MRP - Single Purchase requisition for multiple Items

Hi
We have recently introduced MRP module in SAP .In some specific scaeanrios , we want to create a single Purchase Requisition for multiple items .Standard SAP generate different Purchase requisition for each item
Is there any way out

Sandeep,
This topic has been covered numerous times in this forum and in the MM forum.  You evidently have not used the search feature.  There are thousands of posts in these forums, and the search function will be very helpful for you in future questions.
To answer your question, No, nothing is available to make standard SAP MRP create Purchase requisitions for multiple items.
Most companies address this issue during the conversion of Purchase Requisitions to Purchase orders.  During this process, you can add many items to a single purchase order.
Rgds,
DB49

Similar Messages

  • Is it possible to run single workflow instance for multiple item changed or created?

    I have created a SharePoint Designer 2010 approval workflow and I am starting this workflow on item created and modified . Now when I am adding and updating multiple items it is starting workflow for each item but I want to start only one workflow for all items.
    I think it is possible in workflow 2013 but i want to use in
    workflow 2010.
    Is this possible? if yes then how?

    Hi Resham,
    From your description, my understanding is that you want to only start a workflow instance when multiple items are added or updated.
    Per my knowledge, if we set workflow start on item created or modified, when we add or update multiple items, SharePoint will create a workflow instance for each item, it is unable to just create an instance for multiple items. It is same
    between SharePoint 2010 workflow and SharePoint 2013 workflow.
    You said it is possible in workflow 2013, do you have any references?
    Thanks,
    Wendy
    TechNet Community Support
    Please remember to mark the replies as answers if they help, and unmark the answers if they provide no help. If you have feedback for TechNet Support, contact
    [email protected]

  • Avoid  automatic creation of purchase requisition for bom item N

    Dear.
    When I create a production order , for the components  with bom item N the system create a purchase requisition. I need to avoid this automatic creation , do you know a solution to obtain this ?
    Thanks.

    For the many people that have asked this question.
    N item category in the BOM is always going to propose direct procurement. Through configuration I have not found a way to make it go away from the planned order. You can make it go away from the production order.
    The IMG path: 
    Plant Maintenance and Customer Service 
    -> Maintenance and Service Processing 
    --> Maintenance and Service Orders 
    ---> Functions and Settings for Order Types 
    ----> Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval
    Under the Res/PurRq -> Specify Never
    In order make this setting effective, you must define the following
    system message to error or warning, as it is stated on note 569984
    Version Appl.A. No. Cat
    00000000 C2 280 W
    Please note that this setting is effective for reservations and
    requisitions.
    The best solution is to use BOM item category L with the bulk indicator set. You will not get any direct procurement proposals or planned orders and you can use long term planning to see the time phased MRP results.

  • How to create production order for multiple items having common raw materia

    Dear all,
    We are running a sheet metal fabrication company at Vadodara Gujrat.
    Please guide us how to create single production order for multiple items using single raw material??
    For example, We want to produce baby shirt(item code AAA001), shirt with full sleeve(item code AAA002), shirt with half sleeve(item code AAA003),shirt slim fit (item code AAA004),shirt loose fit(item code AAA005) from single raw material say(item code XXX001).
    Right now we have to create 5 production order to produce above 5 items of single sales order  in SAP B1 though it is made from single raw material which is foolishness and time consuming too. (Please also note that to produce any finfish good item, raw material required for that item may vary every time in our process.)
    Kindly guide us how to solve the problem.
    Thanks.
    RUPESH  +91-9227744273
    WEB : www.gorasia.co.in

    Hi Rupesh Gorashiya,
    This is possible through MRP for that you have to put Sales Order first and Run MRP Wizard
    MRP Wizard Put Multi Production Order as per Item Taking in Sales Order just click it on and execute.
    Thanks,
    Srujal Patel

  • Single purchase requisition against multipile purchase requisition

    HI Guru:
    Is there any way to create single purchase requisition against multiple purchase requisition???
    In system we creating purchase requisition time to time and single type material but when we are going to place order that time we want to place order against single purchase requistion.
    Please suggest.
    Thanks.
    Virendra

    You can not create single req against the diff reqs but you can create single po against the multiple reqs
    Either you have to generate the single reqs or you have to combine all reqs in the PO
    Follow what dharma has mentioned in the mail is the easy solution.
    Other wise you have to develope the custom code to combine all the reqs and convert in the PO aginst one req.
    we have done in our site
    we have added custom code in ME59N where it is converting all reqs quantity in to on reqs and create PO against that req and updates all the reqs with PO number and the req number in to which the req is converted.
    this info we are updating in the line text of req

  • Combining multiple planned orders into single purchase requisition

    Hi Gurus,
    could anyone please tell me how to convert multiple planned orders generated during MRP run into a single purchase requisition? Also, is there any other way of getting single purchase requisition fcreated after MRP run for a procured item which is part of multiple BOMs?
    Thanks and regards,
    Abhik

    Hi,
    Conversion of Multiple planned order to single Purchase requisition is not possible.
    But you can have a single Pur.Req for Multiple requirements.
    You can do this by:
    1. Individual/collective indicator "2" collective requirements for the Header Material so that you will get your dependent requirements clubbed together.
    2. Period Lot sizing : Daily/weekly/monthly Lot size so that system will club the entire period requirements and propose a single lot.
    3. for low value materials you can have Reorder Point planning also.
    Hope this helps..
    Regards,
    Siva

  • Document type for MRP generated Purchase Requisition selection

    Hi,
    when I  run MRP ,for externlal procurement items system is creating Purchase Requisition with Document type NB.How to make system to take different Document type automatically with MRP.
    Thanks and Regards
    Raghavendra Pai

    Dear,
    Follow below steps to fullfill your requirements:
    1) Go to Tcode OMDT.
    2) Click on MRP group
    3) In front of your plant  maintain your  doc.type purchase requisitions for standard purchase ord which you want to generate at the time of MRP --PR generation.
    4) Go to Tcode MM02---maintain MRP group  same as above parameter in MRP-1 view .
    Now run MRP..it will pick the defaulted Document type for PR generation via MRP.
    Regards
    Utsav

  • MRP creating additional purchase requisitions for the existing sales order

    Hi,
    We have scenario where we switch materials from POD material to ARP material. POD material is just like make to procurement which creates purchase requisition and purchase order upon saving the sales order. ARP (Auto replenishment) material creates purchase requisition based on sales order and re-order point while running MRP.
    When the material is POD title, it created purchase requisition and purchase order (example: 4500000110) while saving the sales order (example: 1000000010) for the quantity 10. After some time this material is switched to ARP and it has open sales order (1000000010) and purchase order (4500000110).
    We have special MRP run for ARP materials based on MRP type, which creates purchase requisition.. What is happening is when we run MRP; it is creating new purchase requisition for the old sales order (1000000010) for the quantity 10. But old sales order (1000000010) is already having purchase order (4500000110) to fulfill. So we donu2019t want to create new purchase requisition for the old sales orders. It should create purchase requisition only for new sales orders.
    Please advise
    Thanks in advance
    Srinivas

    Mangesh,
    If the components are Inhouse production then you can think of using collective orders by assigning special procurement key 52. If raw material exists then your requirement cannot be met..as i think your scenario is of assembly processing. The idea of assembly processing is that component materials will always be available and only assembly will be done based on Sale Order.
    Regards,
    Prasobh

  • Multiple Document Types For Purchase Requisition For Different Order Types

    Dear SAP Gurus,
    I want to have different document types of Purchase Requisition for different Order types.
    For Example:
    for Order Type ZT01- Document Type used should be YR01
    for Order Type YA01- Document Type used should be ZR01
    How could this be achieved?
    Regards.

    hi
    Kindly check the user exit for the same
    COZF0001 or COZF0002
    regards
    thyagarajan

  • Creation Of A Single Purchase Requisition From Different Planned Orders

    Hi,
         After MRP run i get different Planned Orders for different raw materials . My requirement is that can i combine all the Planned Orders for diiferent materials into a single Purchase Requisition.This is a urgent requirement.
    If useful i will award points.
    Regards
    Jimmy

    Hi,
    it is not possible to combine with planned orders for different materials into single PR but differet PR can combine into a single Purchase Order.
    pls let me know any clarification.
    thanks
    mohan
    Message was edited by:
            Mohan Ramalingam

  • MRP Generating Purchase Reqs for Materials Needed in 2013

    Hi, all.  We're running MRP and it's generating a massive amount of purchase requisitions (18,310 to be exact).
    The following is a typical part setup:
    Lot size = EX
    Planned delivery time = 5 days
    GR processing time = 2 days
    Individual/collective requirements = 1
    MRP profile = BTO
    We have one existing sales order with a delivery date in 2014.
    With a lead time of roughly a week, why is MRP generating purchase requisitions out into 2013 for this material??
    Thanks!
    Sarah

    Sarah,
    MRP Profile doesn't mean much to us, they are all created individually during each implementation, and they are all different.  However, I will guess that BTO is some type of Make-to-order profile.
    You mention 18K of PRs.  Are these all being created in a single run, or is it possible that they may have been accumulating for a while?   To find out, run MRP, but using the parameter for Planning mode 'Delete and Recreate planning data'.  It will delete all the unfirmed PRs and then regenerate new ones based on the current situation.  I will assume for the moment that all these 'future' PRs are unfirmed, please let me know if they are not.
    Since it appears to be a MTO environment (if not, let me know) then you should be able to see in the planning segment which requirement (sales order) is driving the purchase reqs.  Depending on your MRP type, this could give you understanding of why MRP is proposing so many PRs.
    One thing that will generate a large number of purch reqs is an unrealistic value in Maximum Lot size (MRP1 page of material master).  For instance, for a requirement of 1000 widgets, and a max lot size of , say, 2, it would generate 500 PRs for 2 widgets each.
    If my suggestions don't help you, please specify MRP Type, Lot Size, max lot size, rounding value, Safety stock, reorder point, Strategy group,   From these values we can begin to understand your problem a little better.
    Rgds,
    DB49

  • Purchase requisitions for  raw materials

    Iam having multilevel BOM and when I do Sales order MRP then Iam getting planned order for Semi finished items but not getting Purchase requisitions for  raw materials.

    Hi,
    Planing File Entry :-
    The planning file is used to limit the scope of the planning run for the
    total planning run. For this purpose, all materials that have been
    assigned a valid MRP type are automatically entered in the planning
    file.
    System will check the Planing file entry only in the case of Total MRP (MD01) or Total MPS (MD40).
    While there is no need in the case of MD02,MD03,MD41,MD42,MD50.
    Now how this Planing File entry activates,
    - Once MRP is activated at Plant level (T.code OMDU)system automatically maintains entry in Planning file for all those materials which contains the Active MRP type.
    - So if materials which are created before this activation of MRP in that case you have to maintain this planing file entry manual.You can do this either by MD20 or by using Back Ground Jon OMD0.
    Regards,
    Dhaval

  • Problem in MRP generated purchase requisition.

    Hi Friends,
    We have run MRP via MD02 transaction for one material.
    MRP generated purchase requisition created.
    In that MRP generated purchase requisition, under item level in the status tab we are getting below field values is like below.
    Processing status : No edited
    Block ID: Blocked by requester.
    Due to above values we are not able to convert this MRP PR to PO.
    Could you please let us know is there any master setting is cause of this?
    Thanks in advance.
    Regards
    Jegen Mohan

    Hi Friends,
    After debugging MRP programme, we came to know that there is BADI implemented to block the MRP PR's intially and then z programme called for adding secondary materials/services to that MRP PR's.
    After addition of secondary materials/services to MRP PR's,  Status will be unblock automatically then save the PR.
    This is my client specific scenario.
    Thanks & Regards
    Mohan.

  • Single Purchase Order for different Plants of Different Company Codes

    Hi Experts,
    I have a scenario, My Client has 3 Company Codes (1000, 2000, 3000 )
    Company Code 1000 has 2-Plants    ( A001 and A002 )
    Company Code 2000 has 1-Plant      ( B001 )
    Comapny Code 3000 has  3-Plants   ( C001, C002, C003 )
    All these 3-Company codes has centralised purchase organisation.
    My Client requirement is to raise a single purchase order for external vendor, for all the plants A001, A002 which is in one company code and similarly in same Purchase Order for B001 plant which belongs to 2000 Company Code and Similarly for same purchase order for C001, C002, C003 plant which belongs to 3000 Company Code.
    1)Is it possible to raise a Single Purchase to External Vendor for plants of Different Company Codes ?
    2)Does it affect the accounting document ?
    3)How to inward and where to inward these goods ? with respect to plant wise ?
    Please Guide with Valuable inputs.
    Thanks in Advance
    Best Regards
    Javeed
    Best regards
    Javeed Ahamed

    1) How about Profit Centre ? We have Framed each Profit Centre with respect to Plant
    Why should there be a problem?
    2)In Case of Migo does we have to be careful and do stepwise MIGO with respect to different Plants ?
    of course people have to be careful when performing transactions.
    if you have multiple items in a PO then you can easily receive all items in one go. So people have to careful and need to check if they really received each of the PO items. Especially if people have authorization for many plants, then the user who is usually performing the receipts for plant A can easily post the receipts of plant B too.
    3) How to Process MIRO ? Can we process Partial MIRO"S with respect to Line-items of those particular Plants ?
    MIRO allows to post the invoice like it is send to you from your vendor. If it is just for a part of your PO then this is just a fact and MIRO allows to post this kind of invoices too.

  • Single Transfer Order for Multiple Handling Units

    I have been researchig the ability to create a single transfer order for multiple handling units.  My assumptions are if it can be done that:
    1) A transfer order can have a single source, so if the source document for the handling unit (delivery) is different, that means different transfer order
    2) A TO can have multiple materials (line items) with different destination bins and quantities per bin
    I looked at the configuration for TO Split, but it's not clear that this will handle my requirement.
    I also saw this http://aq33.com/material-management/Articles-005798.html and it also says that my requirement can't be meant.  I'm just checking before I tell my customer this cannot be done.

    Yes you are right, if Source document is different, you need to go with different TO.
    But you can choose the Handling unit split, while creating a TO itself. i.e., You can quantify the goods for each handling unit.
    Edited by: Ganesh M on Feb 29, 2012 6:20 AM