 10
    Order B           Req -10     Conf 0
    Inbound Del     Req +100
    ATP                                       90
    After confirmation we can place a new order for 90 because 10 are confirmed (ignoring the 10 required)
    Requirement
    Material A
    Stock                                       0
    Order A           Req -10     Conf 10
    Order B           Req -10     Conf 0
    Inbound Del     Req +100
    ATP                                       80
    To include the requirments not confirmed and those confirmed in ATP calculation
    Any ideas greatly received
    Regards
    Steve

    Hi,
    ATP qty is generated against the Sales Order requirement. It is not assigned to other deliveries.
    If Batch is assigned to Sales Order, it will not assigned to other deliveries.
    Regards,

  • Individual customer requirements and sales order requirements

    Hello Gurus,
    Can anybody please explain me the difference between individual customer requirements and sales order requirements.
    Please clarify
    Thanks,
    Nilesh

    Hi,
    *Individual Customer Requirement *
    Generally this is the material is produced against a Sales order,
    They will have the Stock Categroy as E as special Stock.
    They can be consumed only by the Relevant Sales order.
    Mostly in Case of the MTO this is applicable.
    Sales order Requirement.
    This is again Sales requirements.
    But it can consume any stock,
    the material is not produced against any specific sales order ,
    This is mostly in the MTS Scenario.
    Kindly let me know your feedback.
    Reg
    dsk
    Edited by: DSk on Dec 7, 2010 3:30 PM

  • Requirement in MRP even after Sales order completely delivered/cleared

    I see a sales order in md04 even after that order is already cleared completely delivered
    I have checked the pGI quantity in order and document flow. everything matches and status is completed/cleared.
    I also ran SDRQCR21 in se38 with data transfer checked. Still I am unable to delete that fake order from md04.
    any help is appreciated.

    Hello ,
    Have you checked & followed all instructions  in SAP note 207942.
    "Generally you can solve these problems with report SDRQCR21from Note 25444. If not, these kinds of problems must be processed further in SD-BF-AC.
    However, often the problem is also caused by the fact that
    no requirements are generated at first or the generated requirements are only displayed but are not included in MRP calculation
    or vice versa
    due to the Customizing settings requirements are stored although this is not wanted from the business view. "
    This is a release independent SAP note. so it applies to ECC6.0 as well.
    Hope this helps you resolve your issue.
    Thanks,
    Ram

  • Sales order requirement to planner

    Hello All
    This might be a basic question but need to know more details for this requirement
    1) once the purchase order is received from the customer for 5000 quantity which should be delivered to the customer in a time duration for 1 year  ( to note this Purchase order is not into SAP it is a manual document),Sales order is created in to SAP for the whole 5000 quantity remains open until the whole quantity is delivered.
    2) the delivery is happening week-on week or even some times on monthly basis some time immediate
    3) the question is where is the trig erring  point in SAP on sales order which sends the information  to the planner to produce the material?
    4) need to know more details regarding the integration between sales order and the planner requirement
    Thanks ..

    For your requirement, I would recommend you to check the option of standard functionality Scheduling Agreement.
    Sales doc type (VOV8)
    DS - Scheduling Agreement
    SD document categ
    E - Scheduling agreement
    Item Category (w. I Cat Grp NORM)
    LPN - Sched.Agreement Item
    Billing Relevence
    A - Delivery-related billing document
    Schedule Line Category
    CP - MRP
    Relevant for requirement & Availablity Check
    So, the system based on your
    in schedule line cat
    schedule for delivery will run MRP for
    for production plan
    Based on your schedule, your business flow will be:
    DS (VA31)
    - > LF (VL01N)
    - > F2 (VF01)
    Regards
    JP

  • Mrp run without sales order

    Hi Experts,
         I am running the MRP for a particular material ,and the material contains some sales order. I dont want the mrp to consider the sales order.
    I have made the changes in
    Strategy group from 40 to 10 in MRP3 tab.
    Schedule line from cp to cn in vov5.
    But still its considering the sales orders.
    so can anybody suggest me what changes i should do?
    Thanks & Regards
    Bhargavi desai

    Bhargavi,
    Change the schedule line category of the sales order schedule line to 'CN' in VA02 transaction and check.
    Configuration changes do not change your earlier sales order data.
    You always have option to selectively consider sales orders through BAdI implementation of MD_CHANGE_MRP_DATA method CHANGE_MDPSX_VBBE.
    Best Regards,
    Rajen

  • MRP includes delivered Sales order

    Hi Experts,
    I am using planning strategy 40. Here I am facing problem during the time of MRP.
    Sales order has been created & delivery is done. But when I run MRP of any FG related to Sales order it generates requirement of Delivered Sales order.
    My checking rule & checking group all are correct but still I m facing the same problem.
    Please help me & give me the solution ASAP.

    Hello
    This is probably a database inconsistency. Please check the following link that I have created on this subject, with instructions to correct it:
    http://wiki.sdn.sap.com/wiki/x/tQTNDw
    BR
    Caetano

  • MRP run for sales orders

    Dear Friends,
    I want to run MRP based on the sales order delivery schedules. My sales orders are spread for the next 2 years.
    For example for material A, I am having sales order for 40 quantity (item 10) and material B -20 quantity (item 20). My sales order delivery scedule is defined such away that each month I may required to send 4 items of material A and 2 items of material B starting from March 08.
    In this case I need not to consider all the quantity. I want to run my MRP for which I need to deliver for the next 3 months period.
    If you need any further clairification, please let me know.
    Regards,
    Surya.

    Dear Surya,
    Make sure that the scheduleline in the sales order are having 4 qty of A and 2 qty of B for each month as below
    Schedule line of A
    31.03.2008 - 4 qty
    31.04.2008 - 4 qty
    31.05.2008 - 4 qty
    Schedule line of B
    31.03.2008 - 2 qty
    31.04.2008 - 2 qty
    31.05.2008 - 2 qty
    Make sue that your planning horizon is only one month. and you are running MRP with NETPL option.
    This with consider the sales order line item schedulelisewise and give planned order only for one month.
    i hope u got it

  • MRP run for sales order -- Collective requierements. how to correct?

    Dear All,
    Upon creation off a sales order we entered a material for which the avalability check was set to 01 collective requierements. So when the MRP run finished it created collective requirements. This was not our intention and we changed the availability check to 02 but now the MRP run doesn't pick it up anymore and the requirements remain collective.
    Can we correct this in any way without recreating the sales order?
    Best regards,
    Michaë

    its a MTO strategy
    then
    maintain 1-  individual requirement in individual./collective requirement in   MRP 4 view for the material
    and rerun the MRP with planning mode 3( delete and recreate planning data)
    then all the dependent requirement will be planned based on the sale order
    Regards,
    Sundaresan

  • Preventing MRP run if Sales order is blocked

    Hi
    Relating to SAP note 744484. Is it possible to setup a similar outcome but with
    this dependant on the credit block.
    In other words we wish to prevent MRP generating a planned order once the credit
    block is active but allow planned orders to be generated once the block is removed. This is to cater for replenishment orders should losses occur.

    please check this link.
    <a href="http://sap-img.com/sap-sd/mrp-block.htm">MRP block</a>