MRP Type V1 - Does it create Exception Message for "Reschedule-in"?

Hello Experts,
We are using MRP Type V1 (Which has the Manual Re-Order Planning + External Requirements). However we are facing and issue with the Rescheduling part. Scenario is as following:
Material ROP is - 5000
Open Pur Ord is - 5000 (due in 01 June'09) based on the Std Lead time of the Material
Stok on hand is - 0
At this point a Sales Order is entered for 1000 pcs
After MRP Run, we expect an Exception Message for the Purchase Order to have "Reschedule-in". But, instead, system creates a PReq for 1000 pcs and the required date is NOT the Sales Order required Date but based on the Std Lead Time of the Material.
I have set the Material Lead time - 60 Days
I have set the Reschedule horizon - 0 Days ( I even tried with different Days but NO use)
However, when I change the MRP Type to PD, system generates a "Reschedule-in" Exception Message for the Purchase Order.
How can I get the "Reschedule-in" Exception Message for the Purchase Order with the MRP Type V1?
Thanks for your help in Advance!

Anil,
Reorder point/External MRP performs net requirements calculation (within replenishment lead time).  If the existing firmed supply elements minus the existing requirements bring the projected stock below ROP, it will propose an order that will bring the projected stock back to reorder point.  The proposal will generally come at replenishment lead time.
In the normal business cycle, your sales order would confirm to lead time, and you now have a confirmed sales requirement at lead time, plus a new purchase req to bring the stock back to the reorder point.  The scenario you have described is working exactly as it is designed.  Consumption based MRP will not normally try to reschedule supply elements to match requirements inside of lead time.
Rescheduling horizon generally is counted from the end of lead time.  It won't help you here.
I guess if you insist on having a reschedule message, you could change your lead time to 0 days.  Not a wise move in my opinion.  You then have locked yourself in your choices of types of Sales order availability checks into one that ignores lead time.  You also have to find a way to let your buyers/planners know what the 'real' lead time is when they place their orders on the vendors.
I don't know why you are using a consumption-based planning type (reorder point).  It sounds like your business requirements are that you actually need to be using a demand-type planning method (eg, your supply elements are driven by your demand, not by a reorder point/desired stock level).  If PD works the way you want, why aren't you using it?
Regards,
DB49

Similar Messages

  • FM to create support message for custom process type other than 'SLFN'

    Hi All
    Is there any function module or BAPI which will create support message for the custom process type other than SLFN.
    BAPI_NOTIFICATION_CREATE is posting only for the process type 'SLFN'
    Thanks in advance
    Regards
    Ravi

    Any ideas?

  • Production scheduling profile for production order type 10 does not exist – SAP Message No.10085

    When i tried to make confirmation for Production Order through CO15 transaction , i receive the following error message “ Production scheduling profile for production order type 10 does not exist – SAP Message No.10085 “
    In Work Scheduling view, Production Scheduling Profile is maintained as per OPKP only.
    How to check whether production scheduling profile is maintained for relevant order type 10.
    To do this , i went to OPKP & KOT2_OPA transactions but i don’t know how to check. I guide me through with a screen shot.
    Also, pls explain about  “Order Type 10” and how it is linked with material and order execution.
    Looking for a detailed explanation with screen shots , since i am new to SAP.
    Thanks With Regards,
    Dinesh Kumar V.

    Hello Dinesh,
    Please check the order type dependent parameter in OPL8 here you will get the Substitute Scheduler
    Then go to OPCH and check valid production scheduling profile assign here as per OPKP to your production scheduler for your plant.
    Production order have Order category as 10  Process Order  40 in standard SAP you can check this in OPJH.
    Best Regards,
    R.Brahmankar

  • Exception message for PrdOrd and Planned order

    Hi Gurus,
    It possible based on prdord and planned ord we need to get the Exception message information. It's there any standard transaction code or any sqvi report?
    Note:
    Exception Message:
    10 - Reschedule in
    20 - cancel
    05 - Opening date in the past
    26 - Excess in individual segment
    Please find this information in MD04 (single order). i am looking for same time multple orders with exception message report.
    Thanks and regards,
    Deethya.B

    Hi
    You can use MD06 with refrence to you plant and MRP Controllers. Also you can define your own traffic lights so that based on these you get your exception messages.
    Hope this helps,
    Regards,
    Ravi

  • Exception Message for Lower Level

    Hi everyone...
    I get this message:
    "Exception Message for Lower Level"
    after of one MD02, for my FERT Material.
    This FERT material has 2 lower levels, for a couple HALBs material in the next level and other HALB material into the level 3.
    I don't get the requeriments for the HALBs materials, when I select the Order Report for the PlOrd.
    This 3 materials are produced since level 3 up to level 1 into the same plant, therefore I need to see the requeriment of the Level 3 to produce and then, use it for the Level 2 and till the Level 1., but I'm recieving  this message.
    Thanks in advance.
    OP

    Hi,
    Not quite understandable ur query
    can u re-phrase it, anyways
    as per my understanding
    u are not getting plan orders for (HALB'S)
    just check the stock for that HALB'S &
    just execute CS11, CS12 for that header material & check
    whether BOM is getting exploded or not (upto all levels)
    Regards
    kumar

  • Sold-To Party and Reported missing when doing Help - Create Support Message

    Sorry, I know this has been asked multiple times, but I'm missing something in the responses.  The responses I am finding either don't seem to apply to my situation, or aren't detailed enough to explain what I'm supposed to be doing.
    Solution Manager 7.0 EhP1 SAPKITL435.
    If we try to do a "Help - Create Support Message" from within our production Solution Manager system, the "Reported by" field is correct, but the Sold-To Party is blank.
    If we try to do a "Help - Create Support Message" from within our non-production Solution Manager system, both the "Reported by" and  Sold-To Party fields are blank.
    If we try to do a Help - Create Support Message" from another SAP system whose RFC is pointing to our non-production Solution Manager system, both the "Reported by" and  Sold-To Party fields are blank.
    I've looked at IB52, as well as the SPRO activities under "Partner Determination Procedure."  I think a big part of my problem is that they just don'e make sense to me yet, because I can't figure out what I should be changing.
    For example, IB52 looks to me like it only applies if you want to assign something to the same person all the time.  Am I missing something there, or is that an answer to a different question?
    I also can't figure out if I need to create something new in "Define Access Sequences," or modify something existing, and, if I modify, to what?
    Does anyone know where I could find specific instructions for setting this up?

    Hi Brenda,
    Regargind this issue, please check if Sold-To party is maintained for
    your system with IB52 in your solman system as the steps below:
    SOLUTION MANAGER system
    ->IB52
    ->select the system on left hand side
    ->click on 'goto' on top menu
    ->Select 'partner'
    ->Now maintain Sold-To party
    Also check below note:
    1165357    Sold-to-Party is not assigned to Service Desk messa
    As you said ou already assigned then i would request you to please check if you have assigned at the system level or not. Somtimes people define at top of the tree and also at system level. Please assign at system level and delete all other. Most of the times this is the issue Sold-to-party doesnt fill automatically.
    For reported by field:
    Please check the note: 824640: Customizing missing for Service Desk in Solution
    read this note carefull and this will help you fixing the reported by issue.
    Please, make sure you have applied the following corrections:
    1439191 Incident Create: Message Reporter or Processor is not saved
    1486132 Incident Create: Enhance search help of Reporter field
    1497700 Work center: Message details not updated after refresh
    After this if you still having issue you need to provide more details but i think this will fix the issue.
    Thanks
    Regards
    Vikram

  • MRP Type V1 does not consider Ext. req. Sales Order after MRP run

    Hi Buddies
    My client wants to use MRP Type V1 which should consider re-order point as well as external requirement (i.e. Sales Order) for net requirement calculation.However when i tried using V1 in material master and ran MD03 it only considered re-order point  and ignored Sales Order.Sales Order didnt even reflect in MD04.Moreover in OMDQ for V1 under additional ext req there is no Sales Order for selection.
    Please reply how i can have ext req sales order for MRP Type V1.
    Regards,
    Sachin Narvekar

    Hi
    MRP Type V1 creats the requirement when the need exceeds the Reorder Point, where as the MRP type VB creats the requirement when the stock qty goes below the reorder point.
    Regards

  • MRP Exception message for Excess production quantity

    Originally, there is a demand for a common item material A 1500
    One work order is opened for this grouped demand
    Grouped Demand: 1500
    Work Order QTy: 1500
    Due to a drop in demand, the demand fall to 1200
    At this time, will any MRP exception raise to suggest the order to reduce the scheduled quantity to 1200?
    If there is way to do so, what should I set to achieve this requirement?

    I just afraid additional demand would raise by setting this coverage.
    I tried to define a range of coverage profile in the system with min:0 target:0 and max:1
    I set a material to use this profile and run a MRP with my above case.
    But still No exception message was suggested for the case.
    Is there something I am missing out?
    Anyway, thanks you for your suggest.

  • MD07 - MRP: Why shows me materials without exception messages?

    Hi Everyone!
    I need MD07 to shows me only materials with exception messages. I have 700 materials with MRP and the materials without messages are messing my analysis. Is that possible?
    Thanks in advance!!
    Ignacio

    Venkadesh,
    Thank you very much for your answer. When I go to Plant Parameters there's no Exception Messages setting under any of the 6 sections (Environment, Master Data, Planned Orders Reporting, Planning Run or Performance).
    Could you please put some light on this I feel Alone in the Dark, je. I'm using R3 4.6C
    Thanks in advance.
    Ignacio

  • Exception message 30 & Reschedule date

    Hi All,
    This is about the exception message 30 which is displayed in MD04 and the rescheduling date.How is this date determined and what does the exception message signify. how the system determines this dates?Also, what is the criteria for this rescheduling date to be displayed in MD04?
    For Ex
    Material XYZ , MRP Type : PD, Lot size :Monthly,PIR is 100 for march, After MRP run I am getting reqmnt date is on 1st April. Reschedule dt is 02-March, Expn Msg is 30. Inhouse production is 1 day & GR time is 2 days.
    Please let me know how system arrives on 2 march as rescheduled date & what does it mean?
    Thanks and regards,
    Kundan Kumar

    Dear,
    Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
    The rescheduling horizon is always calculated from the MRP date.
    Please refer this link,
    [Exception message 30 |exception 30]
    Have you assigned a range of coverage profile to the material?
    Regards,
    R.Brahmankar

  • Report to get the Material with Exception message"10"  Rescheduling in

    Hello All
    We want to get the report to get the materials with exception message"10".We can get deatils from T code MD06,but it is restricted to MRP Controller/Vendor and we can get the details from Table "MDKP".Plese provide any report or T code to get the details of the exception message "10"
    Thanks
    Suresh kumar

    Hello
    You can use BAPI_MATERIAL_STOCK_REQ_LIST todata from MD04 or BAPI_MATERIAL_MRP_LIST to get data from MD05.
    BR
    Catano

  • STEPS TO create OSS message for sap

    hi
    we i need to k now how to create a oss message for sap
    pls suggest? the steps
    regards
    Arora

    Hi,
    1. go to service.sap.com
    2. Click SAP Support Portal
    3. you can see Help & Support tab (after HOME)
    4. click that
    5. In that tab you can see Report a Product Error
    If you have suitable rights you can post your OSS message from here.
    Regards,
    Omkar.

  • Mail dock icon does not create new message when a file is dragged onto it

    After installing Snow Leopard, dragging a file to the the Mail icon in the dock no longer creates a new message with the file attached. Mail is brought forward as the active application, just no new message window.
    This was the behavior in earlier versions of mail.
    Is there a preference, or any other change, that can be changed to allow drag-and-drop of a file to create a new message with an attachment?
    --James

    There are some issues with drag and drop. I was having the same issue with Mail with SL, but I didn't check after 10.6.1. However, I just installed a new hard drive, and migrated. Mail works for me, now.
    It didn't work with my 10.6 which had been upgraded with multiple builds in the beta. I assumed it was related to the other drag and drop issues. Now that I check it again, I don't think so.

  • New to SOAP - How to create SOAP message for the SOAP described

    Hi Friends,
    Im bit new to SOAP-JAVA interactions.
    I have an SOAP describing
    POST /abc/WebSrevices/MyService.asmx HTTP/1.1
    Host: 127.0.0.1
    Content-Type: text/xml; charset=utf-8
    Content-Length: length
    SOAPAction: "http://tempuri.org/BillingAddressValidation"
    <?xml version="1.0" encoding="utf-8"?>
    <soap:Envelope xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance"
    xmlns:xsd="http://www.w3.org/2001/XMLSchema"
    xmlns:soap="http://schemas.xmlsoap.org/soap/envelope/">
    <soap:Body>
    <BillingAddressValidation xmlns="http://tempuri.org/">
    <inXml>string</inXml>
    </BillingAddressValidation>
    </soap:Body>
    </soap:Envelope>
    My question is How can I construct an equivalent JAVA message using SAAJ
    I wrote like the following
    public void performSOAPReadWrite(String transaction){
    try{
    SOAPConnectionFactory scf = SOAPConnectionFactory. newInstance();
    SOAPConnection con = scf.createConnection();
    MessageFactory mf =
    MessageFactory.newInstance();
    SOAPMessage msg = mf.createMessage();
    SOAPPart sp = msg.getSOAPPart();
    SOAPEnvelope envelope = sp.getEnvelope();
    //Adding Content to the Header
    envelope.getHeader().detachNode();
    SOAPBody body = envelope.getBody();
    SOAPElement billingAddressValidation =
    body.addChildElement("BillingAddressValidation","http://tempuri.org/");
    SOAPElement inXml =
    billingAddressValidation.addChildElement("inXml");
    inXml.addTextNode(transaction);
    URL urlEndpoint = new URL(DEFAULT_SERVER);
    // 127.0.0.1/abc/WebSrevices/MyService.asmx
    System.out.println("Sending Message");
    SOAPMessage reply = con.call(msg,
    urlEndpoint);
    System.out.println("Reply is "+reply);
    }catch (Exception e) {
    e.printStackTrace();
    // TODO: handle exception
    Can any one let me know whats wrong in this ?
    Thanx in advance
    Im waiting for ur reply
    Mahesh Raja Vandyala
    Senior Analyst

    Hi,
    When im running the program I am getting a
    javax.xml.soap.SOAPException: Failed to send message:java.io.IOException: The server at http://127.0.0.1/abc/WebSrevices/MyService.asmx returned a 500 error code ( Internal Server Error )
    Please ensure that ur URL is correct and the Web service has deployed
    This is web service is provided by .net team and im required to take the services of that web service to retrieve some information provided by that.
    I can launch the webservice definition thru IE....their they have provide a text box with a Invoke button.
    The same data that im sending thru code if invoked thru IE is working fine.
    I suspect that the way Im construcint the SOP message is wrong.
    Any help in finding out the correctness of the Message in the java code ?
    Thanx
    Mahesh

  • Why does Labview create a .vi for each global variables?

    Hello,
    I wrote an Labview application which use several global variables (almost 30 variables). All the variables are of variable type "single process". For each of these variables, Labview creates a vi.
    For example, for the variable "_TS.Measures.channes", Labview creates a vi named "TS_'_TS.Measures.channels'.vi". Which means, I have almost 30 "name of variable".vi files: this is confusing!
    All my VI are inside library (.llb). When I try to put the VI of a global variable in a library, Labview can't find them anymore.
    May be can somebody explain me, why LabVIEW does create these VI and how is it possible to put them in a library.
    Cheers,
    Risotto

    Hi everybody,
    Thank you for your answers, I get a lot of informations.
    Yes, I use the new shared variables in LabVIEW8, which I am using like sort of global constants. Now I am understanding what guys are telling me all this about global variables in LabVIEW7.1. Sorry, I forgot to say I was using LabvVIEW8.
    I will have a look on the tutorial too.
    But yet one point about the library collecting all the shared variables in the windows explorer and in the project explorer: When I create a shared variable in my LabVIEW project - for example "test1" as double/single process - the variable doesn't appear in my file directory, but it appears in the project explorer in a library (.lvlib).
    When I drag/paste my shared variable on the block diagramm of my VI, then a file "Math_test1.vi" appears in my file directory. There is no extra .llb created to contain my shared variable vi.
    If I drag/paste the file "Math_test1.vi" in the Math.llb (see picture), then the file is moved in the llb and disapeared from the directory.
    If I created another shared variable "test2" as double/single process and put it on the VI, then LabVIEW creates2 files in the directory: "Math_test1.vi" and "Math_test2.vi". So that I get 2 vi for the "test1" variable now (one in the llb and one in the directory).
    I use several library in the project explorer. But the  library in the project explorer seems to create file with other extension (.lvlib) than the sdtandard LabVIEW library (.llb).
    Cheers,
    Risotto
    Attachments:
    picture.jpg ‏223 KB

Maybe you are looking for

  • Why is hotmail is not working with Firefox?

    I can log into hotmail then the "Messenger" tab just shows "loading". Whatever I click on nothing happens. If I go to Hotmail through Explorer everything works fine. How to I correct the problem through Firefox?

  • Adobe Connect not recognizing my DV camera

    Adobe Connect no longer will recognize my DV cameras (XL2 and GL2) via firewire 400 on a mac computer (os 10.7.5). I have tried signing in using the ?launcher=false  idea and I have installed the addin for adobe connect and os 10.7.2. Nothing works.

  • What is the best way to migrate PSE6 Catalog (Wxp) to new computer W7, PSE11?

    What is the best way to migrate PSE6 Catalog (Wxp) to new computer W7, PSE11?  Previous PSE6 recovery (Wxp) after a failed HD resulted in pictures showing but not opening due to connection issues.  Had to restore pictures from backup and rebuild the

  • How to use variable in topology

    Hi every one.. how to use variable in topology

  • Getting SYSTEM_ERROR when testing Integarted SOA Gateway setup

    Hi,     I followed all the documentation out there for setting-up Integrated SOA Gateway in EBiz R12.1.3 instance. Finally, when I am testing my setup using "Testing ISG installation using operation TESTUSERNAME in FND_USER_PACKAGE (Doc ID 1506065.1)